用临时塔优化再生模板和更换高压风管150公里

Muhammad Iqbal, Haryo Dwito Armono
{"title":"用临时塔优化再生模板和更换高压风管150公里","authors":"Muhammad Iqbal, Haryo Dwito Armono","doi":"10.21107/rekayasa.v16i2.21105","DOIUrl":null,"url":null,"abstract":"The use of temporary towers is a solution to shorten the outage time. Temporary Tower is used as a tool in reconductoring work and tower replacement. The study by calculating the Budget Plan Cost (RAB) and schedule analysis using Microsoft Project Application to determine the comparative duration of time required to complete the reconductoring work and tower replacement between using temporary tower and without temporary tower. From the time schedule created, it will be known which work method uses a shorter duration of time so that it can save or speed up the outage time. This study will produce what kind or type of conductor is appropriate in the context of replacing conductors or reconductoring SUTT 150 kV A - C, resulting in a reconductoring and tower replacement work schedule that is 15 days faster when using a temporary tower and reduces the outage time by about 132 days or about -89%. However, it requires an additional cost of Rp 1,872,217,454, which is still much smaller than the loss due to outages if the work is not done with a temporary tower.","PeriodicalId":33739,"journal":{"name":"Rekayasa","volume":"36 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-08-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Pemakaian Temporary Tower untuk Optimalisasi Penyelesaian Rekonduktoring dan Penggantian Tower Saluran Udara Tegangan Tinggi (SUTT) 150 KV\",\"authors\":\"Muhammad Iqbal, Haryo Dwito Armono\",\"doi\":\"10.21107/rekayasa.v16i2.21105\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The use of temporary towers is a solution to shorten the outage time. Temporary Tower is used as a tool in reconductoring work and tower replacement. The study by calculating the Budget Plan Cost (RAB) and schedule analysis using Microsoft Project Application to determine the comparative duration of time required to complete the reconductoring work and tower replacement between using temporary tower and without temporary tower. From the time schedule created, it will be known which work method uses a shorter duration of time so that it can save or speed up the outage time. This study will produce what kind or type of conductor is appropriate in the context of replacing conductors or reconductoring SUTT 150 kV A - C, resulting in a reconductoring and tower replacement work schedule that is 15 days faster when using a temporary tower and reduces the outage time by about 132 days or about -89%. However, it requires an additional cost of Rp 1,872,217,454, which is still much smaller than the loss due to outages if the work is not done with a temporary tower.\",\"PeriodicalId\":33739,\"journal\":{\"name\":\"Rekayasa\",\"volume\":\"36 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-08-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Rekayasa\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21107/rekayasa.v16i2.21105\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Rekayasa","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21107/rekayasa.v16i2.21105","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

临时塔的使用是缩短停运时间的一种解决方案。临时塔是在重导工作和塔更换中使用的工具。该研究通过计算预算计划成本(RAB)和使用Microsoft Project Application进行进度分析,以确定在使用临时塔和不使用临时塔之间完成重导工作和塔更换所需的比较时间。从创建的时间计划中,可以知道哪种工作方法使用的时间更短,从而节省或加快停机时间。这项研究将确定在更换导体或重新导电SUTT 150 kV A - C的情况下,哪种类型的导体是合适的,从而在使用临时塔时,重新导电和更换塔的工作时间表将缩短15天,并将停机时间减少约132天或约-89%。然而,它需要额外的成本1,872,217,454卢比,这仍然比如果不使用临时塔完成工作而造成的停机损失要小得多。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Pemakaian Temporary Tower untuk Optimalisasi Penyelesaian Rekonduktoring dan Penggantian Tower Saluran Udara Tegangan Tinggi (SUTT) 150 KV
The use of temporary towers is a solution to shorten the outage time. Temporary Tower is used as a tool in reconductoring work and tower replacement. The study by calculating the Budget Plan Cost (RAB) and schedule analysis using Microsoft Project Application to determine the comparative duration of time required to complete the reconductoring work and tower replacement between using temporary tower and without temporary tower. From the time schedule created, it will be known which work method uses a shorter duration of time so that it can save or speed up the outage time. This study will produce what kind or type of conductor is appropriate in the context of replacing conductors or reconductoring SUTT 150 kV A - C, resulting in a reconductoring and tower replacement work schedule that is 15 days faster when using a temporary tower and reduces the outage time by about 132 days or about -89%. However, it requires an additional cost of Rp 1,872,217,454, which is still much smaller than the loss due to outages if the work is not done with a temporary tower.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
42
审稿时长
12 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信