A. Rifai, Arief Rahman Alfithra, Chanif Faruq Al'adiat, W. P. Sari
{"title":"使用自动布局设计程序(ALDEP)方法进行热解装置生产的设施布局规划","authors":"A. Rifai, Arief Rahman Alfithra, Chanif Faruq Al'adiat, W. P. Sari","doi":"10.31315/opsi.v16i1.8745","DOIUrl":null,"url":null,"abstract":"One important factor to consider in increasing productivity in a company is the design of the facility layout. PT Hari Mukti Teknik is keen producing pyrolysis machine to contribute to addressing waste issue in Indonesia. Currently, the facility layout at the company is not suitable to produce pyrolizers as it was set up to produce industrial scale washing machines. To improve production efficiency, PT Hari Mukti Teknik needs facility layout that can be optimized for pyrolizers. The purpose of this study is to provide a layout design proposal for the pyrolysis machine manufacturing process to obtain an effective and efficient process. Here, we used ALDEP method to produce layouts based on consideration of the level of relationship between departments. There were 4 alternatives for the manufacturing and production and two alternative layouts for employee and office area. The design for new layout was selected based on the closeness relationship between the departments. An overall facility layout plan that is required for the production of pyrolysis machines is a building area the total of 1045 m² covering manufacturing, production, employee, office and parking space areas.","PeriodicalId":34167,"journal":{"name":"OPSI","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-06-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Facility Layout Planning for Pyrolyzer Production Using Automated Layouts Design Program (ALDEP) Method\",\"authors\":\"A. Rifai, Arief Rahman Alfithra, Chanif Faruq Al'adiat, W. P. Sari\",\"doi\":\"10.31315/opsi.v16i1.8745\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"One important factor to consider in increasing productivity in a company is the design of the facility layout. PT Hari Mukti Teknik is keen producing pyrolysis machine to contribute to addressing waste issue in Indonesia. Currently, the facility layout at the company is not suitable to produce pyrolizers as it was set up to produce industrial scale washing machines. To improve production efficiency, PT Hari Mukti Teknik needs facility layout that can be optimized for pyrolizers. The purpose of this study is to provide a layout design proposal for the pyrolysis machine manufacturing process to obtain an effective and efficient process. Here, we used ALDEP method to produce layouts based on consideration of the level of relationship between departments. There were 4 alternatives for the manufacturing and production and two alternative layouts for employee and office area. The design for new layout was selected based on the closeness relationship between the departments. An overall facility layout plan that is required for the production of pyrolysis machines is a building area the total of 1045 m² covering manufacturing, production, employee, office and parking space areas.\",\"PeriodicalId\":34167,\"journal\":{\"name\":\"OPSI\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-06-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"OPSI\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31315/opsi.v16i1.8745\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"OPSI","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31315/opsi.v16i1.8745","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
提高公司生产力的一个重要因素是设施布局的设计。PT Hari Mukti Teknik热衷于生产热解机,以帮助解决印度尼西亚的废物问题。目前,该公司的设施布局不适合生产热解器,因为它是为生产工业规模的洗衣机而设立的。为了提高生产效率,PT Hari Mukti Teknik需要能够针对热解器进行优化的设施布局。本研究的目的是为热解机制造工艺提供一个布局设计方案,以获得一个有效和高效的工艺。在这里,我们使用ALDEP方法在考虑部门之间关系级别的基础上生成布局。制造和生产有4种选择,员工和办公区有两种选择。新布局的设计是基于部门之间的紧密关系来选择的。热解机生产所需的总体设施布局规划为建筑面积总计1045 m²,包括制造区、生产区、员工区、办公区和停车区。
Facility Layout Planning for Pyrolyzer Production Using Automated Layouts Design Program (ALDEP) Method
One important factor to consider in increasing productivity in a company is the design of the facility layout. PT Hari Mukti Teknik is keen producing pyrolysis machine to contribute to addressing waste issue in Indonesia. Currently, the facility layout at the company is not suitable to produce pyrolizers as it was set up to produce industrial scale washing machines. To improve production efficiency, PT Hari Mukti Teknik needs facility layout that can be optimized for pyrolizers. The purpose of this study is to provide a layout design proposal for the pyrolysis machine manufacturing process to obtain an effective and efficient process. Here, we used ALDEP method to produce layouts based on consideration of the level of relationship between departments. There were 4 alternatives for the manufacturing and production and two alternative layouts for employee and office area. The design for new layout was selected based on the closeness relationship between the departments. An overall facility layout plan that is required for the production of pyrolysis machines is a building area the total of 1045 m² covering manufacturing, production, employee, office and parking space areas.