{"title":"模拟 COVID-19 大流行期间跨境建筑物流和供应链质量保证的关键挑战","authors":"Frank Ato Ghansah, Weisheng Lu, Benjamin Kwaku Ababio","doi":"10.1108/ecam-01-2024-0016","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>The COVID-19 pandemic has impacted the construction industry, yet still, it is unclear from existing studies about the critical challenges imposed on quality assurance (QA), particularly Cross-border Construction Logistics and Supply Chain (Cb-CLSC). Thus, this study aims to identify and examine the critical challenges of QA of Cb-CLSC during the COVID-19 pandemic.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>The aim is achieved via an embedded mixed-method approach pragmatically involving a desk literature review and engaging 150 experts across the globe using expert surveys, and results confirmed by semi-structured interviews. The approach is based on Interpretive Structural Modelling (ISM) as its foundation.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>The study revealed ten critical challenges of QA, with the top four including “the shortage of raw construction material (C7)”, “design changes (C6)”, “collaboration and communication difficulties (C1)” and “changes in work practices (C10)”. However, examining the interrelationships among the critical challenges using ISM confirmed C7 and C10 as the most critical challenges. The study again revealed that the critical challenges are sensitive and capable of affecting themselves due to the nature of their interrelationship based on MICMAC analysis. Hence, being consistent with why all the challenges were considered critical amid the pandemic. Sentiment analysis revealed that the critical challenges have not been entirely negative but also positive by creating three areas of opportunities for improvement: technology adoption, worker management, and work process management. However, four areas of challenges in the QA include cost, raw material, time, and work process, including inspection, testing, auditing, communication, etc.</p><!--/ Abstract__block -->\n<h3>Practical implications</h3>\n<p>The finding provides a convenient point of reference to researchers, policymakers, practitioners, and decision-makers on formulating policies to enhance the effectiveness of construction QA during the pandemic through to the post-pandemic era.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>The study enriches the extant literature on QA, Cb-CLSC, and the COVID-19 pandemic in the construction industry by identifying the critical challenges and examining the interrelationships among them. This provides a better understanding of how the construction QA has been affected by the pandemic and the opportunities created.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":"91 1","pages":""},"PeriodicalIF":3.6000,"publicationDate":"2024-03-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Modelling the critical challenges of quality assurance of cross-border construction logistics and supply chain during the COVID-19 pandemic\",\"authors\":\"Frank Ato Ghansah, Weisheng Lu, Benjamin Kwaku Ababio\",\"doi\":\"10.1108/ecam-01-2024-0016\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<h3>Purpose</h3>\\n<p>The COVID-19 pandemic has impacted the construction industry, yet still, it is unclear from existing studies about the critical challenges imposed on quality assurance (QA), particularly Cross-border Construction Logistics and Supply Chain (Cb-CLSC). Thus, this study aims to identify and examine the critical challenges of QA of Cb-CLSC during the COVID-19 pandemic.</p><!--/ Abstract__block -->\\n<h3>Design/methodology/approach</h3>\\n<p>The aim is achieved via an embedded mixed-method approach pragmatically involving a desk literature review and engaging 150 experts across the globe using expert surveys, and results confirmed by semi-structured interviews. The approach is based on Interpretive Structural Modelling (ISM) as its foundation.</p><!--/ Abstract__block -->\\n<h3>Findings</h3>\\n<p>The study revealed ten critical challenges of QA, with the top four including “the shortage of raw construction material (C7)”, “design changes (C6)”, “collaboration and communication difficulties (C1)” and “changes in work practices (C10)”. However, examining the interrelationships among the critical challenges using ISM confirmed C7 and C10 as the most critical challenges. The study again revealed that the critical challenges are sensitive and capable of affecting themselves due to the nature of their interrelationship based on MICMAC analysis. Hence, being consistent with why all the challenges were considered critical amid the pandemic. Sentiment analysis revealed that the critical challenges have not been entirely negative but also positive by creating three areas of opportunities for improvement: technology adoption, worker management, and work process management. However, four areas of challenges in the QA include cost, raw material, time, and work process, including inspection, testing, auditing, communication, etc.</p><!--/ Abstract__block -->\\n<h3>Practical implications</h3>\\n<p>The finding provides a convenient point of reference to researchers, policymakers, practitioners, and decision-makers on formulating policies to enhance the effectiveness of construction QA during the pandemic through to the post-pandemic era.</p><!--/ Abstract__block -->\\n<h3>Originality/value</h3>\\n<p>The study enriches the extant literature on QA, Cb-CLSC, and the COVID-19 pandemic in the construction industry by identifying the critical challenges and examining the interrelationships among them. This provides a better understanding of how the construction QA has been affected by the pandemic and the opportunities created.</p><!--/ Abstract__block -->\",\"PeriodicalId\":11888,\"journal\":{\"name\":\"Engineering, Construction and Architectural Management\",\"volume\":\"91 1\",\"pages\":\"\"},\"PeriodicalIF\":3.6000,\"publicationDate\":\"2024-03-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering, Construction and Architectural Management\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.1108/ecam-01-2024-0016\",\"RegionNum\":2,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-01-2024-0016","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
Modelling the critical challenges of quality assurance of cross-border construction logistics and supply chain during the COVID-19 pandemic
Purpose
The COVID-19 pandemic has impacted the construction industry, yet still, it is unclear from existing studies about the critical challenges imposed on quality assurance (QA), particularly Cross-border Construction Logistics and Supply Chain (Cb-CLSC). Thus, this study aims to identify and examine the critical challenges of QA of Cb-CLSC during the COVID-19 pandemic.
Design/methodology/approach
The aim is achieved via an embedded mixed-method approach pragmatically involving a desk literature review and engaging 150 experts across the globe using expert surveys, and results confirmed by semi-structured interviews. The approach is based on Interpretive Structural Modelling (ISM) as its foundation.
Findings
The study revealed ten critical challenges of QA, with the top four including “the shortage of raw construction material (C7)”, “design changes (C6)”, “collaboration and communication difficulties (C1)” and “changes in work practices (C10)”. However, examining the interrelationships among the critical challenges using ISM confirmed C7 and C10 as the most critical challenges. The study again revealed that the critical challenges are sensitive and capable of affecting themselves due to the nature of their interrelationship based on MICMAC analysis. Hence, being consistent with why all the challenges were considered critical amid the pandemic. Sentiment analysis revealed that the critical challenges have not been entirely negative but also positive by creating three areas of opportunities for improvement: technology adoption, worker management, and work process management. However, four areas of challenges in the QA include cost, raw material, time, and work process, including inspection, testing, auditing, communication, etc.
Practical implications
The finding provides a convenient point of reference to researchers, policymakers, practitioners, and decision-makers on formulating policies to enhance the effectiveness of construction QA during the pandemic through to the post-pandemic era.
Originality/value
The study enriches the extant literature on QA, Cb-CLSC, and the COVID-19 pandemic in the construction industry by identifying the critical challenges and examining the interrelationships among them. This provides a better understanding of how the construction QA has been affected by the pandemic and the opportunities created.
期刊介绍:
ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process.
ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.