使用BIM工具解决伊拉克建筑项目冲突的好处:案例研究

Anmar F.A Al-Izzy, Mohammed A.KA. Al-Btoush
{"title":"使用BIM工具解决伊拉克建筑项目冲突的好处:案例研究","authors":"Anmar F.A Al-Izzy, Mohammed A.KA. Al-Btoush","doi":"10.32441/jaset.05.01.05","DOIUrl":null,"url":null,"abstract":"When the components that make up a built asset are not spatially coordinated and clashed, this is referred to as a clash in design language. These incompatibilities can be identified more quickly in a BIM process during the design phase of a project, before construction begins on site.  Most construction projects in Iraqi ministries suffer from a lack of coordination between project parties, which leads to problems in later project stages, particularly during the building stage, when one of the primary issues is a confrontation between civil, architectural, and other parties. This study aims to shed light on architectural element clashes and detect them early in the design process, resulting in fewer errors during the implementation phase. The study conducted a quantitative technique that included creating a questionnaire divided into three sections and focused on time and expense overruns. The result showed that, (The financial deficit of the contractor) is the most critical factor; (the contractor’s non-compliance with the technical specifications) was the second rank. The second part (Using Building Information Modeling technology that reduces and resolving clashes between project elements during the design phase) was the most critical factor. Moreover, the second factor is (BIM technology increases communication between the project team) is the second rank.","PeriodicalId":431188,"journal":{"name":"Journal of Advanced Sciences and Engineering Technologies","volume":"78 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-03-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Benefits of Using BIM Tools to Resolve Clashes in Iraqi Construction Projects: A Case Study\",\"authors\":\"Anmar F.A Al-Izzy, Mohammed A.KA. Al-Btoush\",\"doi\":\"10.32441/jaset.05.01.05\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"When the components that make up a built asset are not spatially coordinated and clashed, this is referred to as a clash in design language. These incompatibilities can be identified more quickly in a BIM process during the design phase of a project, before construction begins on site.  Most construction projects in Iraqi ministries suffer from a lack of coordination between project parties, which leads to problems in later project stages, particularly during the building stage, when one of the primary issues is a confrontation between civil, architectural, and other parties. This study aims to shed light on architectural element clashes and detect them early in the design process, resulting in fewer errors during the implementation phase. The study conducted a quantitative technique that included creating a questionnaire divided into three sections and focused on time and expense overruns. The result showed that, (The financial deficit of the contractor) is the most critical factor; (the contractor’s non-compliance with the technical specifications) was the second rank. The second part (Using Building Information Modeling technology that reduces and resolving clashes between project elements during the design phase) was the most critical factor. Moreover, the second factor is (BIM technology increases communication between the project team) is the second rank.\",\"PeriodicalId\":431188,\"journal\":{\"name\":\"Journal of Advanced Sciences and Engineering Technologies\",\"volume\":\"78 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-03-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Advanced Sciences and Engineering Technologies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.32441/jaset.05.01.05\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Advanced Sciences and Engineering Technologies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.32441/jaset.05.01.05","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

当组成构建资产的组件在空间上不协调并且冲突时,这被称为设计语言中的冲突。在项目的设计阶段,在现场施工开始之前,BIM流程可以更快地识别这些不兼容性。伊拉克各部门的大多数建筑项目都缺乏项目各方之间的协调,这导致了项目后期阶段的问题,特别是在建筑阶段,其中一个主要问题是民事、建筑和其他各方之间的对抗。本研究旨在揭示架构元素冲突,并在设计过程的早期发现它们,从而减少实现阶段的错误。该研究采用了一种量化技术,包括制作一份分为三个部分的调查问卷,重点关注时间和费用超支。结果表明,(承包商的财政赤字)是最关键的因素;(承包商不符合技术规范)为第二等级。第二部分(使用建筑信息建模技术,在设计阶段减少和解决项目元素之间的冲突)是最关键的因素。其次,第二个因素是(BIM技术增加了项目团队之间的沟通)。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Benefits of Using BIM Tools to Resolve Clashes in Iraqi Construction Projects: A Case Study
When the components that make up a built asset are not spatially coordinated and clashed, this is referred to as a clash in design language. These incompatibilities can be identified more quickly in a BIM process during the design phase of a project, before construction begins on site.  Most construction projects in Iraqi ministries suffer from a lack of coordination between project parties, which leads to problems in later project stages, particularly during the building stage, when one of the primary issues is a confrontation between civil, architectural, and other parties. This study aims to shed light on architectural element clashes and detect them early in the design process, resulting in fewer errors during the implementation phase. The study conducted a quantitative technique that included creating a questionnaire divided into three sections and focused on time and expense overruns. The result showed that, (The financial deficit of the contractor) is the most critical factor; (the contractor’s non-compliance with the technical specifications) was the second rank. The second part (Using Building Information Modeling technology that reduces and resolving clashes between project elements during the design phase) was the most critical factor. Moreover, the second factor is (BIM technology increases communication between the project team) is the second rank.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信