白鹤滩水电站层间剪切带切割地下大型厂房洞室稳定性实例研究

Lifang Zou, Guotao Meng, Jiayao Wu, Wei Fu, Weijiang Chu, Weiya Xu
{"title":"白鹤滩水电站层间剪切带切割地下大型厂房洞室稳定性实例研究","authors":"Lifang Zou,&nbsp;Guotao Meng,&nbsp;Jiayao Wu,&nbsp;Wei Fu,&nbsp;Weijiang Chu,&nbsp;Weiya Xu","doi":"10.1002/dug2.12094","DOIUrl":null,"url":null,"abstract":"<p>The big underground powerhouse cavern of the China Baihetan hydropower plant is 438 m long, 34 m wide, and 88.7 m high. It is cut by a weak interlayer shear zone and its high sidewall poses a huge stability problem. This paper reports our successful solution of this problem through numerical simulations and a replacement-tunnel scheme in the detailed design stage and close site monitoring in the excavation stage. Particularly, in the detail design stage, mechanical parameters of the shear zone were carefully determined through laboratory experiments and site tests. Then, deformation of the surrounding rocks and the shear zone under high in situ stress conditions was predicted using 3 Dimensional Distinct Element Code (3DEC). Subsequently, a replacement-tunnel scheme was proposed for the treatment on the shear zone to prevent severe unloading relaxation of surrounding rocks. In the construction period, excavation responses were closely monitored on deformations of surrounding rocks and the shear zone. The effect of local cracking in the replacement tunnels on sidewall stability was evaluated using the strength reduction method. These monitoring results were compared with the predicted numerical simulation in the detailed design stage. It is found that the shear zone greatly modified the deformation mode of the cavern surrounding rocks. Without any treatment, rock mass deformation on the downstream sidewall was larger than 125 mm and the shearing deformation of the shear zone was 60–70 mm. These preset replacement tunnels can reduce not only the unloading and relaxation of rock masses but also the maximum shearing deformation of the shear zone by 10–20 mm. The predictions by numerical simulation were in good agreement with the monitoring results. The proposed tunnel-replacement scheme can not only restrain the shear zone deformation but also enhance the safety of surrounding rocks and concrete tunnels. This design procedure offers a good reference for interaction between a big underground cavern and a weak layer zone in the future.</p>","PeriodicalId":100363,"journal":{"name":"Deep Underground Science and Engineering","volume":"4 2","pages":"305-315"},"PeriodicalIF":0.0000,"publicationDate":"2024-04-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://onlinelibrary.wiley.com/doi/epdf/10.1002/dug2.12094","citationCount":"0","resultStr":"{\"title\":\"A case study on the stability of a big underground powerhouse cavern cut by an interlayer shear zone in the China Baihetan hydropower plant\",\"authors\":\"Lifang Zou,&nbsp;Guotao Meng,&nbsp;Jiayao Wu,&nbsp;Wei Fu,&nbsp;Weijiang Chu,&nbsp;Weiya Xu\",\"doi\":\"10.1002/dug2.12094\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<p>The big underground powerhouse cavern of the China Baihetan hydropower plant is 438 m long, 34 m wide, and 88.7 m high. It is cut by a weak interlayer shear zone and its high sidewall poses a huge stability problem. This paper reports our successful solution of this problem through numerical simulations and a replacement-tunnel scheme in the detailed design stage and close site monitoring in the excavation stage. Particularly, in the detail design stage, mechanical parameters of the shear zone were carefully determined through laboratory experiments and site tests. Then, deformation of the surrounding rocks and the shear zone under high in situ stress conditions was predicted using 3 Dimensional Distinct Element Code (3DEC). Subsequently, a replacement-tunnel scheme was proposed for the treatment on the shear zone to prevent severe unloading relaxation of surrounding rocks. In the construction period, excavation responses were closely monitored on deformations of surrounding rocks and the shear zone. The effect of local cracking in the replacement tunnels on sidewall stability was evaluated using the strength reduction method. These monitoring results were compared with the predicted numerical simulation in the detailed design stage. It is found that the shear zone greatly modified the deformation mode of the cavern surrounding rocks. Without any treatment, rock mass deformation on the downstream sidewall was larger than 125 mm and the shearing deformation of the shear zone was 60–70 mm. These preset replacement tunnels can reduce not only the unloading and relaxation of rock masses but also the maximum shearing deformation of the shear zone by 10–20 mm. The predictions by numerical simulation were in good agreement with the monitoring results. The proposed tunnel-replacement scheme can not only restrain the shear zone deformation but also enhance the safety of surrounding rocks and concrete tunnels. This design procedure offers a good reference for interaction between a big underground cavern and a weak layer zone in the future.</p>\",\"PeriodicalId\":100363,\"journal\":{\"name\":\"Deep Underground Science and Engineering\",\"volume\":\"4 2\",\"pages\":\"305-315\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-04-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://onlinelibrary.wiley.com/doi/epdf/10.1002/dug2.12094\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Deep Underground Science and Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://onlinelibrary.wiley.com/doi/10.1002/dug2.12094\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Deep Underground Science and Engineering","FirstCategoryId":"1085","ListUrlMain":"https://onlinelibrary.wiley.com/doi/10.1002/dug2.12094","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

中国白鹤滩水电站地下大型厂房洞室长438米,宽34米,高88.7米。它被一个弱层间剪切带切割,其高侧壁带来了巨大的稳定性问题。本文通过数值模拟和详细设计阶段的换洞方案以及开挖阶段的现场监控,成功地解决了这一问题。特别是在详细设计阶段,通过室内试验和现场试验,仔细确定了剪切区的力学参数。然后,利用三维离散元程序(3DEC)对高地应力条件下围岩和剪切带的变形进行了预测。为防止围岩严重卸荷松弛,提出了对剪切区进行补洞处理的方案。在施工期间,密切监测了围岩变形和剪切带的开挖响应。采用强度折减法评价了替代隧道局部开裂对侧壁稳定性的影响。这些监测结果与详细设计阶段的预测数值模拟结果进行了比较。研究发现,剪切带极大地改变了洞室围岩的变形模式。未经处理,下游侧壁岩体变形大于125 mm,剪切带剪切变形为60 ~ 70 mm。这些预设替代隧道不仅可以使岩体卸荷松弛,而且可以使剪切带的最大剪切变形减小10 ~ 20 mm。数值模拟预测结果与监测结果吻合较好。所提出的隧道置换方案既能抑制剪切带变形,又能提高围岩和混凝土隧道的安全性。该设计方法为今后大型地下洞室与软弱层带的相互作用提供了很好的参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A case study on the stability of a big underground powerhouse cavern cut by an interlayer shear zone in the China Baihetan hydropower plant

The big underground powerhouse cavern of the China Baihetan hydropower plant is 438 m long, 34 m wide, and 88.7 m high. It is cut by a weak interlayer shear zone and its high sidewall poses a huge stability problem. This paper reports our successful solution of this problem through numerical simulations and a replacement-tunnel scheme in the detailed design stage and close site monitoring in the excavation stage. Particularly, in the detail design stage, mechanical parameters of the shear zone were carefully determined through laboratory experiments and site tests. Then, deformation of the surrounding rocks and the shear zone under high in situ stress conditions was predicted using 3 Dimensional Distinct Element Code (3DEC). Subsequently, a replacement-tunnel scheme was proposed for the treatment on the shear zone to prevent severe unloading relaxation of surrounding rocks. In the construction period, excavation responses were closely monitored on deformations of surrounding rocks and the shear zone. The effect of local cracking in the replacement tunnels on sidewall stability was evaluated using the strength reduction method. These monitoring results were compared with the predicted numerical simulation in the detailed design stage. It is found that the shear zone greatly modified the deformation mode of the cavern surrounding rocks. Without any treatment, rock mass deformation on the downstream sidewall was larger than 125 mm and the shearing deformation of the shear zone was 60–70 mm. These preset replacement tunnels can reduce not only the unloading and relaxation of rock masses but also the maximum shearing deformation of the shear zone by 10–20 mm. The predictions by numerical simulation were in good agreement with the monitoring results. The proposed tunnel-replacement scheme can not only restrain the shear zone deformation but also enhance the safety of surrounding rocks and concrete tunnels. This design procedure offers a good reference for interaction between a big underground cavern and a weak layer zone in the future.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
2.20
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信