{"title":"审裁官的决定","authors":"The Rt Hon. Lord Justice Coulson","doi":"10.1093/oso/9780198822110.003.0026","DOIUrl":null,"url":null,"abstract":"Reasons\n It is often forgotten that, under the Scheme for Construction Contracts, the adjudicator is not required to give reasons unless at least one of the parties requires them. Thus it is necessary for one or both of the parties to notify the...","PeriodicalId":434490,"journal":{"name":"Coulson on Construction Adjudication","volume":"309 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-12-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The Adjudicator’s Decision\",\"authors\":\"The Rt Hon. Lord Justice Coulson\",\"doi\":\"10.1093/oso/9780198822110.003.0026\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Reasons\\n It is often forgotten that, under the Scheme for Construction Contracts, the adjudicator is not required to give reasons unless at least one of the parties requires them. Thus it is necessary for one or both of the parties to notify the...\",\"PeriodicalId\":434490,\"journal\":{\"name\":\"Coulson on Construction Adjudication\",\"volume\":\"309 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-12-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Coulson on Construction Adjudication\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1093/oso/9780198822110.003.0026\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Coulson on Construction Adjudication","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1093/oso/9780198822110.003.0026","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Reasons
It is often forgotten that, under the Scheme for Construction Contracts, the adjudicator is not required to give reasons unless at least one of the parties requires them. Thus it is necessary for one or both of the parties to notify the...