施工合同纠纷的有效管理策略

IF 2.1 Q2 CONSTRUCTION & BUILDING TECHNOLOGY
C. Amoah, Hlatshwayo Nkosazana
{"title":"施工合同纠纷的有效管理策略","authors":"C. Amoah, Hlatshwayo Nkosazana","doi":"10.1108/ijbpa-01-2022-0004","DOIUrl":null,"url":null,"abstract":"PurposeContract risk management has become a critical mission, as contract issues may lead to a loss of vast amounts of money to parties involved or cause project failure. This study sought to identify effective management strategies to mitigate construction contract issues that might emerge during construction.Design/methodology/approachA quantitative research approach was adopted for the study. Structured questionnaires made up of close-ended questions were distributed to construction professionals in South Africa via the SurveyMonkey platform. The data were then analysed using descriptive statistics.FindingsThe findings indicate that the critical sources of contract-related disputes are ambiguous definitions of the contract parties' scope of their rights and obligations, lack of precise arrangements regarding the calculation of contractual penalties for failure to meet the deadline, lack of detailed specification of the works and specific milestones, lack of provisions regulating changes to the project documentation during the construction stage, an excessive amount of contractual penalties on contractor's side and lack of provisions regarding the rules of performing additional and replacement works and their settlement. However, for these disputes to be effectively managed, strategies such as reduction uncertainties in project's phases, setting up contingency plans, construction guarantee, extension of time claims, payment guarantee, retention and escalation clause should be implemented by the parties involved.Research limitations/implicationsEven though the empirical study focused on construction professionals in South Africa, the findings could be applied to other countries outside of South Africa.Practical implicationsTo effectively manage and prevent contract disputes from averting project failures and losses to parties involved in the contract, construction professionals need to be aware of strategies that must be implemented before and during the project execution. If well implemented, these strategies will help a construction project be successful and experience fewer contractual disputes.Originality/valueThe study has identified the knowledge gap concerning suitable contract risk management strategies available for implementation to effectively prevent any contract parties from losing money, time and project failure.","PeriodicalId":44905,"journal":{"name":"International Journal of Building Pathology and Adaptation","volume":" ","pages":""},"PeriodicalIF":2.1000,"publicationDate":"2022-08-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Effective management strategies for construction contract disputes\",\"authors\":\"C. Amoah, Hlatshwayo Nkosazana\",\"doi\":\"10.1108/ijbpa-01-2022-0004\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"PurposeContract risk management has become a critical mission, as contract issues may lead to a loss of vast amounts of money to parties involved or cause project failure. This study sought to identify effective management strategies to mitigate construction contract issues that might emerge during construction.Design/methodology/approachA quantitative research approach was adopted for the study. Structured questionnaires made up of close-ended questions were distributed to construction professionals in South Africa via the SurveyMonkey platform. The data were then analysed using descriptive statistics.FindingsThe findings indicate that the critical sources of contract-related disputes are ambiguous definitions of the contract parties' scope of their rights and obligations, lack of precise arrangements regarding the calculation of contractual penalties for failure to meet the deadline, lack of detailed specification of the works and specific milestones, lack of provisions regulating changes to the project documentation during the construction stage, an excessive amount of contractual penalties on contractor's side and lack of provisions regarding the rules of performing additional and replacement works and their settlement. However, for these disputes to be effectively managed, strategies such as reduction uncertainties in project's phases, setting up contingency plans, construction guarantee, extension of time claims, payment guarantee, retention and escalation clause should be implemented by the parties involved.Research limitations/implicationsEven though the empirical study focused on construction professionals in South Africa, the findings could be applied to other countries outside of South Africa.Practical implicationsTo effectively manage and prevent contract disputes from averting project failures and losses to parties involved in the contract, construction professionals need to be aware of strategies that must be implemented before and during the project execution. If well implemented, these strategies will help a construction project be successful and experience fewer contractual disputes.Originality/valueThe study has identified the knowledge gap concerning suitable contract risk management strategies available for implementation to effectively prevent any contract parties from losing money, time and project failure.\",\"PeriodicalId\":44905,\"journal\":{\"name\":\"International Journal of Building Pathology and Adaptation\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":2.1000,\"publicationDate\":\"2022-08-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Building Pathology and Adaptation\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/ijbpa-01-2022-0004\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"CONSTRUCTION & BUILDING TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Building Pathology and Adaptation","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/ijbpa-01-2022-0004","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 2

摘要

目的合同风险管理已成为一项关键任务,因为合同问题可能导致相关方损失巨额资金或导致项目失败。本研究旨在确定有效的管理策略,以缓解施工过程中可能出现的施工合同问题。设计/方法/方法本研究采用了定量研究方法。由封闭式问题组成的结构化问卷通过SurveyMonkey平台分发给南非的建筑专业人员。然后使用描述性统计对数据进行分析。调查结果表明,与合同相关的争议的关键来源是对合同当事人的权利和义务范围的定义不明确,对未能在截止日期前完成合同处罚的计算缺乏准确的安排,缺乏对工程和具体里程碑的详细说明,缺乏规范施工阶段项目文件变更的规定,承包商方面的合同处罚金额过大,以及缺乏关于执行额外和替换工程及其结算规则的规定。然而,为了有效管理这些争议,相关各方应实施减少项目阶段不确定性、制定应急计划、施工担保、延期索赔、付款担保、保留和升级条款等策略。研究局限性/含义尽管实证研究的重点是南非的建筑专业人员,但研究结果可以应用于南非以外的其他国家。实际含义为了有效管理和防止合同纠纷避免项目失败和合同各方的损失,建筑专业人员需要意识到在项目执行之前和执行过程中必须实施的策略。如果实施得当,这些策略将有助于建筑项目取得成功,减少合同纠纷。独创性/价值该研究发现了可用于实施的适当合同风险管理策略方面的知识差距,以有效防止任何合同方损失金钱、时间和项目失败。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Effective management strategies for construction contract disputes
PurposeContract risk management has become a critical mission, as contract issues may lead to a loss of vast amounts of money to parties involved or cause project failure. This study sought to identify effective management strategies to mitigate construction contract issues that might emerge during construction.Design/methodology/approachA quantitative research approach was adopted for the study. Structured questionnaires made up of close-ended questions were distributed to construction professionals in South Africa via the SurveyMonkey platform. The data were then analysed using descriptive statistics.FindingsThe findings indicate that the critical sources of contract-related disputes are ambiguous definitions of the contract parties' scope of their rights and obligations, lack of precise arrangements regarding the calculation of contractual penalties for failure to meet the deadline, lack of detailed specification of the works and specific milestones, lack of provisions regulating changes to the project documentation during the construction stage, an excessive amount of contractual penalties on contractor's side and lack of provisions regarding the rules of performing additional and replacement works and their settlement. However, for these disputes to be effectively managed, strategies such as reduction uncertainties in project's phases, setting up contingency plans, construction guarantee, extension of time claims, payment guarantee, retention and escalation clause should be implemented by the parties involved.Research limitations/implicationsEven though the empirical study focused on construction professionals in South Africa, the findings could be applied to other countries outside of South Africa.Practical implicationsTo effectively manage and prevent contract disputes from averting project failures and losses to parties involved in the contract, construction professionals need to be aware of strategies that must be implemented before and during the project execution. If well implemented, these strategies will help a construction project be successful and experience fewer contractual disputes.Originality/valueThe study has identified the knowledge gap concerning suitable contract risk management strategies available for implementation to effectively prevent any contract parties from losing money, time and project failure.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
4.80
自引率
18.20%
发文量
76
期刊介绍: The International Journal of Building Pathology and Adaptation publishes findings on contemporary and original research towards sustaining, maintaining and managing existing buildings. The journal provides an interdisciplinary approach to the study of buildings, their performance and adaptation in order to develop appropriate technical and management solutions. This requires an holistic understanding of the complex interactions between the materials, components, occupants, design and environment, demanding the application and development of methodologies for diagnosis, prognosis and treatment in this multidisciplinary area. With rapid technological developments, a changing climate and more extreme weather, coupled with developing societal demands, the challenges to the professions responsible are complex and varied; solutions need to be rigorously researched and tested to navigate the dynamic context in which today''s buildings are to be sustained. Within this context, the scope and coverage of the journal incorporates the following indicative topics: • Behavioural and human responses • Building defects and prognosis • Building adaptation and retrofit • Building conservation and restoration • Building Information Modelling (BIM) • Building and planning regulations and legislation • Building technology • Conflict avoidance, management and disputes resolution • Digital information and communication technologies • Education and training • Environmental performance • Energy management • Health, safety and welfare issues • Healthy enclosures • Innovations and innovative technologies • Law and practice of dilapidation • Maintenance and refurbishment • Materials testing • Policy formulation and development • Project management • Resilience • Structural considerations • Surveying methodologies and techniques • Sustainability and climate change • Valuation and financial investment
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信