南岸广场开发项目:隧道运动预测和监测性能

Stuart Hardy, Anton Pillai, Xiangbo Qui, Duncan Nicholson
{"title":"南岸广场开发项目:隧道运动预测和监测性能","authors":"Stuart Hardy, Anton Pillai, Xiangbo Qui, Duncan Nicholson","doi":"10.1680/jgeen.23.00173","DOIUrl":null,"url":null,"abstract":"The Southbank Place project comprised the redevelopment of the UK headquarters of the Shell company (formerly known as the Shell Centre) in the Waterloo area of London. The project included demolition of all structures within the site except for the iconic tower building, the local extension of the existing basement and the construction of eight new mixed-use buildings. London Underground's (LU) Bakerloo and Northern Line running tunnels pass beneath the site. The excavation of the basement and construction of the Shell Centre in the late 1950s caused movements of the underlying Bakerloo Line tunnels that were much larger than expected. The monitoring of these tunnels between 1958 and 1995 has provided a classic case history for the behaviour of London Clay. The proposed redevelopment offered an opportunity to analyse and monitor the behaviour of London Underground tunnels over a period of 60 years and two phases of significant construction. The paper presents the back analysis of the historical monitoring of the Bakerloo Line tunnels and the calibration of a sophisticated finite element model. The model was subsequently used to predict the impact of the redevelopment on the tunnels as part of the assurance procedure with LU.","PeriodicalId":509438,"journal":{"name":"Proceedings of the Institution of Civil Engineers - Geotechnical Engineering","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2024-01-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The Southbank Place development: tunnel movement predictions and monitoring performance\",\"authors\":\"Stuart Hardy, Anton Pillai, Xiangbo Qui, Duncan Nicholson\",\"doi\":\"10.1680/jgeen.23.00173\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Southbank Place project comprised the redevelopment of the UK headquarters of the Shell company (formerly known as the Shell Centre) in the Waterloo area of London. The project included demolition of all structures within the site except for the iconic tower building, the local extension of the existing basement and the construction of eight new mixed-use buildings. London Underground's (LU) Bakerloo and Northern Line running tunnels pass beneath the site. The excavation of the basement and construction of the Shell Centre in the late 1950s caused movements of the underlying Bakerloo Line tunnels that were much larger than expected. The monitoring of these tunnels between 1958 and 1995 has provided a classic case history for the behaviour of London Clay. The proposed redevelopment offered an opportunity to analyse and monitor the behaviour of London Underground tunnels over a period of 60 years and two phases of significant construction. The paper presents the back analysis of the historical monitoring of the Bakerloo Line tunnels and the calibration of a sophisticated finite element model. The model was subsequently used to predict the impact of the redevelopment on the tunnels as part of the assurance procedure with LU.\",\"PeriodicalId\":509438,\"journal\":{\"name\":\"Proceedings of the Institution of Civil Engineers - Geotechnical Engineering\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2024-01-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the Institution of Civil Engineers - Geotechnical Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1680/jgeen.23.00173\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the Institution of Civil Engineers - Geotechnical Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jgeen.23.00173","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

南岸广场项目包括对位于伦敦滑铁卢地区的壳牌公司英国总部(前身为壳牌中心)的重建。该项目包括拆除场地内除标志性塔楼以外的所有建筑,对现有地下室进行局部扩建,并新建八栋多功能建筑。伦敦地铁(LU)的贝克鲁线和北线运行隧道从地块下方穿过。20 世纪 50 年代末,地下室的挖掘和壳牌中心的建设导致地下贝克鲁线隧道的移动比预期的要大得多。1958 年至 1995 年期间对这些隧道的监测为伦敦粘土的行为提供了经典案例。拟议中的重建项目为分析和监测伦敦地铁隧道在 60 年间和两个重要施工阶段的行为提供了机会。本文介绍了对贝克鲁线隧道历史监测的回溯分析以及复杂有限元模型的校准。该模型随后被用于预测重建对隧道的影响,作为与 LU 保证程序的一部分。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
The Southbank Place development: tunnel movement predictions and monitoring performance
The Southbank Place project comprised the redevelopment of the UK headquarters of the Shell company (formerly known as the Shell Centre) in the Waterloo area of London. The project included demolition of all structures within the site except for the iconic tower building, the local extension of the existing basement and the construction of eight new mixed-use buildings. London Underground's (LU) Bakerloo and Northern Line running tunnels pass beneath the site. The excavation of the basement and construction of the Shell Centre in the late 1950s caused movements of the underlying Bakerloo Line tunnels that were much larger than expected. The monitoring of these tunnels between 1958 and 1995 has provided a classic case history for the behaviour of London Clay. The proposed redevelopment offered an opportunity to analyse and monitor the behaviour of London Underground tunnels over a period of 60 years and two phases of significant construction. The paper presents the back analysis of the historical monitoring of the Bakerloo Line tunnels and the calibration of a sophisticated finite element model. The model was subsequently used to predict the impact of the redevelopment on the tunnels as part of the assurance procedure with LU.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信