隧道工程诱发桩筏地基土拱演变的实验研究

IF 4.9 2区 工程技术 Q1 ENGINEERING, CIVIL
{"title":"隧道工程诱发桩筏地基土拱演变的实验研究","authors":"","doi":"10.1016/j.trgeo.2024.101340","DOIUrl":null,"url":null,"abstract":"<div><p>The evolution and progressive failure of the tunneling-induced soil arching effect in pile-raft foundations are still unclear. A series of tunnel-shaped trapdoor tests in a pile−raft foundation were conducted to study the effects of the tunnel−pile distance and the load on the subgrade surface on the progressive failure of the tunneling-induced soil arching effect. PIV technology was used to measure the evolution of the deformation pattern and shear bands of foundation soil with increasing tunnel volume loss. The ground reaction curve (GRC) for the tunnels and the pile settlement were measured by using a load cell and LVDTs. The results revealed that the minimum tunnel pressure in the pile-raft foundation was greater than that in the greenfield foundation because of the lower soil arching effect. The GRC curve in the pile−raft foundation can be divided into three stages: initial arching, maximum arching, and the ultimate stage. The minimum soil arching ratio decreased with increasing tunnel−pile distance and surface load. In the pile-raft foundation, a triangular disturbed zone was observed above the tunnel crown in the initial stage and gradually developed upward within a rectangular zone as the tunnel volume loss increased. The width of the tunneling-disturbed area was larger than the tunnel diameter in the ultimate stage. As the tunnel−pile distance increased, the evolution pattern of the tunnel-induced loosened area changed from “triangular expanding expansion” to “equal settlement expansion”. The effects of the tunnel−pile distance and surface loads on the tunneling-induced failure mechanism of pile−raft foundations are also discussed in this study, which provides valuable guidance for underground engineering construction.</p></div>","PeriodicalId":56013,"journal":{"name":"Transportation Geotechnics","volume":null,"pages":null},"PeriodicalIF":4.9000,"publicationDate":"2024-08-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Experimental study on tunneling-induced soil arching evolution in pile-raft foundations\",\"authors\":\"\",\"doi\":\"10.1016/j.trgeo.2024.101340\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><p>The evolution and progressive failure of the tunneling-induced soil arching effect in pile-raft foundations are still unclear. A series of tunnel-shaped trapdoor tests in a pile−raft foundation were conducted to study the effects of the tunnel−pile distance and the load on the subgrade surface on the progressive failure of the tunneling-induced soil arching effect. PIV technology was used to measure the evolution of the deformation pattern and shear bands of foundation soil with increasing tunnel volume loss. The ground reaction curve (GRC) for the tunnels and the pile settlement were measured by using a load cell and LVDTs. The results revealed that the minimum tunnel pressure in the pile-raft foundation was greater than that in the greenfield foundation because of the lower soil arching effect. The GRC curve in the pile−raft foundation can be divided into three stages: initial arching, maximum arching, and the ultimate stage. The minimum soil arching ratio decreased with increasing tunnel−pile distance and surface load. In the pile-raft foundation, a triangular disturbed zone was observed above the tunnel crown in the initial stage and gradually developed upward within a rectangular zone as the tunnel volume loss increased. The width of the tunneling-disturbed area was larger than the tunnel diameter in the ultimate stage. As the tunnel−pile distance increased, the evolution pattern of the tunnel-induced loosened area changed from “triangular expanding expansion” to “equal settlement expansion”. The effects of the tunnel−pile distance and surface loads on the tunneling-induced failure mechanism of pile−raft foundations are also discussed in this study, which provides valuable guidance for underground engineering construction.</p></div>\",\"PeriodicalId\":56013,\"journal\":{\"name\":\"Transportation Geotechnics\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":4.9000,\"publicationDate\":\"2024-08-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Transportation Geotechnics\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/S2214391224001612\",\"RegionNum\":2,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Transportation Geotechnics","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S2214391224001612","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0

摘要

隧道诱发的土拱效应在桩筏地基中的演变和逐步破坏仍不清楚。为了研究隧道-桩间距和地基表面荷载对隧道诱导土拱起效应逐步破坏的影响,我们在桩-筏地基中进行了一系列隧道形活门试验。采用 PIV 技术测量了地基土随着隧道容积损失的增加而发生的变形模式和剪切带的演变。使用称重传感器和 LVDT 测量了隧道的地面反力曲线(GRC)和桩基沉降。结果表明,由于地基土的起拱效应较低,桩拉地基的最小隧道压力大于绿地地基。桩筏地基的 GRC 曲线可分为三个阶段:初始起拱、最大起拱和终极阶段。随着隧道-桩距和地表荷载的增加,最小土拱度减小。在桩-筏地基中,初始阶段在隧道顶部上方观察到一个三角形的扰动区,随着隧道容积损失的增加,扰动区逐渐在矩形区域内向上发展。在最终阶段,隧道扰动区的宽度大于隧道直径。随着隧道-桩距的增加,隧道诱导松动区的演变模式由 "三角形扩展 "变为 "等沉降扩展"。本研究还讨论了隧道桩距和地表荷载对隧道诱发桩-筏地基破坏机理的影响,为地下工程施工提供了有价值的指导。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Experimental study on tunneling-induced soil arching evolution in pile-raft foundations

The evolution and progressive failure of the tunneling-induced soil arching effect in pile-raft foundations are still unclear. A series of tunnel-shaped trapdoor tests in a pile−raft foundation were conducted to study the effects of the tunnel−pile distance and the load on the subgrade surface on the progressive failure of the tunneling-induced soil arching effect. PIV technology was used to measure the evolution of the deformation pattern and shear bands of foundation soil with increasing tunnel volume loss. The ground reaction curve (GRC) for the tunnels and the pile settlement were measured by using a load cell and LVDTs. The results revealed that the minimum tunnel pressure in the pile-raft foundation was greater than that in the greenfield foundation because of the lower soil arching effect. The GRC curve in the pile−raft foundation can be divided into three stages: initial arching, maximum arching, and the ultimate stage. The minimum soil arching ratio decreased with increasing tunnel−pile distance and surface load. In the pile-raft foundation, a triangular disturbed zone was observed above the tunnel crown in the initial stage and gradually developed upward within a rectangular zone as the tunnel volume loss increased. The width of the tunneling-disturbed area was larger than the tunnel diameter in the ultimate stage. As the tunnel−pile distance increased, the evolution pattern of the tunnel-induced loosened area changed from “triangular expanding expansion” to “equal settlement expansion”. The effects of the tunnel−pile distance and surface loads on the tunneling-induced failure mechanism of pile−raft foundations are also discussed in this study, which provides valuable guidance for underground engineering construction.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Transportation Geotechnics
Transportation Geotechnics Social Sciences-Transportation
CiteScore
8.10
自引率
11.30%
发文量
194
审稿时长
51 days
期刊介绍: Transportation Geotechnics is a journal dedicated to publishing high-quality, theoretical, and applied papers that cover all facets of geotechnics for transportation infrastructure such as roads, highways, railways, underground railways, airfields, and waterways. The journal places a special emphasis on case studies that present original work relevant to the sustainable construction of transportation infrastructure. The scope of topics it addresses includes the geotechnical properties of geomaterials for sustainable and rational design and construction, the behavior of compacted and stabilized geomaterials, the use of geosynthetics and reinforcement in constructed layers and interlayers, ground improvement and slope stability for transportation infrastructures, compaction technology and management, maintenance technology, the impact of climate, embankments for highways and high-speed trains, transition zones, dredging, underwater geotechnics for infrastructure purposes, and the modeling of multi-layered structures and supporting ground under dynamic and repeated loads.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信