{"title":"评估新兴经济体PPP项目的关键障碍和成功因素:以越南为例","authors":"Hung Duy Nguyen, Tuan Anh Nguyen, Vi Vu Doan, Chau Ngoc Dang","doi":"10.1108/jedt-08-2023-0340","DOIUrl":null,"url":null,"abstract":"Purpose Public–private partnership (PPP) projects play a pivotal role in fostering infrastructure development in developing countries. This study aims to identify major barriers and critical success factors (CSFs) for PPP projects in Vietnam. Design/methodology/approach The study initially conducted an extensive literature review and interviewed industry experts to compile a comprehensive list of barriers and success factors. Subsequently, a survey involving 250 construction professionals was conducted to assess these identified factors. The research used both ANOVA test and hierarchical regression analysis to explore the relationship between participants’ characteristics and assessments. Findings The results could provide a valuable reference for practitioners by assessing barriers and CSFs in PPP projects. Specifically, the ANOVA analysis indicated a positive correlation between barrier assessment and participants’ experience, while the influence of participants’ sector on the evaluation was minor. Furthermore, the hierarchical regression analysis demonstrated that participants’ sector did not moderate the relationship between barrier assessment and industry experience. Originality/value This research contributes to the existing literature by offering empirical insights into barriers and CSFs specific to PPP projects in a developing country context. The findings highlight the crucial role of experienced professionals in ensuring PPP project success. Moreover, the study provides construction practitioners with a better understanding of the essential factors and supports the development of effective management strategies for future PPP projects.","PeriodicalId":46533,"journal":{"name":"Journal of Engineering Design and Technology","volume":"11 3","pages":"0"},"PeriodicalIF":2.6000,"publicationDate":"2023-11-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Assessing critical barriers and success factors of PPP projects in emerging economies: a case of Vietnam\",\"authors\":\"Hung Duy Nguyen, Tuan Anh Nguyen, Vi Vu Doan, Chau Ngoc Dang\",\"doi\":\"10.1108/jedt-08-2023-0340\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose Public–private partnership (PPP) projects play a pivotal role in fostering infrastructure development in developing countries. This study aims to identify major barriers and critical success factors (CSFs) for PPP projects in Vietnam. Design/methodology/approach The study initially conducted an extensive literature review and interviewed industry experts to compile a comprehensive list of barriers and success factors. Subsequently, a survey involving 250 construction professionals was conducted to assess these identified factors. The research used both ANOVA test and hierarchical regression analysis to explore the relationship between participants’ characteristics and assessments. Findings The results could provide a valuable reference for practitioners by assessing barriers and CSFs in PPP projects. Specifically, the ANOVA analysis indicated a positive correlation between barrier assessment and participants’ experience, while the influence of participants’ sector on the evaluation was minor. Furthermore, the hierarchical regression analysis demonstrated that participants’ sector did not moderate the relationship between barrier assessment and industry experience. Originality/value This research contributes to the existing literature by offering empirical insights into barriers and CSFs specific to PPP projects in a developing country context. The findings highlight the crucial role of experienced professionals in ensuring PPP project success. Moreover, the study provides construction practitioners with a better understanding of the essential factors and supports the development of effective management strategies for future PPP projects.\",\"PeriodicalId\":46533,\"journal\":{\"name\":\"Journal of Engineering Design and Technology\",\"volume\":\"11 3\",\"pages\":\"0\"},\"PeriodicalIF\":2.6000,\"publicationDate\":\"2023-11-02\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Engineering Design and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/jedt-08-2023-0340\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, MULTIDISCIPLINARY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Engineering Design and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/jedt-08-2023-0340","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, MULTIDISCIPLINARY","Score":null,"Total":0}
Assessing critical barriers and success factors of PPP projects in emerging economies: a case of Vietnam
Purpose Public–private partnership (PPP) projects play a pivotal role in fostering infrastructure development in developing countries. This study aims to identify major barriers and critical success factors (CSFs) for PPP projects in Vietnam. Design/methodology/approach The study initially conducted an extensive literature review and interviewed industry experts to compile a comprehensive list of barriers and success factors. Subsequently, a survey involving 250 construction professionals was conducted to assess these identified factors. The research used both ANOVA test and hierarchical regression analysis to explore the relationship between participants’ characteristics and assessments. Findings The results could provide a valuable reference for practitioners by assessing barriers and CSFs in PPP projects. Specifically, the ANOVA analysis indicated a positive correlation between barrier assessment and participants’ experience, while the influence of participants’ sector on the evaluation was minor. Furthermore, the hierarchical regression analysis demonstrated that participants’ sector did not moderate the relationship between barrier assessment and industry experience. Originality/value This research contributes to the existing literature by offering empirical insights into barriers and CSFs specific to PPP projects in a developing country context. The findings highlight the crucial role of experienced professionals in ensuring PPP project success. Moreover, the study provides construction practitioners with a better understanding of the essential factors and supports the development of effective management strategies for future PPP projects.
期刊介绍:
- Design strategies - Usability and adaptability - Material, component and systems performance - Process control - Alternative and new technologies - Organizational, management and research issues - Human factors - Environmental, quality and health and safety issues - Cost and life cycle issues - Sustainability criteria, indicators, measurement and practices - Risk management - Entrepreneurship Law, regulation and governance - Design, implementing, managing and practicing innovation - Visualization, simulation, information and communication technologies - Education practices, innovation, strategies and policy issues.