东西伯利亚Srednebotuobinskoye油田多井设计:鱼骨、叉骨和桦树叶

M. Rylance, Y. Tuzov, S. Aliyev, A. Gorbov, I. Galitskiy, D. Makhmutov, V. Grinchenko, R. Sultanov, I. Levanov
{"title":"东西伯利亚Srednebotuobinskoye油田多井设计:鱼骨、叉骨和桦树叶","authors":"M. Rylance, Y. Tuzov, S. Aliyev, A. Gorbov, I. Galitskiy, D. Makhmutov, V. Grinchenko, R. Sultanov, I. Levanov","doi":"10.2118/201849-ms","DOIUrl":null,"url":null,"abstract":"\n The TAAS-Yurakh Neftegazodobycha Company (TYNGD) have been ramping up the drilling activity in the Srednebotuobinskoye oil field in Eastern Siberia, beating new records and delivering audacious targets in multilateral well designs. Drilling activity has ramped-up from 2 to 10 drilling rigs since formation of the JV business in Early 2015. As development drilling has progressed, a number of existing and newly identified challenges have arisen.\n Development of the Srednebotuobinskoye oil field is from the Bt. formation which is a thin oil rim with a massive gas cap. As the horizontal permeability is more than 350 mD this leads to severe challenges in increasing the oil production while restricting the production of associated gas and in order to deal with these challenges, a multilateral project was established to apply the best that this technology can offer. The multilateral well concept was a key approach to successfully develop the field, based on the in-situ risks and required well economics. Many of these issues have been addressed, in a stepwise and logical fashion, and this paper describes how this has been achieved and the progress that has been made to date.\n Economic challenges required that the well construction process be improved in efficiency, increased the individual well productivity and enhanced economic delivery. In order to deliver these efficiencies, the TYNGD Team prioritised a number of initiatives, such as a reduction in the Non-Productive Time (NPT) that is associated with the drilling and well construction process. From vuggy-losses in the overburden, to managing increasing losses and differential sticking within the reservoir; a number of key challenges have been identified; many have been addressed, others are in action and a few remain opportunities.\n In order to manage limited resources as efficiently as possible, and while building a meaningful and sufficiently populated drilling wells database; a simplistic roadmap of the wellbore construction process was created from best practice. This approach allowed TYNGD to prioritize targeting of trials, pilots and techniques to those areas that were most impactful to the overall field development at this stage. Close integration between the drilling and sub-surface teams allowed such ranking/prioritisation to be highly effective. This began with ensuring that the cement integrity was being achieved through the gas-cap region, to ensure that productivity, in the open-hole was assured. Major losses in the overburden were also targeted and prioritised, and a range of options were developed and deployed in order to help minimise issues. In parallel with this, formation damage and well productivity behaviour was also addressed, which has led to the planning and implementation of a number of multilateral field trials.\n Development of the Srednebotuobinskoye oilfield is underway and in order to deliver the most efficient development, drilling optimisation and continuous improvement are the key themes. To date a number of initiatives have been identified and implemented that have improved overall performance and resulted in significant economic enhancement. This paper will summarise the approaches taken in developing the field and multilateral well design; the results of implementation to date, as well as identifying and outlining potential further opportunities that are either currently in execution, consideration or planning.","PeriodicalId":359083,"journal":{"name":"Day 2 Tue, October 27, 2020","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-10-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Fishbones, Wishbones and Birch-Leaves, Multilateral Well Design on the Srednebotuobinskoye Field in Eastern Siberia\",\"authors\":\"M. Rylance, Y. Tuzov, S. Aliyev, A. Gorbov, I. Galitskiy, D. Makhmutov, V. Grinchenko, R. Sultanov, I. Levanov\",\"doi\":\"10.2118/201849-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The TAAS-Yurakh Neftegazodobycha Company (TYNGD) have been ramping up the drilling activity in the Srednebotuobinskoye oil field in Eastern Siberia, beating new records and delivering audacious targets in multilateral well designs. Drilling activity has ramped-up from 2 to 10 drilling rigs since formation of the JV business in Early 2015. As development drilling has progressed, a number of existing and newly identified challenges have arisen.\\n Development of the Srednebotuobinskoye oil field is from the Bt. formation which is a thin oil rim with a massive gas cap. As the horizontal permeability is more than 350 mD this leads to severe challenges in increasing the oil production while restricting the production of associated gas and in order to deal with these challenges, a multilateral project was established to apply the best that this technology can offer. The multilateral well concept was a key approach to successfully develop the field, based on the in-situ risks and required well economics. Many of these issues have been addressed, in a stepwise and logical fashion, and this paper describes how this has been achieved and the progress that has been made to date.\\n Economic challenges required that the well construction process be improved in efficiency, increased the individual well productivity and enhanced economic delivery. In order to deliver these efficiencies, the TYNGD Team prioritised a number of initiatives, such as a reduction in the Non-Productive Time (NPT) that is associated with the drilling and well construction process. From vuggy-losses in the overburden, to managing increasing losses and differential sticking within the reservoir; a number of key challenges have been identified; many have been addressed, others are in action and a few remain opportunities.\\n In order to manage limited resources as efficiently as possible, and while building a meaningful and sufficiently populated drilling wells database; a simplistic roadmap of the wellbore construction process was created from best practice. This approach allowed TYNGD to prioritize targeting of trials, pilots and techniques to those areas that were most impactful to the overall field development at this stage. Close integration between the drilling and sub-surface teams allowed such ranking/prioritisation to be highly effective. This began with ensuring that the cement integrity was being achieved through the gas-cap region, to ensure that productivity, in the open-hole was assured. Major losses in the overburden were also targeted and prioritised, and a range of options were developed and deployed in order to help minimise issues. In parallel with this, formation damage and well productivity behaviour was also addressed, which has led to the planning and implementation of a number of multilateral field trials.\\n Development of the Srednebotuobinskoye oilfield is underway and in order to deliver the most efficient development, drilling optimisation and continuous improvement are the key themes. To date a number of initiatives have been identified and implemented that have improved overall performance and resulted in significant economic enhancement. This paper will summarise the approaches taken in developing the field and multilateral well design; the results of implementation to date, as well as identifying and outlining potential further opportunities that are either currently in execution, consideration or planning.\",\"PeriodicalId\":359083,\"journal\":{\"name\":\"Day 2 Tue, October 27, 2020\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-10-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, October 27, 2020\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/201849-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, October 27, 2020","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/201849-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

TAAS-Yurakh Neftegazodobycha公司(TYNGD)一直在加大西伯利亚东部Srednebotuobinskoye油田的钻探活动,打破了新的纪录,并在多边井设计中实现了大胆的目标。自2015年初成立合资公司以来,钻井活动已从2台增加到10台。随着开发钻井的进行,出现了许多现有的和新发现的挑战。Srednebotuobinskoye油田的开发来自bt地层,这是一个具有大量气顶的薄油环。由于水平渗透率超过350 mD,这给增加石油产量带来了严峻的挑战,同时限制了伴生气的生产,为了应对这些挑战,建立了一个多边项目,以应用该技术所能提供的最佳技术。考虑到现场风险和所需井的经济效益,多边井概念是成功开发该油田的关键方法。这些问题中的许多已经以一种逐步和合乎逻辑的方式得到了解决,本文描述了如何实现这一目标以及迄今为止所取得的进展。经济方面的挑战要求提高建井过程的效率,提高单井产能,提高经济产出。为了实现这些效率,TYNGD团队优先考虑了一些措施,例如减少与钻井和建井过程相关的非生产时间(NPT)。从覆盖层的孔洞损失,到管理储层内不断增加的损失和差异粘滞;已经确定了一些关键挑战;许多问题已得到解决,其他问题正在采取行动,少数问题仍有机会。为了尽可能有效地管理有限的资源,同时建立一个有意义且人口充足的钻井数据库;根据最佳实践创建了井筒施工过程的简化路线图。这种方法使TYNGD能够优先考虑在该阶段对整个油田开发影响最大的领域进行试验、试点和技术。钻井和地下团队之间的紧密结合使得这种排序/优先级非常有效。首先要确保在气顶区域实现水泥的完整性,以确保裸眼井的产能。针对覆盖层的主要损失也进行了定位和优先处理,并开发和部署了一系列选择,以帮助最大限度地减少问题。与此同时,还解决了地层损害和油井产能的问题,这导致了一系列多边现场试验的规划和实施。Srednebotuobinskoye油田的开发正在进行中,为了实现最有效的开发,钻井优化和持续改进是关键主题。迄今为止,已经确定并实施了一些举措,这些举措改善了总体绩效,并显著提高了经济效益。本文将总结油田开发和多边井设计所采取的方法;迄今为止的执行结果,以及确定和概述目前正在执行、考虑或规划中的潜在进一步机会。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Fishbones, Wishbones and Birch-Leaves, Multilateral Well Design on the Srednebotuobinskoye Field in Eastern Siberia
The TAAS-Yurakh Neftegazodobycha Company (TYNGD) have been ramping up the drilling activity in the Srednebotuobinskoye oil field in Eastern Siberia, beating new records and delivering audacious targets in multilateral well designs. Drilling activity has ramped-up from 2 to 10 drilling rigs since formation of the JV business in Early 2015. As development drilling has progressed, a number of existing and newly identified challenges have arisen. Development of the Srednebotuobinskoye oil field is from the Bt. formation which is a thin oil rim with a massive gas cap. As the horizontal permeability is more than 350 mD this leads to severe challenges in increasing the oil production while restricting the production of associated gas and in order to deal with these challenges, a multilateral project was established to apply the best that this technology can offer. The multilateral well concept was a key approach to successfully develop the field, based on the in-situ risks and required well economics. Many of these issues have been addressed, in a stepwise and logical fashion, and this paper describes how this has been achieved and the progress that has been made to date. Economic challenges required that the well construction process be improved in efficiency, increased the individual well productivity and enhanced economic delivery. In order to deliver these efficiencies, the TYNGD Team prioritised a number of initiatives, such as a reduction in the Non-Productive Time (NPT) that is associated with the drilling and well construction process. From vuggy-losses in the overburden, to managing increasing losses and differential sticking within the reservoir; a number of key challenges have been identified; many have been addressed, others are in action and a few remain opportunities. In order to manage limited resources as efficiently as possible, and while building a meaningful and sufficiently populated drilling wells database; a simplistic roadmap of the wellbore construction process was created from best practice. This approach allowed TYNGD to prioritize targeting of trials, pilots and techniques to those areas that were most impactful to the overall field development at this stage. Close integration between the drilling and sub-surface teams allowed such ranking/prioritisation to be highly effective. This began with ensuring that the cement integrity was being achieved through the gas-cap region, to ensure that productivity, in the open-hole was assured. Major losses in the overburden were also targeted and prioritised, and a range of options were developed and deployed in order to help minimise issues. In parallel with this, formation damage and well productivity behaviour was also addressed, which has led to the planning and implementation of a number of multilateral field trials. Development of the Srednebotuobinskoye oilfield is underway and in order to deliver the most efficient development, drilling optimisation and continuous improvement are the key themes. To date a number of initiatives have been identified and implemented that have improved overall performance and resulted in significant economic enhancement. This paper will summarise the approaches taken in developing the field and multilateral well design; the results of implementation to date, as well as identifying and outlining potential further opportunities that are either currently in execution, consideration or planning.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信