Hyeon-Ki Kim, Sang-Hwa Shin, Chang-Sig Kong, Chang-Lak Kim
{"title":"科里 1 号机组蒸汽发生器拆除过程中工人辐射暴露评估","authors":"Hyeon-Ki Kim, Sang-Hwa Shin, Chang-Sig Kong, Chang-Lak Kim","doi":"10.1155/2024/4230293","DOIUrl":null,"url":null,"abstract":"Kori Unit 1 was permanently shut down on June 18, 2017. Since then, Korea is actively preparing for the decommissioning of the nuclear power plant. Because decommissioning work is performed in a radioactive environment, worker radiation exposure is a significant consideration. In this study, worker radiation exposure is evaluated during the steam generator, one of the heavy components of nuclear power plant, dismantling process. A radiation evaluation for the dismantling process is performed using the code RESRAD-BUILD. A steam generator dismantling scenario and optimal cutting method are designed to evaluate worker radiation exposure, considering pipe dimensions, cutting tool speed, and experience in steam generator replacement. The evaluation results are derived for each work type and year. As a result of the evaluation, worker radiation exposure is 7.5 man-mSv at the year of planned decommissioning.","PeriodicalId":21629,"journal":{"name":"Science and Technology of Nuclear Installations","volume":"10 1","pages":""},"PeriodicalIF":1.0000,"publicationDate":"2024-01-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Evaluation of Worker Radiation Exposure during the Kori Unit 1 Steam Generator Dismantling Process\",\"authors\":\"Hyeon-Ki Kim, Sang-Hwa Shin, Chang-Sig Kong, Chang-Lak Kim\",\"doi\":\"10.1155/2024/4230293\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Kori Unit 1 was permanently shut down on June 18, 2017. Since then, Korea is actively preparing for the decommissioning of the nuclear power plant. Because decommissioning work is performed in a radioactive environment, worker radiation exposure is a significant consideration. In this study, worker radiation exposure is evaluated during the steam generator, one of the heavy components of nuclear power plant, dismantling process. A radiation evaluation for the dismantling process is performed using the code RESRAD-BUILD. A steam generator dismantling scenario and optimal cutting method are designed to evaluate worker radiation exposure, considering pipe dimensions, cutting tool speed, and experience in steam generator replacement. The evaluation results are derived for each work type and year. As a result of the evaluation, worker radiation exposure is 7.5 man-mSv at the year of planned decommissioning.\",\"PeriodicalId\":21629,\"journal\":{\"name\":\"Science and Technology of Nuclear Installations\",\"volume\":\"10 1\",\"pages\":\"\"},\"PeriodicalIF\":1.0000,\"publicationDate\":\"2024-01-30\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Science and Technology of Nuclear Installations\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.1155/2024/4230293\",\"RegionNum\":4,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"NUCLEAR SCIENCE & TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Science and Technology of Nuclear Installations","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1155/2024/4230293","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"NUCLEAR SCIENCE & TECHNOLOGY","Score":null,"Total":0}
Evaluation of Worker Radiation Exposure during the Kori Unit 1 Steam Generator Dismantling Process
Kori Unit 1 was permanently shut down on June 18, 2017. Since then, Korea is actively preparing for the decommissioning of the nuclear power plant. Because decommissioning work is performed in a radioactive environment, worker radiation exposure is a significant consideration. In this study, worker radiation exposure is evaluated during the steam generator, one of the heavy components of nuclear power plant, dismantling process. A radiation evaluation for the dismantling process is performed using the code RESRAD-BUILD. A steam generator dismantling scenario and optimal cutting method are designed to evaluate worker radiation exposure, considering pipe dimensions, cutting tool speed, and experience in steam generator replacement. The evaluation results are derived for each work type and year. As a result of the evaluation, worker radiation exposure is 7.5 man-mSv at the year of planned decommissioning.
期刊介绍:
Science and Technology of Nuclear Installations is an international scientific journal that aims to make available knowledge on issues related to the nuclear industry and to promote development in the area of nuclear sciences and technologies. The endeavor associated with the establishment and the growth of the journal is expected to lend support to the renaissance of nuclear technology in the world and especially in those countries where nuclear programs have not yet been developed.