肯尼亚纳库鲁县房地产建设项目的风险管理实践和绩效

IF 2 4区 管理学 Q3 MANAGEMENT
{"title":"肯尼亚纳库鲁县房地产建设项目的风险管理实践和绩效","authors":"","doi":"10.53819/81018102t5284","DOIUrl":null,"url":null,"abstract":"Real estate development performance in Nakuru County continuously deteriorates, as evidenced by rising vacancy rates in outdated office buildings, restrained consumer spending due to the difficult economic climate, and competition from unofficial retail spaces in some submarkets. The study aimed at finding out how risk management practices influence the performance of real estate construction projects in Nakuru County. The research determined how technical risk management practices, financial risk management practices, market risk management practices and operational risk management practices affect the performance of real estate construction projects in Nakuru County. This research used a mixed-method study design with a population target of 45 ongoing and 25 completed real estate projects in Nakuru County. Using stratified simple sampling technique, a sample size of 25 ongoing and 15 completed real estate projects were selected. The study was affixed on strategic planning theory, Decision theory and risk/uncertainty bearing theory. The researcher used questionnaires to obtain data and suggestions from the respondentsA pilot study to assess the research instruments' accuracy and dependability was conducted in Nairobi County. The research utilized Cronbach's alpha to calculate the reliability coefficient of the questionnaires. Cronbach value greater than 0.7 was considered reliable. The gathered data was cleaned, coded, and accuracy checked for ease of analysis, and then subjected to descriptive analysis involving the calculation of mean, frequency distribution, and standard deviation. Using Pearson correlation analysis, the relationship between the dependent and independent variables was evaluated. Regression analysis was done using the analysis of variance technique (ANOVA). The study found that technical, operational, market, and financial risk management practices each had positive and substantial impacts, indicated by regression coefficients of 0.451, 0.313, 0.531, and 0.273, respectively. Further, the study established that these practices are crucial in managing various risks effectively, demonstrating their significant role in overall risk management strategies. . Constructed from the study findings, this study recommends that the Kenyan government should review all of the approvals that real estate developers need, formulate policies that regulate the construction sector by ensuring that real estate developers demonstrate their creditworthiness on their expected investments before granting any licenses. In addition, real estate developers should be encouraged to take advantage of staff empowerment through professional bodies that equips managers through risk management courses. Lastly, future studies conducted should concentrate on other risk variables not included in this study including legal and environmental risk management practices. Keywords:  Risk Assessment, Project Performance, Construction Management, Real Estate Development, Mitigation Strategies","PeriodicalId":14424,"journal":{"name":"International Journal of Strategic Property Management","volume":"16 4","pages":"0"},"PeriodicalIF":2.0000,"publicationDate":"2023-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Risk Management Practices and Performance of Real Estate Construction Projects in Nakuru County, Kenya\",\"authors\":\"\",\"doi\":\"10.53819/81018102t5284\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Real estate development performance in Nakuru County continuously deteriorates, as evidenced by rising vacancy rates in outdated office buildings, restrained consumer spending due to the difficult economic climate, and competition from unofficial retail spaces in some submarkets. The study aimed at finding out how risk management practices influence the performance of real estate construction projects in Nakuru County. The research determined how technical risk management practices, financial risk management practices, market risk management practices and operational risk management practices affect the performance of real estate construction projects in Nakuru County. This research used a mixed-method study design with a population target of 45 ongoing and 25 completed real estate projects in Nakuru County. Using stratified simple sampling technique, a sample size of 25 ongoing and 15 completed real estate projects were selected. The study was affixed on strategic planning theory, Decision theory and risk/uncertainty bearing theory. The researcher used questionnaires to obtain data and suggestions from the respondentsA pilot study to assess the research instruments' accuracy and dependability was conducted in Nairobi County. The research utilized Cronbach's alpha to calculate the reliability coefficient of the questionnaires. Cronbach value greater than 0.7 was considered reliable. The gathered data was cleaned, coded, and accuracy checked for ease of analysis, and then subjected to descriptive analysis involving the calculation of mean, frequency distribution, and standard deviation. Using Pearson correlation analysis, the relationship between the dependent and independent variables was evaluated. Regression analysis was done using the analysis of variance technique (ANOVA). The study found that technical, operational, market, and financial risk management practices each had positive and substantial impacts, indicated by regression coefficients of 0.451, 0.313, 0.531, and 0.273, respectively. Further, the study established that these practices are crucial in managing various risks effectively, demonstrating their significant role in overall risk management strategies. . Constructed from the study findings, this study recommends that the Kenyan government should review all of the approvals that real estate developers need, formulate policies that regulate the construction sector by ensuring that real estate developers demonstrate their creditworthiness on their expected investments before granting any licenses. In addition, real estate developers should be encouraged to take advantage of staff empowerment through professional bodies that equips managers through risk management courses. Lastly, future studies conducted should concentrate on other risk variables not included in this study including legal and environmental risk management practices. Keywords:  Risk Assessment, Project Performance, Construction Management, Real Estate Development, Mitigation Strategies\",\"PeriodicalId\":14424,\"journal\":{\"name\":\"International Journal of Strategic Property Management\",\"volume\":\"16 4\",\"pages\":\"0\"},\"PeriodicalIF\":2.0000,\"publicationDate\":\"2023-11-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Strategic Property Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.53819/81018102t5284\",\"RegionNum\":4,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Strategic Property Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.53819/81018102t5284","RegionNum":4,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 0

摘要

纳库鲁县的房地产开发业绩持续恶化,过时办公楼空置率上升,经济环境困难导致消费者支出受限,以及一些子市场中来自非官方零售空间的竞争。该研究旨在找出风险管理实践如何影响纳库鲁县房地产建设项目的绩效。研究确定了技术风险管理实践、财务风险管理实践、市场风险管理实践和操作风险管理实践如何影响纳库鲁县房地产建设项目的绩效。本研究采用混合方法研究设计,人口目标为纳库鲁县45个正在进行和25个已完成的房地产项目。采用分层简单抽样技术,选取了25个正在进行的房地产项目和15个已完成的房地产项目作为样本。对战略规划理论、决策理论和风险/不确定性承担理论进行了研究。研究人员使用问卷调查的方式从受访者那里获得数据和建议。在内罗毕县进行了一项试点研究,以评估研究工具的准确性和可靠性。本研究采用Cronbach's alpha计算问卷信度系数。Cronbach值大于0.7为可靠值。收集到的数据经过清理、编码和准确性检查,以便于分析,然后进行描述性分析,包括计算平均值、频率分布和标准差。采用Pearson相关分析,评价因变量与自变量之间的关系。采用方差分析技术(ANOVA)进行回归分析。研究发现,技术风险管理、运营风险管理、市场风险管理和财务风险管理各有积极和实质性的影响,回归系数分别为0.451、0.313、0.531和0.273。此外,研究表明,这些实践对于有效管理各种风险至关重要,表明它们在整体风险管理战略中的重要作用。根据研究结果,本研究建议肯尼亚政府应审查房地产开发商所需的所有批准,制定规范建筑行业的政策,确保房地产开发商在授予任何许可证之前证明其预期投资的信誉。此外,应鼓励房地产开发商利用专业机构赋予员工权力的机会,通过风险管理课程为管理人员提供装备。最后,未来的研究应集中于本研究未包括的其他风险变量,包括法律和环境风险管理实践。关键词:风险评估,项目绩效,施工管理,房地产开发,缓解策略
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Risk Management Practices and Performance of Real Estate Construction Projects in Nakuru County, Kenya
Real estate development performance in Nakuru County continuously deteriorates, as evidenced by rising vacancy rates in outdated office buildings, restrained consumer spending due to the difficult economic climate, and competition from unofficial retail spaces in some submarkets. The study aimed at finding out how risk management practices influence the performance of real estate construction projects in Nakuru County. The research determined how technical risk management practices, financial risk management practices, market risk management practices and operational risk management practices affect the performance of real estate construction projects in Nakuru County. This research used a mixed-method study design with a population target of 45 ongoing and 25 completed real estate projects in Nakuru County. Using stratified simple sampling technique, a sample size of 25 ongoing and 15 completed real estate projects were selected. The study was affixed on strategic planning theory, Decision theory and risk/uncertainty bearing theory. The researcher used questionnaires to obtain data and suggestions from the respondentsA pilot study to assess the research instruments' accuracy and dependability was conducted in Nairobi County. The research utilized Cronbach's alpha to calculate the reliability coefficient of the questionnaires. Cronbach value greater than 0.7 was considered reliable. The gathered data was cleaned, coded, and accuracy checked for ease of analysis, and then subjected to descriptive analysis involving the calculation of mean, frequency distribution, and standard deviation. Using Pearson correlation analysis, the relationship between the dependent and independent variables was evaluated. Regression analysis was done using the analysis of variance technique (ANOVA). The study found that technical, operational, market, and financial risk management practices each had positive and substantial impacts, indicated by regression coefficients of 0.451, 0.313, 0.531, and 0.273, respectively. Further, the study established that these practices are crucial in managing various risks effectively, demonstrating their significant role in overall risk management strategies. . Constructed from the study findings, this study recommends that the Kenyan government should review all of the approvals that real estate developers need, formulate policies that regulate the construction sector by ensuring that real estate developers demonstrate their creditworthiness on their expected investments before granting any licenses. In addition, real estate developers should be encouraged to take advantage of staff empowerment through professional bodies that equips managers through risk management courses. Lastly, future studies conducted should concentrate on other risk variables not included in this study including legal and environmental risk management practices. Keywords:  Risk Assessment, Project Performance, Construction Management, Real Estate Development, Mitigation Strategies
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
4.00
自引率
18.50%
发文量
23
审稿时长
15 weeks
期刊介绍: International Journal of Strategic Property Management is a peer-reviewed, interdisciplinary journal which publishes original research papers. The journal provides a forum for discussion and debate relating to all areas of strategic property management. Topics include, but are not limited to, the following: asset management, facilities management, property policy, budgeting and financial controls, enhancing residential property value, marketing and leasing, risk management, real estate valuation and investment, innovations in residential management, housing finance, sustainability and housing development, applications, etc.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信