新型RCD和MPD技术可实现泄漏悬浮井的安全再入和退役

Gabriela Luisa Carvalho, A. Adenipekun, Sasa Ignjatic, Angus Hunter, T. Clay, Emil Stoian
{"title":"新型RCD和MPD技术可实现泄漏悬浮井的安全再入和退役","authors":"Gabriela Luisa Carvalho, A. Adenipekun, Sasa Ignjatic, Angus Hunter, T. Clay, Emil Stoian","doi":"10.2118/195718-MS","DOIUrl":null,"url":null,"abstract":"\n A long-term suspended subsea exploration well within a producing gas reservoir needed to be decommissioned after 21 years. During a pre-decommissioning diving campaign, bubbles confirmed as reservoir gas were observed to be percolating from the well bore through a hard silt / cement debris plug inside the wellhead. A pressure study established that the reservoir may have re-charged to 2,200 psi. An alternative pressure controlled well re-entry method was required to safely re-enter, tie-back the well to surface with 16-in. high pressure riser, install BOP while preventing gas from reaching the rig floor from seabed. Two existing cement plugs would then be drilled out under controlled conditions due to the potential for high-pressure gas beneath the plugs. Casing integrity evaluation and cement bond logging would be carried out to establish the path of gas ingress into the wellbore. Remedial work would be conducted, and permanent abandonment barriers installed in the well. Casings and wellheads would then be recovered from a depth below the seabed.\n A customized managed pressure drilling (MPD) system was designed using a rotating control device (RCD) and modified drilling chokes. A pioneering plan was developed to meet the specific well re-entry requirements of the percolating suspended well to account for the potential for virgin reservoir pressure at seabed and the wellhead silt plug preventing deployment of BOP test tools. A hazard and operability study (HAZOP) was conducted with key personnel, which supported development of well-specific operating procedures and decision matrices. Successful deployment included MPD system calibration, well behavior fingerprinting, and training of rig personnel at the well site.\n The combination of experienced personnel, innovative MPD equipment, specific procedures, team interactions and risk analyses were key to safely completing this well re-entry and decommissioning scope. The strategy enabled drilling out of two cement plugs with potential high-pressure gas trapped beneath them. Both cement plugs, 356ft and 669ft long, were drilled without any well-control or plugged-choke events. Throughout the process, the well was monitored using MPD equipment, which included an RCD on top of rig's BOP, modular drilling chokes and multiple pressure gauges and sensors installed at critical points. Additionally, temporary modifications were made to the rig and new lines of communication between the rig crew and the MPD team were established to ensure all pressures were correctly interpreted and the decision matrix was correctly applied. An effective close partnership developed between the equipment service provider, well operator and drilling contractor was a key enabler to deliver this very challenging novel implementation of MPD technology within eight weeks. The MPD approach was estimated to have saved 9 days of rig time, when compared to alternative coiled tubing-based solutions.\n This paper describes the first MPD-assisted well re-entry for well decommissioning in the UK North Sea sector. The novel application of existing technology can help operators to cost effectively re-enter and decommission troublesome legacy wells without harm to people, environment or assets. This new approach resulted in the safe unconventional re-entry and decommissioning of a potentially live gas well.","PeriodicalId":332235,"journal":{"name":"Day 4 Fri, September 06, 2019","volume":"21 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-09-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Novel RCD and MPD Techniques Enable Safe Re-Entry and Decommissioning of a Leaking Suspended Well\",\"authors\":\"Gabriela Luisa Carvalho, A. Adenipekun, Sasa Ignjatic, Angus Hunter, T. Clay, Emil Stoian\",\"doi\":\"10.2118/195718-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n A long-term suspended subsea exploration well within a producing gas reservoir needed to be decommissioned after 21 years. During a pre-decommissioning diving campaign, bubbles confirmed as reservoir gas were observed to be percolating from the well bore through a hard silt / cement debris plug inside the wellhead. A pressure study established that the reservoir may have re-charged to 2,200 psi. An alternative pressure controlled well re-entry method was required to safely re-enter, tie-back the well to surface with 16-in. high pressure riser, install BOP while preventing gas from reaching the rig floor from seabed. Two existing cement plugs would then be drilled out under controlled conditions due to the potential for high-pressure gas beneath the plugs. Casing integrity evaluation and cement bond logging would be carried out to establish the path of gas ingress into the wellbore. Remedial work would be conducted, and permanent abandonment barriers installed in the well. Casings and wellheads would then be recovered from a depth below the seabed.\\n A customized managed pressure drilling (MPD) system was designed using a rotating control device (RCD) and modified drilling chokes. A pioneering plan was developed to meet the specific well re-entry requirements of the percolating suspended well to account for the potential for virgin reservoir pressure at seabed and the wellhead silt plug preventing deployment of BOP test tools. A hazard and operability study (HAZOP) was conducted with key personnel, which supported development of well-specific operating procedures and decision matrices. Successful deployment included MPD system calibration, well behavior fingerprinting, and training of rig personnel at the well site.\\n The combination of experienced personnel, innovative MPD equipment, specific procedures, team interactions and risk analyses were key to safely completing this well re-entry and decommissioning scope. The strategy enabled drilling out of two cement plugs with potential high-pressure gas trapped beneath them. Both cement plugs, 356ft and 669ft long, were drilled without any well-control or plugged-choke events. Throughout the process, the well was monitored using MPD equipment, which included an RCD on top of rig's BOP, modular drilling chokes and multiple pressure gauges and sensors installed at critical points. Additionally, temporary modifications were made to the rig and new lines of communication between the rig crew and the MPD team were established to ensure all pressures were correctly interpreted and the decision matrix was correctly applied. An effective close partnership developed between the equipment service provider, well operator and drilling contractor was a key enabler to deliver this very challenging novel implementation of MPD technology within eight weeks. The MPD approach was estimated to have saved 9 days of rig time, when compared to alternative coiled tubing-based solutions.\\n This paper describes the first MPD-assisted well re-entry for well decommissioning in the UK North Sea sector. The novel application of existing technology can help operators to cost effectively re-enter and decommission troublesome legacy wells without harm to people, environment or assets. This new approach resulted in the safe unconventional re-entry and decommissioning of a potentially live gas well.\",\"PeriodicalId\":332235,\"journal\":{\"name\":\"Day 4 Fri, September 06, 2019\",\"volume\":\"21 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-09-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 4 Fri, September 06, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/195718-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Fri, September 06, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/195718-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

在一个生产气藏中,一个长期停工的海底勘探井需要在21年后退役。在退役前的潜水作业中,观察到气泡通过井口内的硬淤泥/水泥碎屑塞从井筒中渗出,确认为储层气体。一项压力研究表明,储层可能已经重新充至2200 psi。需要另一种压力控制的回井方法来安全回井,并将16-in井回接到地面。高压立管,安装防喷器,同时防止气体从海底到达钻台。由于塞下可能存在高压气体,现有的两个水泥塞将在受控条件下钻出。套管完整性评价和水泥胶结测井将用于确定气体进入井筒的路径。将进行补救工作,并在井中安装永久的废弃屏障。然后,套管和井口将从海底深处回收。使用旋转控制装置(RCD)和改进的钻井扼流圈,设计了定制的控压钻井(MPD)系统。考虑到海底可能存在未开发油藏压力,以及井口淤塞阻碍防喷器测试工具的部署,开发人员制定了一项开创性的计划,以满足渗流悬浮井的特定重返井要求。与关键人员一起进行了危害和可操作性研究(HAZOP),以支持开发特定井的操作程序和决策矩阵。成功的部署包括MPD系统校准、井态指纹识别和井场钻机人员培训。经验丰富的人员、创新的MPD设备、特定的程序、团队互动和风险分析的结合是安全完成该井的关键。该策略能够钻出两个水泥塞,其下方可能存在高压气体。水泥塞的长度分别为356英尺和669英尺,均未发生井控或堵塞事故。在整个过程中,使用MPD设备对井进行监控,其中包括钻机防喷器顶部的RCD,模块化钻井扼流圈以及安装在关键点的多个压力表和传感器。此外,还对钻机进行了临时修改,并在钻机人员和MPD团队之间建立了新的沟通渠道,以确保正确解释所有压力并正确应用决策矩阵。设备服务提供商、作业者和钻井承包商之间建立了有效的密切合作关系,这是在8周内完成这项极具挑战性的新型MPD技术的关键推动因素。与基于连续油管的替代解决方案相比,MPD方法估计节省了9天的钻机时间。本文介绍了英国北海地区首个mpd辅助下的油井再入作业。现有技术的新应用可以帮助运营商经济有效地重新进入和关闭麻烦的遗留井,而不会对人员、环境或资产造成伤害。这种新方法可以安全的重新进入并关闭潜在的活气井。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Novel RCD and MPD Techniques Enable Safe Re-Entry and Decommissioning of a Leaking Suspended Well
A long-term suspended subsea exploration well within a producing gas reservoir needed to be decommissioned after 21 years. During a pre-decommissioning diving campaign, bubbles confirmed as reservoir gas were observed to be percolating from the well bore through a hard silt / cement debris plug inside the wellhead. A pressure study established that the reservoir may have re-charged to 2,200 psi. An alternative pressure controlled well re-entry method was required to safely re-enter, tie-back the well to surface with 16-in. high pressure riser, install BOP while preventing gas from reaching the rig floor from seabed. Two existing cement plugs would then be drilled out under controlled conditions due to the potential for high-pressure gas beneath the plugs. Casing integrity evaluation and cement bond logging would be carried out to establish the path of gas ingress into the wellbore. Remedial work would be conducted, and permanent abandonment barriers installed in the well. Casings and wellheads would then be recovered from a depth below the seabed. A customized managed pressure drilling (MPD) system was designed using a rotating control device (RCD) and modified drilling chokes. A pioneering plan was developed to meet the specific well re-entry requirements of the percolating suspended well to account for the potential for virgin reservoir pressure at seabed and the wellhead silt plug preventing deployment of BOP test tools. A hazard and operability study (HAZOP) was conducted with key personnel, which supported development of well-specific operating procedures and decision matrices. Successful deployment included MPD system calibration, well behavior fingerprinting, and training of rig personnel at the well site. The combination of experienced personnel, innovative MPD equipment, specific procedures, team interactions and risk analyses were key to safely completing this well re-entry and decommissioning scope. The strategy enabled drilling out of two cement plugs with potential high-pressure gas trapped beneath them. Both cement plugs, 356ft and 669ft long, were drilled without any well-control or plugged-choke events. Throughout the process, the well was monitored using MPD equipment, which included an RCD on top of rig's BOP, modular drilling chokes and multiple pressure gauges and sensors installed at critical points. Additionally, temporary modifications were made to the rig and new lines of communication between the rig crew and the MPD team were established to ensure all pressures were correctly interpreted and the decision matrix was correctly applied. An effective close partnership developed between the equipment service provider, well operator and drilling contractor was a key enabler to deliver this very challenging novel implementation of MPD technology within eight weeks. The MPD approach was estimated to have saved 9 days of rig time, when compared to alternative coiled tubing-based solutions. This paper describes the first MPD-assisted well re-entry for well decommissioning in the UK North Sea sector. The novel application of existing technology can help operators to cost effectively re-enter and decommission troublesome legacy wells without harm to people, environment or assets. This new approach resulted in the safe unconventional re-entry and decommissioning of a potentially live gas well.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信