在恶劣的海岸环境中进行油气建设项目的经验教训

T. Bullock, S. Beale, Ron McCarthy, Hugh Anthony Kelly
{"title":"在恶劣的海岸环境中进行油气建设项目的经验教训","authors":"T. Bullock, S. Beale, Ron McCarthy, Hugh Anthony Kelly","doi":"10.4043/29422-MS","DOIUrl":null,"url":null,"abstract":"\n The Hebron Platform was constructed from 2012 to 2017 in the harsh environment of coastal Newfoundland and Labrador. The construction site experienced winds and seas that approached expected values for a 100-year return period event, unusual non-tidal water levels during topsides / GBS mating, and historically extreme sea ice conditions that delayed tow-to-field operations. Topsides marine operations required data collection and forecasting system enhancements more than 2 years in advance due to the sensitivity of the operations, and the complex topography and climate of the site. Installation offshore was limited by winds, seas and long period swells that could reach the site from remote areas of the Atlantic. A summary of metocean support for the Hebron Platform is presented with lessons learned and comparisons made with the Hibernia Construction Project executed 20 years earlier in the same location.\n Several technologies were applied to the Hebron Project that were not available during the Hibernia Project. Emerging technologies combined with in-situ measurements of atmospheric and oceanic conditions were used to provide operational metocean support for the Hebron Project. Examples of effective processes are described that could apply to similar harsh environments, complex terrains or northern coastal construction projects. There were also technologies attempted which were deemed unfeasible. Complex metocean decision making for an environmentally sensitive oil and gas construction project is described within a quantitative risk assessment framework.\n Embedded experienced metocean personnel used advanced information behind the scenes to improve forecast accuracy and to provide guidance on the timing and likelihood of threshold-exceedance events. It was demonstrated that an effective metocean decision making process was highly dependent on forecast magnitude and timing accuracy at various forecast horizons. It was found that specific operational parameters and governing, operational weather windows for the Hebron Project were achieved with minimal waiting on weather due to a ‘go/no-go’ decision making process which was based on confidence in the forecast accuracy, and a risk assessment system that embedded metocean specialists with the relevant event-likelihood information. Operational delays due to unreliable forecasting would have led to significant delays, personnel and equipment downtime, and cost over-runs for the Hebron Project.\n Weather forecasting in support of the Hebron Project demonstrated that metocean analytic and predictive science has improved sufficiently over the past 20 years to effectively support oil and gas exploration and development operations that have moved into harsher environments.","PeriodicalId":214691,"journal":{"name":"Day 4 Thu, May 09, 2019","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Metocean Decision Making Lessons-Learned during an Oil & Gas Construction Project Conducted in a Harsh Coastal Environment\",\"authors\":\"T. Bullock, S. Beale, Ron McCarthy, Hugh Anthony Kelly\",\"doi\":\"10.4043/29422-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The Hebron Platform was constructed from 2012 to 2017 in the harsh environment of coastal Newfoundland and Labrador. The construction site experienced winds and seas that approached expected values for a 100-year return period event, unusual non-tidal water levels during topsides / GBS mating, and historically extreme sea ice conditions that delayed tow-to-field operations. Topsides marine operations required data collection and forecasting system enhancements more than 2 years in advance due to the sensitivity of the operations, and the complex topography and climate of the site. Installation offshore was limited by winds, seas and long period swells that could reach the site from remote areas of the Atlantic. A summary of metocean support for the Hebron Platform is presented with lessons learned and comparisons made with the Hibernia Construction Project executed 20 years earlier in the same location.\\n Several technologies were applied to the Hebron Project that were not available during the Hibernia Project. Emerging technologies combined with in-situ measurements of atmospheric and oceanic conditions were used to provide operational metocean support for the Hebron Project. Examples of effective processes are described that could apply to similar harsh environments, complex terrains or northern coastal construction projects. There were also technologies attempted which were deemed unfeasible. Complex metocean decision making for an environmentally sensitive oil and gas construction project is described within a quantitative risk assessment framework.\\n Embedded experienced metocean personnel used advanced information behind the scenes to improve forecast accuracy and to provide guidance on the timing and likelihood of threshold-exceedance events. It was demonstrated that an effective metocean decision making process was highly dependent on forecast magnitude and timing accuracy at various forecast horizons. It was found that specific operational parameters and governing, operational weather windows for the Hebron Project were achieved with minimal waiting on weather due to a ‘go/no-go’ decision making process which was based on confidence in the forecast accuracy, and a risk assessment system that embedded metocean specialists with the relevant event-likelihood information. Operational delays due to unreliable forecasting would have led to significant delays, personnel and equipment downtime, and cost over-runs for the Hebron Project.\\n Weather forecasting in support of the Hebron Project demonstrated that metocean analytic and predictive science has improved sufficiently over the past 20 years to effectively support oil and gas exploration and development operations that have moved into harsher environments.\",\"PeriodicalId\":214691,\"journal\":{\"name\":\"Day 4 Thu, May 09, 2019\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 4 Thu, May 09, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/29422-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 4 Thu, May 09, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29422-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

Hebron平台于2012年至2017年在纽芬兰和拉布拉多沿海的恶劣环境中建造。施工现场经历了接近100年回复期的风和海,在顶部/ GBS配合期间不寻常的非潮汐水位,以及历史上极端的海冰条件,这些都延迟了拖至现场的作业。由于作业的敏感性以及现场复杂的地形和气候,海上作业需要提前2年以上的数据收集和预测系统。海上安装受到风、海洋和长时间的巨浪的限制,这些巨浪可能从大西洋的偏远地区到达现场。总结了Hebron平台的metoocean支持情况,并与20年前在同一地点执行的Hibernia建设项目进行了比较。希布伦项目采用了一些在希伯尼亚项目中没有的技术。新兴技术与大气和海洋条件的现场测量相结合,为希布伦项目提供了业务上的海洋气象支持。描述了适用于类似恶劣环境、复杂地形或北部沿海建设项目的有效过程的例子。还有一些尝试的技术被认为是不可行的。在定量风险评估框架下,描述了环境敏感型油气建设项目复杂的海洋环境决策。嵌入式经验丰富的海洋气象人员在幕后使用先进的信息来提高预报的准确性,并就超过阈值事件的时间和可能性提供指导。结果表明,有效的海洋气象决策过程高度依赖于不同预报层的预报量级和授时精度。研究发现,Hebron项目的具体操作参数和管理、操作天气窗口可以在最小的天气等待下实现,这是由于基于对预测准确性的信心的“进行/不进行”决策过程,以及嵌入了具有相关事件可能性信息的海洋专家的风险评估系统。由于不可靠的预测而导致的操作延迟将导致Hebron项目的重大延误、人员和设备停机以及成本超支。支持希伯伦项目的天气预报表明,在过去的20年里,海洋分析和预测科学已经得到了充分的改进,可以有效地支持在更恶劣环境下的油气勘探和开发作业。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Metocean Decision Making Lessons-Learned during an Oil & Gas Construction Project Conducted in a Harsh Coastal Environment
The Hebron Platform was constructed from 2012 to 2017 in the harsh environment of coastal Newfoundland and Labrador. The construction site experienced winds and seas that approached expected values for a 100-year return period event, unusual non-tidal water levels during topsides / GBS mating, and historically extreme sea ice conditions that delayed tow-to-field operations. Topsides marine operations required data collection and forecasting system enhancements more than 2 years in advance due to the sensitivity of the operations, and the complex topography and climate of the site. Installation offshore was limited by winds, seas and long period swells that could reach the site from remote areas of the Atlantic. A summary of metocean support for the Hebron Platform is presented with lessons learned and comparisons made with the Hibernia Construction Project executed 20 years earlier in the same location. Several technologies were applied to the Hebron Project that were not available during the Hibernia Project. Emerging technologies combined with in-situ measurements of atmospheric and oceanic conditions were used to provide operational metocean support for the Hebron Project. Examples of effective processes are described that could apply to similar harsh environments, complex terrains or northern coastal construction projects. There were also technologies attempted which were deemed unfeasible. Complex metocean decision making for an environmentally sensitive oil and gas construction project is described within a quantitative risk assessment framework. Embedded experienced metocean personnel used advanced information behind the scenes to improve forecast accuracy and to provide guidance on the timing and likelihood of threshold-exceedance events. It was demonstrated that an effective metocean decision making process was highly dependent on forecast magnitude and timing accuracy at various forecast horizons. It was found that specific operational parameters and governing, operational weather windows for the Hebron Project were achieved with minimal waiting on weather due to a ‘go/no-go’ decision making process which was based on confidence in the forecast accuracy, and a risk assessment system that embedded metocean specialists with the relevant event-likelihood information. Operational delays due to unreliable forecasting would have led to significant delays, personnel and equipment downtime, and cost over-runs for the Hebron Project. Weather forecasting in support of the Hebron Project demonstrated that metocean analytic and predictive science has improved sufficiently over the past 20 years to effectively support oil and gas exploration and development operations that have moved into harsher environments.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信