{"title":"西爪哇省西万隆县 Citatah 区 Sarimukti 村 H. Adin Sumarna 个人公司在砂岩开采中购买和租用挖掘、装载和运输设备的经济比较研究","authors":"Rismul Rasyad Rasyad, Zaenal, Noor Fauzi Isniarno","doi":"10.29313/bcsme.v2i1.1658","DOIUrl":null,"url":null,"abstract":"Perusahaan Perseorangan atas nama H.ADIN SUMARNA, which plans to use the SUMITOMO digging tool SH-210 type and HUTO haulage type DUTRO 130MDL for the activity of digging, loading and transporting sand material, to determine the selection of the loading and unloading digging equipment and conveyance that has the most economical supply the economy. \n CV Bumi Pasir Makmur which has 2,632,821 tons of mined reserves, with a planned production target of 460,000 tons / year with an effective working time of 6.5 hours / day or 1,931 hours / year. The need for the number of loading and unloading equipment and conveyances to meet production targets is carried out by calculating the productivity and Macth Factor values of the equipment to be used. The productivity value is 264.67 tons / hour or 510,953 tons / year for loading and unloading equipment and 131.78 tons / hour / unit or 254,405 tons / year / unit for transportation, so the amount of loading and unloading equipment needs 1 (one) unit and tool transport 2 (two) units with an alignment value of 1 (one) which means perfect. \n The costs that have to be incurred by Perusahaan Perseorangan atas nama H.ADIN SUMARNA for the need for loading and unloading equipment and transportation equipment for production which includes equipment procurement costs, operational costs, and operator salary costs. The cost for procurement of equipment by purchase is Rp. 2,115,300,000 and rental fee is Rp. 849,600,000 / year. The operational cost of the equipment is Rp. 1,137,240,248/year and the lease is Rp. 1,065,240,248/year. Operator salary costs as much as Rp. 129,360,000 / year. The cost of producing unloading and loading and buying conveyance equipment is IDR 1,266,600,248/year and rent is IDR 2,044,200,248/year. \n Economic analysis of loading and unloading equipment and conveyances with a value of inflation of 3% / year shows the cumulative value of NPV in purchase of Rp. 712,271,102,963 and a rental of Rp. 695,245,976,224 with a difference of Rp. 17,026,129,738. IRR value of 63.53 for purchase and 63.73 for rent with a difference of 0.2. PBP value of purchase is 1.58 and rent is 1.56 with a difference of 0.02. \nPerusahaan Perseorangan atas nama H.ADIN SUMARNA dalam kegitanan penambangan yang merencanakan penggunaan alat gali muat pabrikan SUMITOMO tipe SH-210 dan alat angkut pabrikan HINO type DUTRO 130MDL untuk kegiatan gali, muat, dan angkut material pasir. Penentuan pemilihan penggunaan alat gali muat dan alat angkut yang efektif dan efisien dilakukan perhitungan dan kajian ekonomi. \nPerusahaan Perseorangan atas nama H.ADIN SUMARNA yang memiliki cadangan tertambang 2.632.821 ton, dengan rencana target produksi 460.000 ton/tahun dengan waktu efektif kerja 6,5 jam/hari atau 1.931 jam/tahun. Kebutuhan jumlah alat gali muat dan alat angkut untuk memenuhi target produksi dilakukan perhitungan produktifitas dan nilai keserasian/Macth Factor dari alat-alat yang akan digunakan. Nilai produktifitas 264,67 ton/jam atau 510.953 ton/tahun untuk alat gali muat dan 131,78 ton/jam/unit atau 254.405 ton/tahun/unit untuk alat angkut maka maka jumlah kebutuhan alat gali muat 1 (satu) unit dan alat angkut 2 (dua) unit dengan nilai keselarasan 1 (satu) yang artinya sempurna. \nBiaya-biaya yang harus dikeluarkan oleh Perusahaan untuk kebutuhan alat gali muat dan alat angkut untuk produksi yang meliputi biaya pengadaan alat, biaya oprasional, dan biaya gaji operator. Biaya untuk pengadaan alat secara beli sebesar Rp 2.115.300.000 dan secara sewa sebes Rp 849.600.000/tahun. Biaya oprasional alat secara beli sebesar Rp 1.137.240.248/tahun dan secara sewa sebesar Rp 1.065.240.248/tahun. Biaya gaji operator sebesar Rp 129.360.000/tahun. Biaya produksi alat gali muat dan alat angkut beli sebesar Rp 1.266.600.248/tahun dan secara sewa sebesar Rp 2.044.200.248/tahun. \nAnalisa ekonomi alat gali muat dan alat angkut dengan nilai inflasi 3%/tahun menunjukan Kumulatif nilai NPV secara beli sebesar Rp 712.271.102.963 dan secara sewa sebesar Rp 695.245.976.224 dengan selisih sebesar Rp 17.026.129.738. nilai IRR secara beli sebesar 63,53 dan secara sewa 63,73 dengan selisih sebesar 0,2. Nilai PBP secara beli sebesar 1,58 dan secara sewa 1,56 dengan selisih 0,02.","PeriodicalId":187584,"journal":{"name":"Bandung Conference Series: Mining Engineering","volume":"48 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-01-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Kajian Ekonomi Perbandingan Antara Beli dan Sewa Alat Gali Muat dan Alat Angkut pada Penambangan Batu Pasir Perusahaan Perorangan H. Adin Sumarna di Desa Sarimukti, Kecamatan Citatah, Kabupaten Bandung Barat, Provinsi Jawa Barat\",\"authors\":\"Rismul Rasyad Rasyad, Zaenal, Noor Fauzi Isniarno\",\"doi\":\"10.29313/bcsme.v2i1.1658\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Perusahaan Perseorangan atas nama H.ADIN SUMARNA, which plans to use the SUMITOMO digging tool SH-210 type and HUTO haulage type DUTRO 130MDL for the activity of digging, loading and transporting sand material, to determine the selection of the loading and unloading digging equipment and conveyance that has the most economical supply the economy. \\n CV Bumi Pasir Makmur which has 2,632,821 tons of mined reserves, with a planned production target of 460,000 tons / year with an effective working time of 6.5 hours / day or 1,931 hours / year. The need for the number of loading and unloading equipment and conveyances to meet production targets is carried out by calculating the productivity and Macth Factor values of the equipment to be used. The productivity value is 264.67 tons / hour or 510,953 tons / year for loading and unloading equipment and 131.78 tons / hour / unit or 254,405 tons / year / unit for transportation, so the amount of loading and unloading equipment needs 1 (one) unit and tool transport 2 (two) units with an alignment value of 1 (one) which means perfect. \\n The costs that have to be incurred by Perusahaan Perseorangan atas nama H.ADIN SUMARNA for the need for loading and unloading equipment and transportation equipment for production which includes equipment procurement costs, operational costs, and operator salary costs. The cost for procurement of equipment by purchase is Rp. 2,115,300,000 and rental fee is Rp. 849,600,000 / year. The operational cost of the equipment is Rp. 1,137,240,248/year and the lease is Rp. 1,065,240,248/year. Operator salary costs as much as Rp. 129,360,000 / year. The cost of producing unloading and loading and buying conveyance equipment is IDR 1,266,600,248/year and rent is IDR 2,044,200,248/year. \\n Economic analysis of loading and unloading equipment and conveyances with a value of inflation of 3% / year shows the cumulative value of NPV in purchase of Rp. 712,271,102,963 and a rental of Rp. 695,245,976,224 with a difference of Rp. 17,026,129,738. IRR value of 63.53 for purchase and 63.73 for rent with a difference of 0.2. PBP value of purchase is 1.58 and rent is 1.56 with a difference of 0.02. \\nPerusahaan Perseorangan atas nama H.ADIN SUMARNA dalam kegitanan penambangan yang merencanakan penggunaan alat gali muat pabrikan SUMITOMO tipe SH-210 dan alat angkut pabrikan HINO type DUTRO 130MDL untuk kegiatan gali, muat, dan angkut material pasir. Penentuan pemilihan penggunaan alat gali muat dan alat angkut yang efektif dan efisien dilakukan perhitungan dan kajian ekonomi. \\nPerusahaan Perseorangan atas nama H.ADIN SUMARNA yang memiliki cadangan tertambang 2.632.821 ton, dengan rencana target produksi 460.000 ton/tahun dengan waktu efektif kerja 6,5 jam/hari atau 1.931 jam/tahun. Kebutuhan jumlah alat gali muat dan alat angkut untuk memenuhi target produksi dilakukan perhitungan produktifitas dan nilai keserasian/Macth Factor dari alat-alat yang akan digunakan. Nilai produktifitas 264,67 ton/jam atau 510.953 ton/tahun untuk alat gali muat dan 131,78 ton/jam/unit atau 254.405 ton/tahun/unit untuk alat angkut maka maka jumlah kebutuhan alat gali muat 1 (satu) unit dan alat angkut 2 (dua) unit dengan nilai keselarasan 1 (satu) yang artinya sempurna. \\nBiaya-biaya yang harus dikeluarkan oleh Perusahaan untuk kebutuhan alat gali muat dan alat angkut untuk produksi yang meliputi biaya pengadaan alat, biaya oprasional, dan biaya gaji operator. Biaya untuk pengadaan alat secara beli sebesar Rp 2.115.300.000 dan secara sewa sebes Rp 849.600.000/tahun. Biaya oprasional alat secara beli sebesar Rp 1.137.240.248/tahun dan secara sewa sebesar Rp 1.065.240.248/tahun. Biaya gaji operator sebesar Rp 129.360.000/tahun. Biaya produksi alat gali muat dan alat angkut beli sebesar Rp 1.266.600.248/tahun dan secara sewa sebesar Rp 2.044.200.248/tahun. \\nAnalisa ekonomi alat gali muat dan alat angkut dengan nilai inflasi 3%/tahun menunjukan Kumulatif nilai NPV secara beli sebesar Rp 712.271.102.963 dan secara sewa sebesar Rp 695.245.976.224 dengan selisih sebesar Rp 17.026.129.738. nilai IRR secara beli sebesar 63,53 dan secara sewa 63,73 dengan selisih sebesar 0,2. Nilai PBP secara beli sebesar 1,58 dan secara sewa 1,56 dengan selisih 0,02.\",\"PeriodicalId\":187584,\"journal\":{\"name\":\"Bandung Conference Series: Mining Engineering\",\"volume\":\"48 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-01-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Bandung Conference Series: Mining Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.29313/bcsme.v2i1.1658\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bandung Conference Series: Mining Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29313/bcsme.v2i1.1658","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
Perusahaan Perseorangan atas nama H.ADIN SUMARNA计划使用住友挖掘工具SH-210型和HUTO运输型DUTRO 130MDL进行挖掘,装载和运输沙料的活动,以确定最经济的装卸挖掘设备和运输方式的选择。CV Bumi Pasir Makmur拥有2,632,821吨已开采储量,计划生产目标为46万吨/年,有效工作时间为6.5小时/天或1931小时/年。通过计算要使用的设备的生产率和数学系数值来确定需要多少装卸设备和运输工具来满足生产目标。装卸设备的生产率值为264.67吨/小时或510,953吨/年,运输的生产率值为131.78吨/小时/单位或254,405吨/年/单位,因此装卸设备的数量需要1(1)台,工具运输2(2)台,对齐值为1(1),即完美。Perusahaan Perseorangan atas nama H.ADIN SUMARNA必须为生产所需的装卸设备和运输设备产生的成本,包括设备采购成本、运营成本和操作人员工资成本。采购设备的成本为2,115,300,000卢比,租赁费用为84,9,600,000卢比/年。设备的运营成本为1,137,240,248卢比/年,租赁成本为1,065,240,248卢比/年。操作员的工资每年高达129,36万卢比。生产、装卸和购买运输设备的成本为1,266,600,248印尼盾/年,租金为2,044,200,248印尼盾/年。对装卸设备和运输工具的经济分析显示,在通货膨胀率为3% /年的情况下,购买Rp. 712,271,102,963和租赁Rp. 695,245,976,224的累计NPV值相差为Rp. 17,026,129,738。购买的IRR值为63.53,租赁的IRR值为63.73,差0.2。购买的PBP值为1.58,租赁的PBP值为1.56,相差0.02。Perusahaan Perseorangan atnama H.ADIN SUMARNA dalam kegitanan penambangan yang merencananakan penggunaan alat gali mut pabrikan住友型SH-210 danalat angkut pabrikan HINO型DUTRO 130MDL untuk kegiatan gali, muat, danangkut材料pasir。彭俊贤:彭俊贤,彭俊贤;彭俊贤,彭俊贤;彭俊贤;彭俊贤;彭俊贤;彭俊贤;Perusahaan Perseorangan atas nama H.ADIN SUMARNA yang memiliki cadangan tertambang 2.632.821吨,dengan rencana目标产量460.000吨/tahun dengan waktu efektif kerja 6,5果酱/hari atau 1.931果酱/tahun。Kebutuhan jumlah alat gali muat danalat angkut untuk memenuhi target produksi dilakukan perhitungan produktifitas dan nilai keserasian/数学因子dari alat-alat yang akan digunakan。Nilai产品264,67吨/果酱/ atau 510.953吨/tahun untuk alat gali muat dan 131,78吨/果酱/unit atau 254.405吨/tahun/unit untuk alat angkut maka maka jumlah kebutuhan alat gali muat 1 (satu) unit danat angkut 2 (dua) unit dengan Nilai keselarasan 1 (satu) yang artinya sempurna。biaya -biaya yang harus dikeluarkan oleh Perusahaan untuk kebutuhan alat gali muat alat angkut untuk产品duksi yang meliputi biaya pengadaan alat, biaya运营,dan biaya gaji运营商。Biaya untuk pengadaan alat secara beli sebesar Rp 2.115.30万,但secara sewa sebes Rp 84960万/tahun。Biaya操作alat secara beli sebesar Rp 1.137.240.248/tahun dan secara sewa sebesar Rp 1.065.240.248/tahun。Biaya gaji运营商sebesar Rp 129.36万/tahun。Biaya produksi alat gali muat alat angkut beli sebesar Rp 1.266.600.248/tahun dansecara sewa sebesar Rp 2.044.200.248/tahun。分析经济alat gali muat dan alat angkut dengan nilai inflasi 3%/tahun menunjukan Kumulatif nilai NPV secara beli sebesar Rp 712.271.102.963 dan secara sewa sebesar Rp 695.245.976.224 dengan selisih sebesar Rp 17.026.129.738。我是说,我是说,我是说,我是说,我是说,我是说,我是说,我是说,我是说,我是说。Nilai PBP secara beli sebesar 1,58但secara sewa 1,56登干selisish 0,02。
Kajian Ekonomi Perbandingan Antara Beli dan Sewa Alat Gali Muat dan Alat Angkut pada Penambangan Batu Pasir Perusahaan Perorangan H. Adin Sumarna di Desa Sarimukti, Kecamatan Citatah, Kabupaten Bandung Barat, Provinsi Jawa Barat
Perusahaan Perseorangan atas nama H.ADIN SUMARNA, which plans to use the SUMITOMO digging tool SH-210 type and HUTO haulage type DUTRO 130MDL for the activity of digging, loading and transporting sand material, to determine the selection of the loading and unloading digging equipment and conveyance that has the most economical supply the economy.
CV Bumi Pasir Makmur which has 2,632,821 tons of mined reserves, with a planned production target of 460,000 tons / year with an effective working time of 6.5 hours / day or 1,931 hours / year. The need for the number of loading and unloading equipment and conveyances to meet production targets is carried out by calculating the productivity and Macth Factor values of the equipment to be used. The productivity value is 264.67 tons / hour or 510,953 tons / year for loading and unloading equipment and 131.78 tons / hour / unit or 254,405 tons / year / unit for transportation, so the amount of loading and unloading equipment needs 1 (one) unit and tool transport 2 (two) units with an alignment value of 1 (one) which means perfect.
The costs that have to be incurred by Perusahaan Perseorangan atas nama H.ADIN SUMARNA for the need for loading and unloading equipment and transportation equipment for production which includes equipment procurement costs, operational costs, and operator salary costs. The cost for procurement of equipment by purchase is Rp. 2,115,300,000 and rental fee is Rp. 849,600,000 / year. The operational cost of the equipment is Rp. 1,137,240,248/year and the lease is Rp. 1,065,240,248/year. Operator salary costs as much as Rp. 129,360,000 / year. The cost of producing unloading and loading and buying conveyance equipment is IDR 1,266,600,248/year and rent is IDR 2,044,200,248/year.
Economic analysis of loading and unloading equipment and conveyances with a value of inflation of 3% / year shows the cumulative value of NPV in purchase of Rp. 712,271,102,963 and a rental of Rp. 695,245,976,224 with a difference of Rp. 17,026,129,738. IRR value of 63.53 for purchase and 63.73 for rent with a difference of 0.2. PBP value of purchase is 1.58 and rent is 1.56 with a difference of 0.02.
Perusahaan Perseorangan atas nama H.ADIN SUMARNA dalam kegitanan penambangan yang merencanakan penggunaan alat gali muat pabrikan SUMITOMO tipe SH-210 dan alat angkut pabrikan HINO type DUTRO 130MDL untuk kegiatan gali, muat, dan angkut material pasir. Penentuan pemilihan penggunaan alat gali muat dan alat angkut yang efektif dan efisien dilakukan perhitungan dan kajian ekonomi.
Perusahaan Perseorangan atas nama H.ADIN SUMARNA yang memiliki cadangan tertambang 2.632.821 ton, dengan rencana target produksi 460.000 ton/tahun dengan waktu efektif kerja 6,5 jam/hari atau 1.931 jam/tahun. Kebutuhan jumlah alat gali muat dan alat angkut untuk memenuhi target produksi dilakukan perhitungan produktifitas dan nilai keserasian/Macth Factor dari alat-alat yang akan digunakan. Nilai produktifitas 264,67 ton/jam atau 510.953 ton/tahun untuk alat gali muat dan 131,78 ton/jam/unit atau 254.405 ton/tahun/unit untuk alat angkut maka maka jumlah kebutuhan alat gali muat 1 (satu) unit dan alat angkut 2 (dua) unit dengan nilai keselarasan 1 (satu) yang artinya sempurna.
Biaya-biaya yang harus dikeluarkan oleh Perusahaan untuk kebutuhan alat gali muat dan alat angkut untuk produksi yang meliputi biaya pengadaan alat, biaya oprasional, dan biaya gaji operator. Biaya untuk pengadaan alat secara beli sebesar Rp 2.115.300.000 dan secara sewa sebes Rp 849.600.000/tahun. Biaya oprasional alat secara beli sebesar Rp 1.137.240.248/tahun dan secara sewa sebesar Rp 1.065.240.248/tahun. Biaya gaji operator sebesar Rp 129.360.000/tahun. Biaya produksi alat gali muat dan alat angkut beli sebesar Rp 1.266.600.248/tahun dan secara sewa sebesar Rp 2.044.200.248/tahun.
Analisa ekonomi alat gali muat dan alat angkut dengan nilai inflasi 3%/tahun menunjukan Kumulatif nilai NPV secara beli sebesar Rp 712.271.102.963 dan secara sewa sebesar Rp 695.245.976.224 dengan selisih sebesar Rp 17.026.129.738. nilai IRR secara beli sebesar 63,53 dan secara sewa 63,73 dengan selisih sebesar 0,2. Nilai PBP secara beli sebesar 1,58 dan secara sewa 1,56 dengan selisih 0,02.