{"title":"MTO-ETO混合生产系统中关键工位的产能规划:以西门子公司为例","authors":"L. Zschorn, Steve Müller, D. Ivanov","doi":"10.1504/IJIR.2017.10009643","DOIUrl":null,"url":null,"abstract":"The focus of this study is on tactical-level capacity management which refers to the determination of in-house workforce production capacity in an optimal cost-efficient manner in a multi-period mode. Two options for capacity planning are investigated for rapid prototyping with the help of a mixed-integer linear optimisation model: smoothing the capacity utilisation over time vs. a higher level of capacity availability. A sensitivity analysis based on real empirical data in Siemens AG is used for the revealing the impact of workforce and capacity flexibility on operational performance. The results suggest that the number of workers decreases if production orders have not to be completed within only one week. On the contrary, if the binary restriction on the order fulfilment within one week is released, the production orders can be split into different weeks and this results in a higher smoothing rate and thus in a higher capacity utilisation degree.","PeriodicalId":113309,"journal":{"name":"International Journal of Inventory Research","volume":"46 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-12-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":"{\"title\":\"Capacity planning on key work stations in a hybrid MTO-ETO production system: a case-study on Siemens AG\",\"authors\":\"L. Zschorn, Steve Müller, D. Ivanov\",\"doi\":\"10.1504/IJIR.2017.10009643\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The focus of this study is on tactical-level capacity management which refers to the determination of in-house workforce production capacity in an optimal cost-efficient manner in a multi-period mode. Two options for capacity planning are investigated for rapid prototyping with the help of a mixed-integer linear optimisation model: smoothing the capacity utilisation over time vs. a higher level of capacity availability. A sensitivity analysis based on real empirical data in Siemens AG is used for the revealing the impact of workforce and capacity flexibility on operational performance. The results suggest that the number of workers decreases if production orders have not to be completed within only one week. On the contrary, if the binary restriction on the order fulfilment within one week is released, the production orders can be split into different weeks and this results in a higher smoothing rate and thus in a higher capacity utilisation degree.\",\"PeriodicalId\":113309,\"journal\":{\"name\":\"International Journal of Inventory Research\",\"volume\":\"46 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-12-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"4\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Inventory Research\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1504/IJIR.2017.10009643\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Inventory Research","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/IJIR.2017.10009643","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Capacity planning on key work stations in a hybrid MTO-ETO production system: a case-study on Siemens AG
The focus of this study is on tactical-level capacity management which refers to the determination of in-house workforce production capacity in an optimal cost-efficient manner in a multi-period mode. Two options for capacity planning are investigated for rapid prototyping with the help of a mixed-integer linear optimisation model: smoothing the capacity utilisation over time vs. a higher level of capacity availability. A sensitivity analysis based on real empirical data in Siemens AG is used for the revealing the impact of workforce and capacity flexibility on operational performance. The results suggest that the number of workers decreases if production orders have not to be completed within only one week. On the contrary, if the binary restriction on the order fulfilment within one week is released, the production orders can be split into different weeks and this results in a higher smoothing rate and thus in a higher capacity utilisation degree.