印尼工业过程热电联产电厂的隔夜成本估算

Rizki Firmansyah Setya Budi, Arum Puni Rijanti, Sahala Maruli Lumbanraja, E. S. Amitayani, M. Birmano, E. Liun
{"title":"印尼工业过程热电联产电厂的隔夜成本估算","authors":"Rizki Firmansyah Setya Budi, Arum Puni Rijanti, Sahala Maruli Lumbanraja, E. S. Amitayani, M. Birmano, E. Liun","doi":"10.17146/jpen.2018.20.2.5045","DOIUrl":null,"url":null,"abstract":"Indonesia’s cogeneration power plant for industrial processes (PeLUIt) is needed to be implemented in Indonesia. Economic analysis is an important factor for PeLUIt implementation. One of the data that needs in the analysis is overnight cost. This research estimates HTGR’s overnight cost by using scaling law.By using the estimated value, it can be calculated the PeLUIt overnight cost. The research’s purpose is to obtain an estimation of overnight costs of PeLUIt. The estimation result shows the overnight cost of PeLUIt. PeLUIt 10 MWth has an overnight cost 166,26 million USD. PeLUIt 30 MWth has an overnight cost 233,49 million USD. PeLUIt 50 MWth has an overnight cost 281,31 million USD. PeLUIt 100 MWth has an overnight cost 371,86 million USD. PeLUIt 350 MWth has an overnight cost 657,16 million USD.Keywords: PeLUIt; Estimation; High temperature gas-cooled reactor; Overnight cost; Scaling law","PeriodicalId":179965,"journal":{"name":"Jurnal Pengembangan Energi Nuklir","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2018-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"OVERNIGHT COST ESTIMATION OFINDONESIA’S COGENERATION POWER PLANT FOR INDUSTRIAL PROCESSES\",\"authors\":\"Rizki Firmansyah Setya Budi, Arum Puni Rijanti, Sahala Maruli Lumbanraja, E. S. Amitayani, M. Birmano, E. Liun\",\"doi\":\"10.17146/jpen.2018.20.2.5045\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Indonesia’s cogeneration power plant for industrial processes (PeLUIt) is needed to be implemented in Indonesia. Economic analysis is an important factor for PeLUIt implementation. One of the data that needs in the analysis is overnight cost. This research estimates HTGR’s overnight cost by using scaling law.By using the estimated value, it can be calculated the PeLUIt overnight cost. The research’s purpose is to obtain an estimation of overnight costs of PeLUIt. The estimation result shows the overnight cost of PeLUIt. PeLUIt 10 MWth has an overnight cost 166,26 million USD. PeLUIt 30 MWth has an overnight cost 233,49 million USD. PeLUIt 50 MWth has an overnight cost 281,31 million USD. PeLUIt 100 MWth has an overnight cost 371,86 million USD. PeLUIt 350 MWth has an overnight cost 657,16 million USD.Keywords: PeLUIt; Estimation; High temperature gas-cooled reactor; Overnight cost; Scaling law\",\"PeriodicalId\":179965,\"journal\":{\"name\":\"Jurnal Pengembangan Energi Nuklir\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Pengembangan Energi Nuklir\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.17146/jpen.2018.20.2.5045\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Pengembangan Energi Nuklir","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.17146/jpen.2018.20.2.5045","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

印度尼西亚的工业过程热电联产电厂(PeLUIt)需要在印度尼西亚实施。经济分析是实施PeLUIt的重要因素。分析中需要的数据之一是隔夜成本。本研究利用标度法估算高温堆的隔夜成本。利用估算值,可以计算出PeLUIt的隔夜成本。本研究的目的是对PeLUIt的隔夜成本进行估算。估算结果显示了PeLUIt的夜间成本。PeLUIt 10 mth的夜间成本为1.626亿美元。PeLUIt 30mth的夜间成本为2.3349亿美元。PeLUIt 50 mth的隔夜成本为281.31亿美元。PeLUIt 100 mth的夜间成本为3.71.86亿美元。PeLUIt 350 mth的夜间成本为6.5716亿美元。关键词:PeLUIt;估计;高温气冷堆;一夜之间成本;标度律
本文章由计算机程序翻译,如有差异,请以英文原文为准。
OVERNIGHT COST ESTIMATION OFINDONESIA’S COGENERATION POWER PLANT FOR INDUSTRIAL PROCESSES
Indonesia’s cogeneration power plant for industrial processes (PeLUIt) is needed to be implemented in Indonesia. Economic analysis is an important factor for PeLUIt implementation. One of the data that needs in the analysis is overnight cost. This research estimates HTGR’s overnight cost by using scaling law.By using the estimated value, it can be calculated the PeLUIt overnight cost. The research’s purpose is to obtain an estimation of overnight costs of PeLUIt. The estimation result shows the overnight cost of PeLUIt. PeLUIt 10 MWth has an overnight cost 166,26 million USD. PeLUIt 30 MWth has an overnight cost 233,49 million USD. PeLUIt 50 MWth has an overnight cost 281,31 million USD. PeLUIt 100 MWth has an overnight cost 371,86 million USD. PeLUIt 350 MWth has an overnight cost 657,16 million USD.Keywords: PeLUIt; Estimation; High temperature gas-cooled reactor; Overnight cost; Scaling law
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信