{"title":"增加对并行程序总执行时间的分析","authors":"Dingchao Li, Hiromitsu Takagi, N. Ishii","doi":"10.1109/ISPAN.1994.367175","DOIUrl":null,"url":null,"abstract":"Lower bound on the finishing time of optimal schedules is used as an absolute performance measure of static scheduling heuristics. This paper presents an efficient method of computing such a bound based on estimating overlaps among the execution ranges of tasks in a given task graph and analyzing the delays of tasks on the critical paths of the graph. The computation performed by this method is shown to be of higher quality than that of other known methods. The future work and directions on this topic are also indicated.<<ETX>>","PeriodicalId":142405,"journal":{"name":"Proceedings of the International Symposium on Parallel Architectures, Algorithms and Networks (ISPAN)","volume":"34 4 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1994-12-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Increase analysis in the total execution time of a parallel program\",\"authors\":\"Dingchao Li, Hiromitsu Takagi, N. Ishii\",\"doi\":\"10.1109/ISPAN.1994.367175\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Lower bound on the finishing time of optimal schedules is used as an absolute performance measure of static scheduling heuristics. This paper presents an efficient method of computing such a bound based on estimating overlaps among the execution ranges of tasks in a given task graph and analyzing the delays of tasks on the critical paths of the graph. The computation performed by this method is shown to be of higher quality than that of other known methods. The future work and directions on this topic are also indicated.<<ETX>>\",\"PeriodicalId\":142405,\"journal\":{\"name\":\"Proceedings of the International Symposium on Parallel Architectures, Algorithms and Networks (ISPAN)\",\"volume\":\"34 4 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1994-12-14\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the International Symposium on Parallel Architectures, Algorithms and Networks (ISPAN)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ISPAN.1994.367175\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the International Symposium on Parallel Architectures, Algorithms and Networks (ISPAN)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ISPAN.1994.367175","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Increase analysis in the total execution time of a parallel program
Lower bound on the finishing time of optimal schedules is used as an absolute performance measure of static scheduling heuristics. This paper presents an efficient method of computing such a bound based on estimating overlaps among the execution ranges of tasks in a given task graph and analyzing the delays of tasks on the critical paths of the graph. The computation performed by this method is shown to be of higher quality than that of other known methods. The future work and directions on this topic are also indicated.<>