使用 cpm 和 pert 方法对巴伦邦 dexa medica 仓库建设中的时间安排进行分析

Lega Reskita Lubis, Zuul Fitriana Umari, Kristi Kristi, Akhirini Akhirini
{"title":"使用 cpm 和 pert 方法对巴伦邦 dexa medica 仓库建设中的时间安排进行分析","authors":"Lega Reskita Lubis, Zuul Fitriana Umari, Kristi Kristi, Akhirini Akhirini","doi":"10.52333/lateral.v1i2.314","DOIUrl":null,"url":null,"abstract":"The project is a series of sensitive work mechanisms because each aspect of the project is interconnected with each other. The purpose of this research is to determine the planned duration, critical path activities, and probability in the implementation of the Dexa Medica warehouse construction project in Palembang. Primary data used for estimation of work time, while secondary data used time schedules (S-curve) and work plan drawings. The methods used are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). The planned project completion duration using the CPM calculation method is 39 weeks. The activities known to be on the critical path are preparation, earthworks and others on the 1st floor, concrete work on the 1st floor, architectural work on the 1st floor, site development, and genset room work. The planned project completion duration using the PERT calculation method is 40.2 weeks. The probability (Probabiliti) with the PERT method is found to be 0.7324, meaning that there is a 73.24% probability that the project will be completed within 41 weeks.","PeriodicalId":126911,"journal":{"name":"Jurnal Teknik Sipil LATERAL","volume":"152 ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-11-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALISIS PENJADWALAN WAKTU MENGGUNAKAN METODE CPM DAN PERT PADA PEMBANGUNAN GUDANG DEXA MEDICA PALEMBANG\",\"authors\":\"Lega Reskita Lubis, Zuul Fitriana Umari, Kristi Kristi, Akhirini Akhirini\",\"doi\":\"10.52333/lateral.v1i2.314\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The project is a series of sensitive work mechanisms because each aspect of the project is interconnected with each other. The purpose of this research is to determine the planned duration, critical path activities, and probability in the implementation of the Dexa Medica warehouse construction project in Palembang. Primary data used for estimation of work time, while secondary data used time schedules (S-curve) and work plan drawings. The methods used are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). The planned project completion duration using the CPM calculation method is 39 weeks. The activities known to be on the critical path are preparation, earthworks and others on the 1st floor, concrete work on the 1st floor, architectural work on the 1st floor, site development, and genset room work. The planned project completion duration using the PERT calculation method is 40.2 weeks. The probability (Probabiliti) with the PERT method is found to be 0.7324, meaning that there is a 73.24% probability that the project will be completed within 41 weeks.\",\"PeriodicalId\":126911,\"journal\":{\"name\":\"Jurnal Teknik Sipil LATERAL\",\"volume\":\"152 \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-11-30\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Teknik Sipil LATERAL\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.52333/lateral.v1i2.314\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Sipil LATERAL","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.52333/lateral.v1i2.314","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

该项目是一系列敏感的工作机制,因为项目的每个方面都相互关联。本研究的目的是确定巴伦邦 Dexa Medica 仓库建设项目实施过程中的计划工期、关键路径活动和概率。主要数据用于估算工作时间,次要数据用于时间进度表(S 曲线)和工作计划图纸。使用的方法是关键路径法(CPM)和计划评估与审查技术(PERT)。采用 CPM 计算方法,计划项目完工时间为 39 周。已知在关键路径上的活动有:一楼的准备工作、土方工程和其他工程、一楼的混凝土工程、一楼的建筑工程、场地开发和发电机房工程。根据 PERT 计算方法,计划项目完工时间为 40.2 周。采用 PERT 计算法得出的概率(Probabiliti)为 0.7324,即该项目在 41 周内完工的概率为 73.24%。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
ANALISIS PENJADWALAN WAKTU MENGGUNAKAN METODE CPM DAN PERT PADA PEMBANGUNAN GUDANG DEXA MEDICA PALEMBANG
The project is a series of sensitive work mechanisms because each aspect of the project is interconnected with each other. The purpose of this research is to determine the planned duration, critical path activities, and probability in the implementation of the Dexa Medica warehouse construction project in Palembang. Primary data used for estimation of work time, while secondary data used time schedules (S-curve) and work plan drawings. The methods used are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). The planned project completion duration using the CPM calculation method is 39 weeks. The activities known to be on the critical path are preparation, earthworks and others on the 1st floor, concrete work on the 1st floor, architectural work on the 1st floor, site development, and genset room work. The planned project completion duration using the PERT calculation method is 40.2 weeks. The probability (Probabiliti) with the PERT method is found to be 0.7324, meaning that there is a 73.24% probability that the project will be completed within 41 weeks.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信