{"title":"具有批量可用性和优先约束的双组件产品多准则调度。","authors":"Zhenxin Wen, Shuguang Li","doi":"10.7717/peerj-cs.3093","DOIUrl":null,"url":null,"abstract":"<p><p>This article studies the multicriteria problems of scheduling a set of n products on a fabrication facility, focusing on batch availability and precedence constraints. Each product is composed of two distinct subassemblies: a common subassembly, shared across all products, and a unique subassembly unique to each product. The common subassemblies are processed together in batches, with each batch requiring an initial setup, while unique subassemblies are handled individually. The availability of a common subassembly is contingent upon the completion of its entire batch (<i>i.e</i>., batch availability), whereas a unique subassembly becomes available immediately after its processing. The product completion time is determined by the availability of both subassemblies. Strict (weak) precedence means that if a product precedes another, then the latter can start only after the former is completed (the latter cannot start earlier than the former). We propose O(n<sup>4</sup>)-time algorithms to simultaneously optimize makespan and maximum cost, as well as to lexicographically optimize two maximum costs and makespan under strict or weak precedence constraints.</p>","PeriodicalId":54224,"journal":{"name":"PeerJ Computer Science","volume":"11 ","pages":"e3093"},"PeriodicalIF":2.5000,"publicationDate":"2025-08-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://www.ncbi.nlm.nih.gov/pmc/articles/PMC12453827/pdf/","citationCount":"0","resultStr":"{\"title\":\"Multicriteria scheduling of two-subassembly products with batch availability and precedence constraints.\",\"authors\":\"Zhenxin Wen, Shuguang Li\",\"doi\":\"10.7717/peerj-cs.3093\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<p><p>This article studies the multicriteria problems of scheduling a set of n products on a fabrication facility, focusing on batch availability and precedence constraints. Each product is composed of two distinct subassemblies: a common subassembly, shared across all products, and a unique subassembly unique to each product. The common subassemblies are processed together in batches, with each batch requiring an initial setup, while unique subassemblies are handled individually. The availability of a common subassembly is contingent upon the completion of its entire batch (<i>i.e</i>., batch availability), whereas a unique subassembly becomes available immediately after its processing. The product completion time is determined by the availability of both subassemblies. Strict (weak) precedence means that if a product precedes another, then the latter can start only after the former is completed (the latter cannot start earlier than the former). We propose O(n<sup>4</sup>)-time algorithms to simultaneously optimize makespan and maximum cost, as well as to lexicographically optimize two maximum costs and makespan under strict or weak precedence constraints.</p>\",\"PeriodicalId\":54224,\"journal\":{\"name\":\"PeerJ Computer Science\",\"volume\":\"11 \",\"pages\":\"e3093\"},\"PeriodicalIF\":2.5000,\"publicationDate\":\"2025-08-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://www.ncbi.nlm.nih.gov/pmc/articles/PMC12453827/pdf/\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"PeerJ Computer Science\",\"FirstCategoryId\":\"94\",\"ListUrlMain\":\"https://doi.org/10.7717/peerj-cs.3093\",\"RegionNum\":4,\"RegionCategory\":\"计算机科学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"2025/1/1 0:00:00\",\"PubModel\":\"eCollection\",\"JCR\":\"Q2\",\"JCRName\":\"COMPUTER SCIENCE, ARTIFICIAL INTELLIGENCE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"PeerJ Computer Science","FirstCategoryId":"94","ListUrlMain":"https://doi.org/10.7717/peerj-cs.3093","RegionNum":4,"RegionCategory":"计算机科学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"2025/1/1 0:00:00","PubModel":"eCollection","JCR":"Q2","JCRName":"COMPUTER SCIENCE, ARTIFICIAL INTELLIGENCE","Score":null,"Total":0}
Multicriteria scheduling of two-subassembly products with batch availability and precedence constraints.
This article studies the multicriteria problems of scheduling a set of n products on a fabrication facility, focusing on batch availability and precedence constraints. Each product is composed of two distinct subassemblies: a common subassembly, shared across all products, and a unique subassembly unique to each product. The common subassemblies are processed together in batches, with each batch requiring an initial setup, while unique subassemblies are handled individually. The availability of a common subassembly is contingent upon the completion of its entire batch (i.e., batch availability), whereas a unique subassembly becomes available immediately after its processing. The product completion time is determined by the availability of both subassemblies. Strict (weak) precedence means that if a product precedes another, then the latter can start only after the former is completed (the latter cannot start earlier than the former). We propose O(n4)-time algorithms to simultaneously optimize makespan and maximum cost, as well as to lexicographically optimize two maximum costs and makespan under strict or weak precedence constraints.
期刊介绍:
PeerJ Computer Science is the new open access journal covering all subject areas in computer science, with the backing of a prestigious advisory board and more than 300 academic editors.