{"title":"基于解释结构模型的建筑工程延误原因分析:葡萄牙案例","authors":"Amílcar Arantes, L. Ferreira","doi":"10.5220/0010315303660374","DOIUrl":null,"url":null,"abstract":"Delays are a common issue in construction projects worldwide, and they can frequently have an influence on time and cost overruns, among other problems. This study aims to add to the knowledge on construction project management theory and practice by identifying the leading causes of Delays in Construction Projects (DCP) in Portugal, modeling their interrelationships, and determining their main causes. The study presented herein adopted a two-phase methodology. First, based on the literature, the causes of DCP in Portugal are identified. Then the hierarchical structure of the causes of DCP is determined, using integrated Interpretive Structural Modelling (ISM), and an ISM-based Model is developed. The results show that the 16 causes of DCP taken into consideration are hierarchized in six different influence levels. The causes Bidding and contract award process and Lack of communication between parties are the most influential causes, and are thus considered to be the root causes of DCP in Portugal. Additionally, the results show that the causes of DCP can be divided into four different categories relating to Relationships and contract, Material, the Developer, and the Contractor. Finally, these results provide fundamental insights for practitioners and researchers to develop effective measures to mitigate the causes of DCP.","PeriodicalId":235376,"journal":{"name":"International Conference on Operations Research and Enterprise Systems","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case\",\"authors\":\"Amílcar Arantes, L. Ferreira\",\"doi\":\"10.5220/0010315303660374\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Delays are a common issue in construction projects worldwide, and they can frequently have an influence on time and cost overruns, among other problems. This study aims to add to the knowledge on construction project management theory and practice by identifying the leading causes of Delays in Construction Projects (DCP) in Portugal, modeling their interrelationships, and determining their main causes. The study presented herein adopted a two-phase methodology. First, based on the literature, the causes of DCP in Portugal are identified. Then the hierarchical structure of the causes of DCP is determined, using integrated Interpretive Structural Modelling (ISM), and an ISM-based Model is developed. The results show that the 16 causes of DCP taken into consideration are hierarchized in six different influence levels. The causes Bidding and contract award process and Lack of communication between parties are the most influential causes, and are thus considered to be the root causes of DCP in Portugal. Additionally, the results show that the causes of DCP can be divided into four different categories relating to Relationships and contract, Material, the Developer, and the Contractor. Finally, these results provide fundamental insights for practitioners and researchers to develop effective measures to mitigate the causes of DCP.\",\"PeriodicalId\":235376,\"journal\":{\"name\":\"International Conference on Operations Research and Enterprise Systems\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Conference on Operations Research and Enterprise Systems\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5220/0010315303660374\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Conference on Operations Research and Enterprise Systems","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5220/0010315303660374","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

在世界各地的建设项目中,延迟是一个常见的问题,它们经常会对时间和成本超支产生影响,以及其他问题。本研究旨在通过确定葡萄牙建筑项目延迟(DCP)的主要原因,建立其相互关系模型,并确定其主要原因,从而增加建筑项目管理理论和实践的知识。本研究采用两阶段方法。首先,根据文献,葡萄牙DCP的原因被确定。利用综合解释结构模型(ISM)确定了DCP成因的层次结构,建立了基于ISM的DCP成因模型。结果表明,所考虑的16个DCP原因可分为6个不同的影响等级。投标和合同授予过程以及双方之间缺乏沟通是影响最大的原因,因此被认为是葡萄牙DCP的根本原因。此外,结果表明,DCP的原因可以分为与关系和合同、材料、开发商和承包商有关的四种不同类型。最后,这些结果为从业者和研究人员制定有效的措施来减轻DCP的原因提供了基本的见解。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Interpretive Structural Model-based for Analysis of Causes of Delays in Construction Projects: The Portuguese Case
Delays are a common issue in construction projects worldwide, and they can frequently have an influence on time and cost overruns, among other problems. This study aims to add to the knowledge on construction project management theory and practice by identifying the leading causes of Delays in Construction Projects (DCP) in Portugal, modeling their interrelationships, and determining their main causes. The study presented herein adopted a two-phase methodology. First, based on the literature, the causes of DCP in Portugal are identified. Then the hierarchical structure of the causes of DCP is determined, using integrated Interpretive Structural Modelling (ISM), and an ISM-based Model is developed. The results show that the 16 causes of DCP taken into consideration are hierarchized in six different influence levels. The causes Bidding and contract award process and Lack of communication between parties are the most influential causes, and are thus considered to be the root causes of DCP in Portugal. Additionally, the results show that the causes of DCP can be divided into four different categories relating to Relationships and contract, Material, the Developer, and the Contractor. Finally, these results provide fundamental insights for practitioners and researchers to develop effective measures to mitigate the causes of DCP.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信