{"title":"Pelita Ilmu Insani 基金会建筑施工项目的时间管理","authors":"Manajemen Waktu, Pada Pekerjaan, Arsitektur Proyek, Pembangunan Gedung, Yayasan Pelita, Ilmu Insani, . Windi1, Ahmad Aguswin, Akhmad Akromusyuhada","doi":"10.37034/infeb.v6i1.801","DOIUrl":null,"url":null,"abstract":"The success or failure of a project can be influenced by the lack of planning of project activities, and the supervision carried out is ineffective and has an impact on the project running inefficiently. Then, it will result in delays and a decrease in the quality of work and have an impact on swelling the project budget. Project management is needed in order to manage projects starting from implementation to the end of a project. This research uses a case study on the Pelita Ilmu Foundation Building Construction Project, especially architectural work. This building is located on Jl. Rawa Kuda, Kp. Rawa Kuda RT/RW 004/002 Karangharum, Kedungwaringin District, Bekasi Regency, West Java 17540 [1]. The S curve is used to find out how long a project takes to complete. The aim of this research is to determine time efficiency in terms of the S Curve graph. The results of time management analysis using the S Curve on the graph showed that the realization of time delays was not in accordance with the plan.","PeriodicalId":242689,"journal":{"name":"Jurnal Informatika Ekonomi Bisnis","volume":"11 4","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-03-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Manajemen Waktu Pada Pekerjaan Arsitektur Proyek Pembangunan Gedung Yayasan Pelita Ilmu Insani\",\"authors\":\"Manajemen Waktu, Pada Pekerjaan, Arsitektur Proyek, Pembangunan Gedung, Yayasan Pelita, Ilmu Insani, . Windi1, Ahmad Aguswin, Akhmad Akromusyuhada\",\"doi\":\"10.37034/infeb.v6i1.801\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The success or failure of a project can be influenced by the lack of planning of project activities, and the supervision carried out is ineffective and has an impact on the project running inefficiently. Then, it will result in delays and a decrease in the quality of work and have an impact on swelling the project budget. Project management is needed in order to manage projects starting from implementation to the end of a project. This research uses a case study on the Pelita Ilmu Foundation Building Construction Project, especially architectural work. This building is located on Jl. Rawa Kuda, Kp. Rawa Kuda RT/RW 004/002 Karangharum, Kedungwaringin District, Bekasi Regency, West Java 17540 [1]. The S curve is used to find out how long a project takes to complete. The aim of this research is to determine time efficiency in terms of the S Curve graph. The results of time management analysis using the S Curve on the graph showed that the realization of time delays was not in accordance with the plan.\",\"PeriodicalId\":242689,\"journal\":{\"name\":\"Jurnal Informatika Ekonomi Bisnis\",\"volume\":\"11 4\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-03-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Informatika Ekonomi Bisnis\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.37034/infeb.v6i1.801\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Informatika Ekonomi Bisnis","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.37034/infeb.v6i1.801","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
一个项目的成败可能会受到项目活动缺乏规划的影响,而开展的监督工作效果不佳,又会影响项目的低效运行。这将导致工作延误和质量下降,并影响项目预算的膨胀。从项目实施到项目结束,都需要对项目进行管理。本研究以 Pelita Ilmu 基金会大楼建设项目(尤其是建筑工程)为案例进行研究。该建筑位于 Jl.Rawa Kuda RT/RW 004/002 Karangharum, Kedungwaringin District, Bekasi Regency, West Java 17540 [1]。S 曲线用于确定一个项目完成所需的时间。本研究的目的是根据 S 曲线图确定时间效率。使用 S 曲线图进行时间管理分析的结果表明,时间延误的实现与计划不符。
Manajemen Waktu Pada Pekerjaan Arsitektur Proyek Pembangunan Gedung Yayasan Pelita Ilmu Insani
The success or failure of a project can be influenced by the lack of planning of project activities, and the supervision carried out is ineffective and has an impact on the project running inefficiently. Then, it will result in delays and a decrease in the quality of work and have an impact on swelling the project budget. Project management is needed in order to manage projects starting from implementation to the end of a project. This research uses a case study on the Pelita Ilmu Foundation Building Construction Project, especially architectural work. This building is located on Jl. Rawa Kuda, Kp. Rawa Kuda RT/RW 004/002 Karangharum, Kedungwaringin District, Bekasi Regency, West Java 17540 [1]. The S curve is used to find out how long a project takes to complete. The aim of this research is to determine time efficiency in terms of the S Curve graph. The results of time management analysis using the S Curve on the graph showed that the realization of time delays was not in accordance with the plan.