{"title":"基于可信度的项目网络风险要素临界度测度的三角模糊数法","authors":"L. Cunbin, W. Jianjun, Li Li, Liu Xueyan","doi":"10.1109/ICRMEM.2008.49","DOIUrl":null,"url":null,"abstract":"A new triangular fuzzy number critical path method was proposed based on linear programming for solving the uncertain project problem. alpha -cut set was used to transfer the fuzzy number to interval number, and a credibility degree was defined so that the total time range and the different critical paths were given by adjusting the credibility degree. Meanwhile, by analyzing the sensitivity coefficient, the control priorities of activities could be acquired. The result shows that compared with traditional probability methods and other related studies, The method can improve the precision of the project time control.","PeriodicalId":430801,"journal":{"name":"2008 International Conference on Risk Management & Engineering Management","volume":"103 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-11-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Triangular Fuzzy Number Method for Measuring Risk Element Criticality by Credibility Degree in Project Network\",\"authors\":\"L. Cunbin, W. Jianjun, Li Li, Liu Xueyan\",\"doi\":\"10.1109/ICRMEM.2008.49\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A new triangular fuzzy number critical path method was proposed based on linear programming for solving the uncertain project problem. alpha -cut set was used to transfer the fuzzy number to interval number, and a credibility degree was defined so that the total time range and the different critical paths were given by adjusting the credibility degree. Meanwhile, by analyzing the sensitivity coefficient, the control priorities of activities could be acquired. The result shows that compared with traditional probability methods and other related studies, The method can improve the precision of the project time control.\",\"PeriodicalId\":430801,\"journal\":{\"name\":\"2008 International Conference on Risk Management & Engineering Management\",\"volume\":\"103 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2008-11-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2008 International Conference on Risk Management & Engineering Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICRMEM.2008.49\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 International Conference on Risk Management & Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICRMEM.2008.49","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Triangular Fuzzy Number Method for Measuring Risk Element Criticality by Credibility Degree in Project Network
A new triangular fuzzy number critical path method was proposed based on linear programming for solving the uncertain project problem. alpha -cut set was used to transfer the fuzzy number to interval number, and a credibility degree was defined so that the total time range and the different critical paths were given by adjusting the credibility degree. Meanwhile, by analyzing the sensitivity coefficient, the control priorities of activities could be acquired. The result shows that compared with traditional probability methods and other related studies, The method can improve the precision of the project time control.