Ilham Juniar Abraham, Ahmad Ridwan, S. Suwarno
{"title":"Percepatan Waktu Pelaksanaan Pembangunan Gedung Rumah Sakit Aisyiyah Kabupaten Ponorogo Menggunakan Metode PERT (Program Evaluation and Review Technique)","authors":"Ilham Juniar Abraham, Ahmad Ridwan, S. Suwarno","doi":"10.30737/jurmateks.v5i1.2843","DOIUrl":null,"url":null,"abstract":"Project scheduling is one of the important factors for successful project implementation that can be achieved in accordance with the initial planning. Problems that can hinder project management are limited resources, inaccurate reports and costly and costly.  The delay in the completion of the project itself is a very undesirable condition, because it can harm both parties both in terms of time or cost.  The purpose of this study is to determine the probability of accelerating the implementation time from the period obtained by taking into account the critical path and calculation of cost crashing in the Aisyiyah Ponorogo Hospital construction project.   The research method used in this study was to analyze the time schedule in the RAB by comparing the project schedule using the PERT (Program Evaluation and Review Technique) method. The data used is the duration of the project time to obtain critical trajectory results, standards and variances. The results of the scheduling analysis with the PERT method obtained a critical path with B-C-D-E-L-M with an acceleration of the implementation time of project activities for 49 weeks on the critical path and a non-critical path for 79 weeks from the planned time.  buildings can speed up implementation time by a possible percentage of 92,073% with efficient calculation of crashing costs with the addition of working hours/overtime at a duration of 49 weeks rather than having to increase labor to achieve this probability.","PeriodicalId":173188,"journal":{"name":"Jurnal Manajemen Teknologi & Teknik Sipil","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-07-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Manajemen Teknologi & Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30737/jurmateks.v5i1.2843","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

项目进度是项目能否按照初始计划顺利实施的重要因素之一。可能阻碍项目管理的问题是有限的资源、不准确的报告和昂贵的成本。项目的延迟完成本身就是一个非常不受欢迎的情况,因为它可以在时间或成本方面损害双方。本研究的目的是在考虑Aisyiyah Ponorogo医院建设项目的关键路径和成本崩溃计算的情况下,确定工期加快实施时间的概率。本研究采用的研究方法是采用PERT (Program Evaluation and Review Technique)方法,通过比较项目进度,分析RAB中的时间进度。所使用的数据是项目时间的持续时间,以获得关键的轨迹结果、标准和方差。利用PERT方法进行进度分析,得到了B-C-D-E-L-M的关键路径,项目活动实施时间在关键路径上加速49周,非关键路径在计划时间上加速79周。在49周的时间内,建筑可以有效地计算崩溃成本,增加工作时间/加班时间,而不是增加劳动力来实现这一概率,从而加快实施时间的百分比可能达到92,03%。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Percepatan Waktu Pelaksanaan Pembangunan Gedung Rumah Sakit Aisyiyah Kabupaten Ponorogo Menggunakan Metode PERT (Program Evaluation and Review Technique)
Project scheduling is one of the important factors for successful project implementation that can be achieved in accordance with the initial planning. Problems that can hinder project management are limited resources, inaccurate reports and costly and costly.  The delay in the completion of the project itself is a very undesirable condition, because it can harm both parties both in terms of time or cost.  The purpose of this study is to determine the probability of accelerating the implementation time from the period obtained by taking into account the critical path and calculation of cost crashing in the Aisyiyah Ponorogo Hospital construction project.   The research method used in this study was to analyze the time schedule in the RAB by comparing the project schedule using the PERT (Program Evaluation and Review Technique) method. The data used is the duration of the project time to obtain critical trajectory results, standards and variances. The results of the scheduling analysis with the PERT method obtained a critical path with B-C-D-E-L-M with an acceleration of the implementation time of project activities for 49 weeks on the critical path and a non-critical path for 79 weeks from the planned time.  buildings can speed up implementation time by a possible percentage of 92,073% with efficient calculation of crashing costs with the addition of working hours/overtime at a duration of 49 weeks rather than having to increase labor to achieve this probability.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信