{"title":"为新山-柔佛电气化双轨项目确定新山中央区 OCS 桅杆偏移量","authors":"Muhamad Syakir Kamis, Muhamad Faiz Abd Latif, Mimi Faisyalini Ramli, Reventheran Ganasan, Mohd Asran Shamsuddin, Mohd Eizzuddin Mahyeddin, Nadia Amena Iskandar","doi":"10.37934/araset.44.2.184198","DOIUrl":null,"url":null,"abstract":"The Gemas – Johor Bahru Electrified Double Track Project (GJBEDTP) is the most recent railway electrification. GJBEDTP runs from Gemas Railway Station to Johore Bahru (JB) Sentral. Since the JB Sentral station platform track is existing, it cannot achieve the minimal offset in the client's Statement of Needs (SON). The station canopy's acting load capacity is limited, so it cannot support the Overhead Line Equipment (OLE). Malaysia's standard offset value was 3.0 m, while the KTMB guideline's maximum offset value is 3.60 m and the minimum is 2.60 m. Thus, this research investigates the concrete mast offset that should be used when track separation is lower than standard. JB Sentral architecture data was collected to evaluate the mast offset. Sicat Master simulation and a cross-sectional diagram can be used to determine the proper minimum offset from the data collected. The results show that the mast at the centre of the two tracks can achieve clearances with the minimum offset of 1.80 m from the track centreline to the concrete mast face. These results also show that tangent track alignment allows a minimum offset of 1.80 m at a lower train speed.","PeriodicalId":506443,"journal":{"name":"Journal of Advanced Research in Applied Sciences and Engineering Technology","volume":"45 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-05-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Determination of OCS Mast Offset in Johore Bahru Sentral for Gemas-Johor Electrified Double Track Project\",\"authors\":\"Muhamad Syakir Kamis, Muhamad Faiz Abd Latif, Mimi Faisyalini Ramli, Reventheran Ganasan, Mohd Asran Shamsuddin, Mohd Eizzuddin Mahyeddin, Nadia Amena Iskandar\",\"doi\":\"10.37934/araset.44.2.184198\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Gemas – Johor Bahru Electrified Double Track Project (GJBEDTP) is the most recent railway electrification. GJBEDTP runs from Gemas Railway Station to Johore Bahru (JB) Sentral. Since the JB Sentral station platform track is existing, it cannot achieve the minimal offset in the client's Statement of Needs (SON). The station canopy's acting load capacity is limited, so it cannot support the Overhead Line Equipment (OLE). Malaysia's standard offset value was 3.0 m, while the KTMB guideline's maximum offset value is 3.60 m and the minimum is 2.60 m. Thus, this research investigates the concrete mast offset that should be used when track separation is lower than standard. JB Sentral architecture data was collected to evaluate the mast offset. Sicat Master simulation and a cross-sectional diagram can be used to determine the proper minimum offset from the data collected. The results show that the mast at the centre of the two tracks can achieve clearances with the minimum offset of 1.80 m from the track centreline to the concrete mast face. These results also show that tangent track alignment allows a minimum offset of 1.80 m at a lower train speed.\",\"PeriodicalId\":506443,\"journal\":{\"name\":\"Journal of Advanced Research in Applied Sciences and Engineering Technology\",\"volume\":\"45 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-05-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Advanced Research in Applied Sciences and Engineering Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.37934/araset.44.2.184198\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Research in Applied Sciences and Engineering Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.37934/araset.44.2.184198","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Determination of OCS Mast Offset in Johore Bahru Sentral for Gemas-Johor Electrified Double Track Project
The Gemas – Johor Bahru Electrified Double Track Project (GJBEDTP) is the most recent railway electrification. GJBEDTP runs from Gemas Railway Station to Johore Bahru (JB) Sentral. Since the JB Sentral station platform track is existing, it cannot achieve the minimal offset in the client's Statement of Needs (SON). The station canopy's acting load capacity is limited, so it cannot support the Overhead Line Equipment (OLE). Malaysia's standard offset value was 3.0 m, while the KTMB guideline's maximum offset value is 3.60 m and the minimum is 2.60 m. Thus, this research investigates the concrete mast offset that should be used when track separation is lower than standard. JB Sentral architecture data was collected to evaluate the mast offset. Sicat Master simulation and a cross-sectional diagram can be used to determine the proper minimum offset from the data collected. The results show that the mast at the centre of the two tracks can achieve clearances with the minimum offset of 1.80 m from the track centreline to the concrete mast face. These results also show that tangent track alignment allows a minimum offset of 1.80 m at a lower train speed.