{"title":"忽略复杂的网络结构低估了大型项目的延迟","authors":"C. Ellinas, D. Avraam, C. Nicolaides","doi":"10.1088/2632-072X/accef0","DOIUrl":null,"url":null,"abstract":"Completing large-scale projects on time is a daunting challenge, partly due to the intricate network of dependencies between a project’s activities. To support this challenge, existing theory focuses on predicting whether a delay in completing a single activity is likely to spread and impact downstream activities. Using fine-grained information from 68 546 activities and 84 934 pairs, associated with the delivery of a $1.86Bn infrastructure project, we show that the core mechanism that underpins existing theory underestimates delay propagation. To elucidate the mechanisms that drive delay, we generated null models that destroyed the structural and temporal correlations of the original project activity network. By doing so, we argue that this underestimation is the result of neglecting endogenous structural features within the project’s activity network. Formulating a new mechanism that utilizes both temporal and structural features may help improve our capacity to predict how delays spread within projects.","PeriodicalId":53211,"journal":{"name":"Journal of Physics Complexity","volume":" ","pages":""},"PeriodicalIF":2.6000,"publicationDate":"2023-04-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Neglecting complex network structures underestimates delays in a large-capital project\",\"authors\":\"C. Ellinas, D. Avraam, C. Nicolaides\",\"doi\":\"10.1088/2632-072X/accef0\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Completing large-scale projects on time is a daunting challenge, partly due to the intricate network of dependencies between a project’s activities. To support this challenge, existing theory focuses on predicting whether a delay in completing a single activity is likely to spread and impact downstream activities. Using fine-grained information from 68 546 activities and 84 934 pairs, associated with the delivery of a $1.86Bn infrastructure project, we show that the core mechanism that underpins existing theory underestimates delay propagation. To elucidate the mechanisms that drive delay, we generated null models that destroyed the structural and temporal correlations of the original project activity network. By doing so, we argue that this underestimation is the result of neglecting endogenous structural features within the project’s activity network. Formulating a new mechanism that utilizes both temporal and structural features may help improve our capacity to predict how delays spread within projects.\",\"PeriodicalId\":53211,\"journal\":{\"name\":\"Journal of Physics Complexity\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":2.6000,\"publicationDate\":\"2023-04-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Physics Complexity\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1088/2632-072X/accef0\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"MATHEMATICS, INTERDISCIPLINARY APPLICATIONS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Physics Complexity","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1088/2632-072X/accef0","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"MATHEMATICS, INTERDISCIPLINARY APPLICATIONS","Score":null,"Total":0}
引用次数: 0

摘要

按时完成大型项目是一项艰巨的挑战,部分原因在于项目活动之间错综复杂的依赖关系网络。为了支持这一挑战,现有的理论侧重于预测完成单个活动的延迟是否可能蔓延并影响下游活动。使用来自68546个活动和84934对的细粒度信息,与18.6亿美元基础设施项目的交付相关,我们表明支撑现有理论的核心机制低估了延迟传播。为了阐明驱动延迟的机制,我们生成了零模型,该模型破坏了原始项目活动网络的结构和时间相关性。通过这样做,我们认为这种低估是忽视了项目活动网络内的内生结构特征的结果。制定一种利用时间和结构特征的新机制可能有助于提高我们预测延迟如何在项目中传播的能力。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Neglecting complex network structures underestimates delays in a large-capital project
Completing large-scale projects on time is a daunting challenge, partly due to the intricate network of dependencies between a project’s activities. To support this challenge, existing theory focuses on predicting whether a delay in completing a single activity is likely to spread and impact downstream activities. Using fine-grained information from 68 546 activities and 84 934 pairs, associated with the delivery of a $1.86Bn infrastructure project, we show that the core mechanism that underpins existing theory underestimates delay propagation. To elucidate the mechanisms that drive delay, we generated null models that destroyed the structural and temporal correlations of the original project activity network. By doing so, we argue that this underestimation is the result of neglecting endogenous structural features within the project’s activity network. Formulating a new mechanism that utilizes both temporal and structural features may help improve our capacity to predict how delays spread within projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Journal of Physics Complexity
Journal of Physics Complexity Computer Science-Information Systems
CiteScore
4.30
自引率
11.10%
发文量
45
审稿时长
14 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信