建设项目进度加速规划(以Japek II Selatan收费公路为例)

Aziz Irsyad, I. Puspita, W. Tripiawan
{"title":"建设项目进度加速规划(以Japek II Selatan收费公路为例)","authors":"Aziz Irsyad, I. Puspita, W. Tripiawan","doi":"10.25124/ijies.v6i01.145","DOIUrl":null,"url":null,"abstract":"This study focuses on the remaining work at stations (STA) 53+950 to 54+550 in Jakarta – Cikampek II Selatan Toll Road Package III project to find the critical path, completion durations, and project costs before and after acceleration. The CPM Technique was used to compile network planning diagrams, determine the critical path and project duration. Crashing Project was applied to crash schedule through the total project duration and cost whose changes due to the implementation of the crashing method. The critical path was found in mobilization, tree felling, clearing, dig and haul, borrow material, subgrade preparation, base course (A grade), subbase course (B grade), drainage layer, lean concrete (t=10 cm), concrete pavement, concrete barrier type B, and signage. In the CPM, the duration of project completion is 214 days. The total project budget under normal circumstances is Rp22.073.412.654. After accelerating with the Crashing Project by proposed overtime was obtained the reduced total cost of Rp32.004.882 from the total normal cost of Rp22.073.412.654 to Rp22.041.407.771 with an optimum duration of 183 days.","PeriodicalId":217640,"journal":{"name":"International Journal of Innovation in Enterprise System","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-01-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad)\",\"authors\":\"Aziz Irsyad, I. Puspita, W. Tripiawan\",\"doi\":\"10.25124/ijies.v6i01.145\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study focuses on the remaining work at stations (STA) 53+950 to 54+550 in Jakarta – Cikampek II Selatan Toll Road Package III project to find the critical path, completion durations, and project costs before and after acceleration. The CPM Technique was used to compile network planning diagrams, determine the critical path and project duration. Crashing Project was applied to crash schedule through the total project duration and cost whose changes due to the implementation of the crashing method. The critical path was found in mobilization, tree felling, clearing, dig and haul, borrow material, subgrade preparation, base course (A grade), subbase course (B grade), drainage layer, lean concrete (t=10 cm), concrete pavement, concrete barrier type B, and signage. In the CPM, the duration of project completion is 214 days. The total project budget under normal circumstances is Rp22.073.412.654. After accelerating with the Crashing Project by proposed overtime was obtained the reduced total cost of Rp32.004.882 from the total normal cost of Rp22.073.412.654 to Rp22.041.407.771 with an optimum duration of 183 days.\",\"PeriodicalId\":217640,\"journal\":{\"name\":\"International Journal of Innovation in Enterprise System\",\"volume\":\"20 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-01-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Innovation in Enterprise System\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.25124/ijies.v6i01.145\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Innovation in Enterprise System","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.25124/ijies.v6i01.145","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本研究的重点是雅加达- Cikampek II Selatan收费公路III包项目的53+950至54+550站(STA)的剩余工作,以找到加速前后的关键路径、完工时间和项目成本。利用CPM技术编制网络规划图,确定关键路径和项目工期。崩溃项目通过实施崩溃方法导致的项目总持续时间和成本变化应用于崩溃计划。在动员、砍伐树木、清理、挖掘和搬运、借料、路基准备、基层(A级)、基层(B级)、排水层、贫混凝土(t=10 cm)、混凝土路面、B型混凝土屏障和标志中发现了关键路径。在CPM中,项目完成时间为214天。正常情况下工程总预算为Rp22.073.412.654。在建议加班加速crash项目后,总成本Rp32.004.882由正常总成本Rp22.073.412.654降低至Rp22.041.407.771,最佳工期为183天。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad)
This study focuses on the remaining work at stations (STA) 53+950 to 54+550 in Jakarta – Cikampek II Selatan Toll Road Package III project to find the critical path, completion durations, and project costs before and after acceleration. The CPM Technique was used to compile network planning diagrams, determine the critical path and project duration. Crashing Project was applied to crash schedule through the total project duration and cost whose changes due to the implementation of the crashing method. The critical path was found in mobilization, tree felling, clearing, dig and haul, borrow material, subgrade preparation, base course (A grade), subbase course (B grade), drainage layer, lean concrete (t=10 cm), concrete pavement, concrete barrier type B, and signage. In the CPM, the duration of project completion is 214 days. The total project budget under normal circumstances is Rp22.073.412.654. After accelerating with the Crashing Project by proposed overtime was obtained the reduced total cost of Rp32.004.882 from the total normal cost of Rp22.073.412.654 to Rp22.041.407.771 with an optimum duration of 183 days.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信