{"title":"用于水电站维修和翻新规划的集成工具","authors":"B. Mo, E. Solvang, J. Heggset, D. Nordgård, A. Haugstad","doi":"10.1201/9781003078722-15","DOIUrl":null,"url":null,"abstract":"Optimal investment in maintenance and refurbishment of hydropower plants is very complicated. This paper describes a new model currently under development. The model consists of several modules, each solving separate tasks and passing on necessary information to the other modules. There is a module for computation of losses from disrupted production caused by forced outages, a module for computation of production losses during maintenance, a module for specification of unit (i.e. turbine, generator and control system) failure probabilities as functions of time, a module for presentation and evaluation of qualitative criteria and finally a module for optimal timing of projects. The whole concept is adapted to decision makers who own many production units, although parts of the system may also be useful for smaller utilities.","PeriodicalId":357593,"journal":{"name":"Hydropower in the New Millennium","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-12-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Integrated tool for maintenance and refurbishment planning of hydropower plants\",\"authors\":\"B. Mo, E. Solvang, J. Heggset, D. Nordgård, A. Haugstad\",\"doi\":\"10.1201/9781003078722-15\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Optimal investment in maintenance and refurbishment of hydropower plants is very complicated. This paper describes a new model currently under development. The model consists of several modules, each solving separate tasks and passing on necessary information to the other modules. There is a module for computation of losses from disrupted production caused by forced outages, a module for computation of production losses during maintenance, a module for specification of unit (i.e. turbine, generator and control system) failure probabilities as functions of time, a module for presentation and evaluation of qualitative criteria and finally a module for optimal timing of projects. The whole concept is adapted to decision makers who own many production units, although parts of the system may also be useful for smaller utilities.\",\"PeriodicalId\":357593,\"journal\":{\"name\":\"Hydropower in the New Millennium\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2020-12-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Hydropower in the New Millennium\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1201/9781003078722-15\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Hydropower in the New Millennium","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1201/9781003078722-15","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

水电站维修改造投资优化是一个非常复杂的问题。本文描述了目前正在开发的一种新模型。该模型由几个模块组成,每个模块解决单独的任务,并将必要的信息传递给其他模块。有一个模块用于计算因强制停机造成的生产中断造成的损失,一个模块用于计算维修期间的生产损失,一个模块用于指定单元(即涡轮机,发电机和控制系统)故障概率作为时间函数,一个模块用于表示和评估定性标准,最后一个模块用于项目的最佳时机。整个概念适用于拥有许多生产单位的决策者,尽管系统的某些部分也可能对较小的公用事业公司有用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Integrated tool for maintenance and refurbishment planning of hydropower plants
Optimal investment in maintenance and refurbishment of hydropower plants is very complicated. This paper describes a new model currently under development. The model consists of several modules, each solving separate tasks and passing on necessary information to the other modules. There is a module for computation of losses from disrupted production caused by forced outages, a module for computation of production losses during maintenance, a module for specification of unit (i.e. turbine, generator and control system) failure probabilities as functions of time, a module for presentation and evaluation of qualitative criteria and finally a module for optimal timing of projects. The whole concept is adapted to decision makers who own many production units, although parts of the system may also be useful for smaller utilities.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信