{"title":"影响肯尼亚蒙巴萨县公共建设项目绩效的因素","authors":"FRIDAH KAWERA, EVELYNE DATCHE, PhD","doi":"10.61426/sjbcm.v10i4.2777","DOIUrl":null,"url":null,"abstract":"The study was about factors affecting project performance of public construction projects in Mombasa County. The study was guided by both general and specific objectives. To strengthen the conceptual framework the study used theory of constraints, project management competency theory and control theory. The study target population was180 and sample size was 126. This study adopted a cross-sectional research design. A modified Likert scale questionnaire was developed and divided into three parts. A pilot study was carried out to refine the instrument. The quality and consistency of the study was further assessed using Cronbach's alpha. Data analysis was performed on a computer using Statistical Package for Social Science (SPSS Version 25) for Windows. Data was presented in form of means, standard deviation, percentages and tables. Findings show that there was a strong positive correlation between project staff competencies, project monitoring and evaluation and project risk management and there was no correlation between project resource mobilization and performance of public projects in Mombasa County. The study findings further showed project staff competencies and project monitoring and evaluation have a significant effect on project performance of public construction projects in Mombasa County and project resource mobilization and project risk management have no effect on project performance of public construction projects in Mombasa County. The study recommends that counties should continuously train construction experts to be able to build their capacity as well as competencies to be able to deliver quality works and on time within the budgets; that counties should design better monitoring and evaluation tools to be adopted in service delivery; that counties should undertake projects that they have sufficient financial resources and human capacity to deliver the work and that counties should partner with the public under PPPs to deliver on projects where there have no sufficient resources. Key Terms: Project Staff Competencies, Project Evaluation, Project Resource Mobilization, Project Risk Management CITATION : Kawera, F., & Datche, E. (2023). Factors affecting project performance of public construction projects in Mombasa County, Kenya. The Strategic Journal of Business & Change Management, 10 (4), 601 – 619. http://dx.doi.org/10.61426/sjbcm.v10i4.2777.","PeriodicalId":22086,"journal":{"name":"Strategic Journal of Business & Change Management","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"FACTORS AFFECTING PROJECT PERFORMANCE OF PUBLIC CONSTRUCTION PROJECTS IN MOMBASA COUNTY, KENYA\",\"authors\":\"FRIDAH KAWERA, EVELYNE DATCHE, PhD\",\"doi\":\"10.61426/sjbcm.v10i4.2777\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The study was about factors affecting project performance of public construction projects in Mombasa County. The study was guided by both general and specific objectives. To strengthen the conceptual framework the study used theory of constraints, project management competency theory and control theory. The study target population was180 and sample size was 126. This study adopted a cross-sectional research design. A modified Likert scale questionnaire was developed and divided into three parts. A pilot study was carried out to refine the instrument. The quality and consistency of the study was further assessed using Cronbach's alpha. Data analysis was performed on a computer using Statistical Package for Social Science (SPSS Version 25) for Windows. Data was presented in form of means, standard deviation, percentages and tables. Findings show that there was a strong positive correlation between project staff competencies, project monitoring and evaluation and project risk management and there was no correlation between project resource mobilization and performance of public projects in Mombasa County. The study findings further showed project staff competencies and project monitoring and evaluation have a significant effect on project performance of public construction projects in Mombasa County and project resource mobilization and project risk management have no effect on project performance of public construction projects in Mombasa County. The study recommends that counties should continuously train construction experts to be able to build their capacity as well as competencies to be able to deliver quality works and on time within the budgets; that counties should design better monitoring and evaluation tools to be adopted in service delivery; that counties should undertake projects that they have sufficient financial resources and human capacity to deliver the work and that counties should partner with the public under PPPs to deliver on projects where there have no sufficient resources. Key Terms: Project Staff Competencies, Project Evaluation, Project Resource Mobilization, Project Risk Management CITATION : Kawera, F., & Datche, E. (2023). Factors affecting project performance of public construction projects in Mombasa County, Kenya. The Strategic Journal of Business & Change Management, 10 (4), 601 – 619. http://dx.doi.org/10.61426/sjbcm.v10i4.2777.\",\"PeriodicalId\":22086,\"journal\":{\"name\":\"Strategic Journal of Business & Change Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-11-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Strategic Journal of Business & Change Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.61426/sjbcm.v10i4.2777\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Strategic Journal of Business & Change Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.61426/sjbcm.v10i4.2777","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
本文以蒙巴萨县公共建设项目绩效影响因素为研究对象。这项研究以一般目标和具体目标为指导。为了强化概念框架,本研究运用了约束理论、项目管理胜任力理论和控制理论。研究目标人群为180人,样本量为126人。本研究采用横断面研究设计。开发了一份改进的李克特量表问卷,分为三个部分。为了改进仪器,进行了初步研究。使用Cronbach's alpha进一步评估研究的质量和一致性。数据分析在计算机上使用Statistical Package for Social Science (SPSS Version 25) for Windows进行。数据以均值、标准差、百分比和表格的形式呈现。研究结果表明,蒙巴萨县的项目人员能力、项目监测和评估与项目风险管理之间存在很强的正相关关系,而项目资源调动与公共项目绩效之间没有相关性。研究结果进一步表明,项目人员胜任力和项目监测评价对蒙巴萨县公共建设项目绩效有显著影响,项目资源调动和项目风险管理对蒙巴萨县公共建设项目绩效没有影响。该研究建议,各国应不断培训建筑专家,使其能够提高能力和胜任能力,从而能够在预算范围内按时交付高质量的工程;各国应设计更好的监测和评估工具,以便在提供服务时采用;各县应该承担有足够财政资源和人力来完成工作的项目,各县应该在公私伙伴关系下与公众合作,在没有足够资源的地方完成项目。关键词:项目人员能力,项目评估,项目资源调动,项目风险管理引文:Kawera, F., &;达切,E.(2023)。影响肯尼亚蒙巴萨县公共建设项目绩效的因素商业战略杂志;管理学报,21(4),391 - 391。http://dx.doi.org/10.61426/sjbcm.v10i4.2777。
FACTORS AFFECTING PROJECT PERFORMANCE OF PUBLIC CONSTRUCTION PROJECTS IN MOMBASA COUNTY, KENYA
The study was about factors affecting project performance of public construction projects in Mombasa County. The study was guided by both general and specific objectives. To strengthen the conceptual framework the study used theory of constraints, project management competency theory and control theory. The study target population was180 and sample size was 126. This study adopted a cross-sectional research design. A modified Likert scale questionnaire was developed and divided into three parts. A pilot study was carried out to refine the instrument. The quality and consistency of the study was further assessed using Cronbach's alpha. Data analysis was performed on a computer using Statistical Package for Social Science (SPSS Version 25) for Windows. Data was presented in form of means, standard deviation, percentages and tables. Findings show that there was a strong positive correlation between project staff competencies, project monitoring and evaluation and project risk management and there was no correlation between project resource mobilization and performance of public projects in Mombasa County. The study findings further showed project staff competencies and project monitoring and evaluation have a significant effect on project performance of public construction projects in Mombasa County and project resource mobilization and project risk management have no effect on project performance of public construction projects in Mombasa County. The study recommends that counties should continuously train construction experts to be able to build their capacity as well as competencies to be able to deliver quality works and on time within the budgets; that counties should design better monitoring and evaluation tools to be adopted in service delivery; that counties should undertake projects that they have sufficient financial resources and human capacity to deliver the work and that counties should partner with the public under PPPs to deliver on projects where there have no sufficient resources. Key Terms: Project Staff Competencies, Project Evaluation, Project Resource Mobilization, Project Risk Management CITATION : Kawera, F., & Datche, E. (2023). Factors affecting project performance of public construction projects in Mombasa County, Kenya. The Strategic Journal of Business & Change Management, 10 (4), 601 – 619. http://dx.doi.org/10.61426/sjbcm.v10i4.2777.