{"title":"桥梁承台水下围堰柔性止水带的施工","authors":"Junlen Zhang","doi":"10.2749/nanjing.2022.1103","DOIUrl":null,"url":null,"abstract":"The water-stopping efficiency of cofferdams for pile caps is an important indicator with direct influ- ence to the quality and durability of the pile-pouring process. In recent years, a new technique fea- turing flexible capsules serving as waterstops has been introduced, but is still in experimental stage. This thesis, taking the water-stopping construction programme of underwater PC houses of the J. P. Magufuli Bridge project in Tanzania as background, analyzed the two existed types of flexible water- stopping construction methods, id est the integral and separate structures, and studied on measures for improving the flexible water-stopping construction techniques and optimizing the rubber cap- sule waterstops, in the hope of providing references and, possibly, inspirations for similar projects in the future.","PeriodicalId":410450,"journal":{"name":"IABSE Congress, Nanjing 2022: Bridges and Structures: Connection, Integration and Harmonisation","volume":"129 ","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Construction of Flexible Waterstops on Underwater Cofferdams for Pile Caps in Bridge Projects\",\"authors\":\"Junlen Zhang\",\"doi\":\"10.2749/nanjing.2022.1103\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The water-stopping efficiency of cofferdams for pile caps is an important indicator with direct influ- ence to the quality and durability of the pile-pouring process. In recent years, a new technique fea- turing flexible capsules serving as waterstops has been introduced, but is still in experimental stage. This thesis, taking the water-stopping construction programme of underwater PC houses of the J. P. Magufuli Bridge project in Tanzania as background, analyzed the two existed types of flexible water- stopping construction methods, id est the integral and separate structures, and studied on measures for improving the flexible water-stopping construction techniques and optimizing the rubber cap- sule waterstops, in the hope of providing references and, possibly, inspirations for similar projects in the future.\",\"PeriodicalId\":410450,\"journal\":{\"name\":\"IABSE Congress, Nanjing 2022: Bridges and Structures: Connection, Integration and Harmonisation\",\"volume\":\"129 \",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IABSE Congress, Nanjing 2022: Bridges and Structures: Connection, Integration and Harmonisation\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2749/nanjing.2022.1103\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IABSE Congress, Nanjing 2022: Bridges and Structures: Connection, Integration and Harmonisation","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2749/nanjing.2022.1103","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

承台围堰的止水效率是一项重要指标,直接影响到浇筑过程的质量和耐久性。近年来,人们提出了一种柔性胶囊作为止水带的新技术,但仍处于试验阶段。本文以坦桑尼亚J. P. Magufuli大桥水下PC屋止水施工方案为背景,分析了现有的两种柔性止水施工方法,对整体结构和分体式结构进行了测试,研究了改进柔性止水施工技术和优化橡胶帽壳止水的措施,以期为今后的工程建设提供参考。对未来类似项目的启发。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Construction of Flexible Waterstops on Underwater Cofferdams for Pile Caps in Bridge Projects
The water-stopping efficiency of cofferdams for pile caps is an important indicator with direct influ- ence to the quality and durability of the pile-pouring process. In recent years, a new technique fea- turing flexible capsules serving as waterstops has been introduced, but is still in experimental stage. This thesis, taking the water-stopping construction programme of underwater PC houses of the J. P. Magufuli Bridge project in Tanzania as background, analyzed the two existed types of flexible water- stopping construction methods, id est the integral and separate structures, and studied on measures for improving the flexible water-stopping construction techniques and optimizing the rubber cap- sule waterstops, in the hope of providing references and, possibly, inspirations for similar projects in the future.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信