膏体回填连续浇筑:红湖作业案例分析

J. Oke, K. Hawley, T. Belem, A. Hashemi
{"title":"膏体回填连续浇筑:红湖作业案例分析","authors":"J. Oke, K. Hawley, T. Belem, A. Hashemi","doi":"10.36487/acg_repo/2115_31","DOIUrl":null,"url":null,"abstract":"Cemented paste backfill (CPB) has become known as a superior secondary ground support technique and mine tailings storage method for stoping. Extensive scientific research has been conducted by the authors on CPB to provide the Red Lake operation (RLO) of Evolution Mining with an optimised backfill placement process. CPB mechanical/viscous behaviour is governed by its plasticity, the tailings particle size distribution, particle shape, mineralogical composition, water content, and the type and dosage of binder used (e.g. cement and/or supplementary cementitious material). For the CPB design, it is necessary to have a thorough understanding of the combined effects of filling rate, self-weight consolidation (volume shrinkage/settlement), and binder hydration rate for each specific paste mixture. Due to these complex factors and interactions, a rational CPB material design process was assessed to demonstrate the safety aspects related to a continuous pour. For this purpose, an extensive field monitoring program was required to quantify the CPB performance and characteristics. There are two different ways of optimising the CPB design to maximise placement rate: (i) optimising the type and amount of binder added to the system, and (ii) optimising the CPB placement process underground. Optimisation of binder type and dosage is relatively easy as the required backfill stand-up strength is based on block dimensions, stope stability, and extraction sequencing. Optimisation of backfill placement is more difficult, as the understanding of the viscous/pseudo-plastic behaviour of the CPB is required throughout the pour. Typically, a three-stage (plug–cure–main) pouring strategy is implemented to mitigate the lack of understanding of the CPB behaviour during placement. The CPB plug (i.e. height of initial pour regime) is designed to mitigate the pressure on the backfill fence. Once this CPB plug has cured and reached the required shear strength, the backfill fence is no longer required, and the remainder of the stope void (main) can be filled. However, if the curing time of the in situ paste is accelerated due to the binder exothermic hydration process (volume shrinkage) and backfill self-weight consolidation (water drainage), it is possible to have a more aggressive pour regime provided that all the required design parameters, site procedures, company protocols, and critical controls are met. RLO implemented instrumentation, and an early-age CPB strength testing program to evaluate whether their CPB can be poured continuously or at least more aggressively. Four stopes were instrumented with total earth pressure cells (TEPCs) and piezometers to capture the pressures acting on the fill fence structures and the strengthening response of the CPB plug within the stopes. This paper summarises the results of each of the tests performed. Based on the results obtained from this study, it was concluded that RLO can safely conduct continuous CPB pours with appropriate safeguards and protocols in place. It is important to note that this paper is a summary of the CPB performance and characteristics in RLO longhole stopes and does not reflect site-specific safety procedures, protocols, and critical controls required for a more aggressive pouring regime.","PeriodicalId":410057,"journal":{"name":"Paste 2021: 24th International Conference on Paste, Thickened and Filtered Tailings","volume":"37 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Paste backfill continuous pour: Red Lake operations case study\",\"authors\":\"J. Oke, K. Hawley, T. Belem, A. Hashemi\",\"doi\":\"10.36487/acg_repo/2115_31\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Cemented paste backfill (CPB) has become known as a superior secondary ground support technique and mine tailings storage method for stoping. Extensive scientific research has been conducted by the authors on CPB to provide the Red Lake operation (RLO) of Evolution Mining with an optimised backfill placement process. CPB mechanical/viscous behaviour is governed by its plasticity, the tailings particle size distribution, particle shape, mineralogical composition, water content, and the type and dosage of binder used (e.g. cement and/or supplementary cementitious material). For the CPB design, it is necessary to have a thorough understanding of the combined effects of filling rate, self-weight consolidation (volume shrinkage/settlement), and binder hydration rate for each specific paste mixture. Due to these complex factors and interactions, a rational CPB material design process was assessed to demonstrate the safety aspects related to a continuous pour. For this purpose, an extensive field monitoring program was required to quantify the CPB performance and characteristics. There are two different ways of optimising the CPB design to maximise placement rate: (i) optimising the type and amount of binder added to the system, and (ii) optimising the CPB placement process underground. Optimisation of binder type and dosage is relatively easy as the required backfill stand-up strength is based on block dimensions, stope stability, and extraction sequencing. Optimisation of backfill placement is more difficult, as the understanding of the viscous/pseudo-plastic behaviour of the CPB is required throughout the pour. Typically, a three-stage (plug–cure–main) pouring strategy is implemented to mitigate the lack of understanding of the CPB behaviour during placement. The CPB plug (i.e. height of initial pour regime) is designed to mitigate the pressure on the backfill fence. Once this CPB plug has cured and reached the required shear strength, the backfill fence is no longer required, and the remainder of the stope void (main) can be filled. However, if the curing time of the in situ paste is accelerated due to the binder exothermic hydration process (volume shrinkage) and backfill self-weight consolidation (water drainage), it is possible to have a more aggressive pour regime provided that all the required design parameters, site procedures, company protocols, and critical controls are met. RLO implemented instrumentation, and an early-age CPB strength testing program to evaluate whether their CPB can be poured continuously or at least more aggressively. Four stopes were instrumented with total earth pressure cells (TEPCs) and piezometers to capture the pressures acting on the fill fence structures and the strengthening response of the CPB plug within the stopes. This paper summarises the results of each of the tests performed. Based on the results obtained from this study, it was concluded that RLO can safely conduct continuous CPB pours with appropriate safeguards and protocols in place. It is important to note that this paper is a summary of the CPB performance and characteristics in RLO longhole stopes and does not reflect site-specific safety procedures, protocols, and critical controls required for a more aggressive pouring regime.\",\"PeriodicalId\":410057,\"journal\":{\"name\":\"Paste 2021: 24th International Conference on Paste, Thickened and Filtered Tailings\",\"volume\":\"37 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Paste 2021: 24th International Conference on Paste, Thickened and Filtered Tailings\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36487/acg_repo/2115_31\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Paste 2021: 24th International Conference on Paste, Thickened and Filtered Tailings","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36487/acg_repo/2115_31","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

胶结膏体充填作为一种较好的二次地面支护技术和尾砂储存方法已被公认。作者对CPB进行了广泛的科学研究,为Evolution Mining的红湖作业(RLO)提供了优化的回填安置过程。CPB的力学/粘性行为取决于其可塑性、尾矿粒度分布、颗粒形状、矿物组成、含水量以及所使用的粘合剂(例如水泥和/或补充胶凝材料)的类型和剂量。对于CPB设计,有必要彻底了解每种特定膏体混合物的填充率、自重固结(体积收缩/沉降)和粘结剂水化率的综合影响。由于这些复杂的因素和相互作用,评估了一个合理的CPB材料设计过程,以证明与连续浇注有关的安全方面。为此,需要广泛的现场监测计划来量化CPB的性能和特性。优化CPB设计有两种不同的方法来最大化放置率:(i)优化添加到系统中的粘合剂的类型和数量,以及(ii)优化地下CPB的放置过程。粘结剂类型和用量的优化相对容易,因为所需的充填体立矿强度取决于块体尺寸、采场稳定性和提取顺序。由于在整个浇注过程中都需要了解CPB的粘性/伪塑性行为,因此回填布置的优化更加困难。通常,采用三阶段(plug -养护- main)浇筑策略,以减轻在浇筑过程中对CPB行为缺乏了解的情况。CPB塞(即初始浇筑高度)的设计是为了减轻回填围栏上的压力。一旦CPB塞固化并达到所需的抗剪强度,则不再需要回填围栏,剩余的采场空隙(主)可以被填充。然而,如果由于粘结剂的放热水化过程(体积收缩)和回填体自重固结(排水)而加速了原位膏体的固化时间,则在满足所有要求的设计参数、现场程序、公司协议和关键控制的情况下,可能会有更积极的浇注制度。RLO实施了仪器和早期CPB强度测试程序,以评估他们的CPB是否可以连续浇注或至少更猛烈地浇注。在4个采场安装了总土压力计(TEPCs)和压力计,以捕捉作用在充填围栏结构上的压力和采场内CPB塞的强化响应。本文总结了所进行的每项试验的结果。根据研究结果,RLO可以在适当的保障措施和规程的情况下安全地进行连续CPB倾倒。值得注意的是,本文是对RLO深孔采场CPB性能和特征的总结,并没有反映现场特定的安全程序、协议和更激进的浇注制度所需的关键控制。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Paste backfill continuous pour: Red Lake operations case study
Cemented paste backfill (CPB) has become known as a superior secondary ground support technique and mine tailings storage method for stoping. Extensive scientific research has been conducted by the authors on CPB to provide the Red Lake operation (RLO) of Evolution Mining with an optimised backfill placement process. CPB mechanical/viscous behaviour is governed by its plasticity, the tailings particle size distribution, particle shape, mineralogical composition, water content, and the type and dosage of binder used (e.g. cement and/or supplementary cementitious material). For the CPB design, it is necessary to have a thorough understanding of the combined effects of filling rate, self-weight consolidation (volume shrinkage/settlement), and binder hydration rate for each specific paste mixture. Due to these complex factors and interactions, a rational CPB material design process was assessed to demonstrate the safety aspects related to a continuous pour. For this purpose, an extensive field monitoring program was required to quantify the CPB performance and characteristics. There are two different ways of optimising the CPB design to maximise placement rate: (i) optimising the type and amount of binder added to the system, and (ii) optimising the CPB placement process underground. Optimisation of binder type and dosage is relatively easy as the required backfill stand-up strength is based on block dimensions, stope stability, and extraction sequencing. Optimisation of backfill placement is more difficult, as the understanding of the viscous/pseudo-plastic behaviour of the CPB is required throughout the pour. Typically, a three-stage (plug–cure–main) pouring strategy is implemented to mitigate the lack of understanding of the CPB behaviour during placement. The CPB plug (i.e. height of initial pour regime) is designed to mitigate the pressure on the backfill fence. Once this CPB plug has cured and reached the required shear strength, the backfill fence is no longer required, and the remainder of the stope void (main) can be filled. However, if the curing time of the in situ paste is accelerated due to the binder exothermic hydration process (volume shrinkage) and backfill self-weight consolidation (water drainage), it is possible to have a more aggressive pour regime provided that all the required design parameters, site procedures, company protocols, and critical controls are met. RLO implemented instrumentation, and an early-age CPB strength testing program to evaluate whether their CPB can be poured continuously or at least more aggressively. Four stopes were instrumented with total earth pressure cells (TEPCs) and piezometers to capture the pressures acting on the fill fence structures and the strengthening response of the CPB plug within the stopes. This paper summarises the results of each of the tests performed. Based on the results obtained from this study, it was concluded that RLO can safely conduct continuous CPB pours with appropriate safeguards and protocols in place. It is important to note that this paper is a summary of the CPB performance and characteristics in RLO longhole stopes and does not reflect site-specific safety procedures, protocols, and critical controls required for a more aggressive pouring regime.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信