{"title":"应用随机挣值法评估不稳定实施条件下办公楼建设的进展情况","authors":"T. Kasprowicz, Anna Starczyk-Kołbyk","doi":"10.24425/ace.2024.148906","DOIUrl":null,"url":null,"abstract":"The REVM method is a modernized option of classical EVM method. The new method has been developed for applying in unstable condition of works implementation. When the works can be accidentally disturbed and the impact of random disruption factors on course and results of works must be taken into consideration. Next, Randomized Budgeted Duration to Completion and Randomized Budgeted Cost to Completion that is duration and cost of works remaining to execution after each inspection, as well as the Randomized Budgeted Duration at Completion and Randomized Budgeted Cost at Completion that is duration and cost of all works of the project completion after the site inspection. Moreover, the risk of durations and costs overrun of works are evaluated. It is important that input data required for the REVM method are the similar and are measured in the same way as in typical control of advancement works. But results of the application consist new decision information. Control of the investment under deterministic conditions, without taking into account the risk of disruptions, resulted in a final deviation from the planned budget of over 7%, and from the planned completion of the investment by almost 12%. Without analysing the factor related to disruptions at the investment implementation stage, the material and financial schedule was completely outdated. On the other hand, when controlling the investment under risk conditions and introducing organizational and technological changes adequate to the inspection reports, the final deviation from the planned budget was less than 2%, and slightly more than 2% from the planned completion date. Researches confirm that the results received by using the REVM method well reflect real situation of works implementation.","PeriodicalId":45753,"journal":{"name":"Archives of Civil Engineering","volume":null,"pages":null},"PeriodicalIF":1.1000,"publicationDate":"2024-03-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Application of the Randomized Earned Value Method to assess the advancement of the construction of the office building under the unstable implementation conditions\",\"authors\":\"T. Kasprowicz, Anna Starczyk-Kołbyk\",\"doi\":\"10.24425/ace.2024.148906\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The REVM method is a modernized option of classical EVM method. The new method has been developed for applying in unstable condition of works implementation. When the works can be accidentally disturbed and the impact of random disruption factors on course and results of works must be taken into consideration. Next, Randomized Budgeted Duration to Completion and Randomized Budgeted Cost to Completion that is duration and cost of works remaining to execution after each inspection, as well as the Randomized Budgeted Duration at Completion and Randomized Budgeted Cost at Completion that is duration and cost of all works of the project completion after the site inspection. Moreover, the risk of durations and costs overrun of works are evaluated. It is important that input data required for the REVM method are the similar and are measured in the same way as in typical control of advancement works. But results of the application consist new decision information. Control of the investment under deterministic conditions, without taking into account the risk of disruptions, resulted in a final deviation from the planned budget of over 7%, and from the planned completion of the investment by almost 12%. Without analysing the factor related to disruptions at the investment implementation stage, the material and financial schedule was completely outdated. On the other hand, when controlling the investment under risk conditions and introducing organizational and technological changes adequate to the inspection reports, the final deviation from the planned budget was less than 2%, and slightly more than 2% from the planned completion date. Researches confirm that the results received by using the REVM method well reflect real situation of works implementation.\",\"PeriodicalId\":45753,\"journal\":{\"name\":\"Archives of Civil Engineering\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.1000,\"publicationDate\":\"2024-03-28\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Archives of Civil Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24425/ace.2024.148906\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Archives of Civil Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24425/ace.2024.148906","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
Application of the Randomized Earned Value Method to assess the advancement of the construction of the office building under the unstable implementation conditions
The REVM method is a modernized option of classical EVM method. The new method has been developed for applying in unstable condition of works implementation. When the works can be accidentally disturbed and the impact of random disruption factors on course and results of works must be taken into consideration. Next, Randomized Budgeted Duration to Completion and Randomized Budgeted Cost to Completion that is duration and cost of works remaining to execution after each inspection, as well as the Randomized Budgeted Duration at Completion and Randomized Budgeted Cost at Completion that is duration and cost of all works of the project completion after the site inspection. Moreover, the risk of durations and costs overrun of works are evaluated. It is important that input data required for the REVM method are the similar and are measured in the same way as in typical control of advancement works. But results of the application consist new decision information. Control of the investment under deterministic conditions, without taking into account the risk of disruptions, resulted in a final deviation from the planned budget of over 7%, and from the planned completion of the investment by almost 12%. Without analysing the factor related to disruptions at the investment implementation stage, the material and financial schedule was completely outdated. On the other hand, when controlling the investment under risk conditions and introducing organizational and technological changes adequate to the inspection reports, the final deviation from the planned budget was less than 2%, and slightly more than 2% from the planned completion date. Researches confirm that the results received by using the REVM method well reflect real situation of works implementation.
期刊介绍:
ARCHIVES OF CIVIL ENGINEERING publish original papers of the theoretical, experimental, numerical and practical nature in the fields of structural mechanics, soil mechanics and foundations engineering, concrete, metal, timber and composite polymer structures, hydrotechnical structures, roads, railways and bridges, building services, building physics, management in construction, production of construction materials, construction of civil engineering structures, education of civil engineers.