M. Christoforidis, B. Awobamise, S. Tong, R. Frowd, F. Rahimi
{"title":"瑞士铁路短期水力发电和立交合同调度","authors":"M. Christoforidis, B. Awobamise, S. Tong, R. Frowd, F. Rahimi","doi":"10.1109/PICA.1995.515177","DOIUrl":null,"url":null,"abstract":"This paper describes the short-term resource scheduling (STRS) function that has been developed by Siemens-Empros as part of the new SBB/Direktion Kraftwerk (Swiss Rail) energy management system. Optimal scheduling of the single-phase hydroelectric power plants, single-phase and three-phase energy accounts, and purchase and sale of three phase energy subject to a multitude of physical and contractual constraints (including spinning and regulating reserve requirements), is the main objective of the STRS function. The operations planning horizon of STRS is one day to one week using an hourly time increment.","PeriodicalId":294493,"journal":{"name":"Proceedings of Power Industry Computer Applications Conference","volume":"17 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1995-05-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"26","resultStr":"{\"title\":\"Short-term hydro generation and interchange contract scheduling for Swiss Rail\",\"authors\":\"M. Christoforidis, B. Awobamise, S. Tong, R. Frowd, F. Rahimi\",\"doi\":\"10.1109/PICA.1995.515177\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper describes the short-term resource scheduling (STRS) function that has been developed by Siemens-Empros as part of the new SBB/Direktion Kraftwerk (Swiss Rail) energy management system. Optimal scheduling of the single-phase hydroelectric power plants, single-phase and three-phase energy accounts, and purchase and sale of three phase energy subject to a multitude of physical and contractual constraints (including spinning and regulating reserve requirements), is the main objective of the STRS function. The operations planning horizon of STRS is one day to one week using an hourly time increment.\",\"PeriodicalId\":294493,\"journal\":{\"name\":\"Proceedings of Power Industry Computer Applications Conference\",\"volume\":\"17 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1995-05-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"26\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of Power Industry Computer Applications Conference\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/PICA.1995.515177\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of Power Industry Computer Applications Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PICA.1995.515177","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 26
摘要
本文介绍了Siemens-Empros开发的短期资源调度(STRS)功能,该功能是新的SBB/ direction Kraftwerk(瑞士铁路)能源管理系统的一部分。STRS功能的主要目标是对单相水电站、单相和三相能源账户以及受多种物理和合同约束(包括旋转和调节储备要求)的三相能源的购买和销售进行优化调度。STRS的操作计划范围是一天到一周,使用小时时间增量。
Short-term hydro generation and interchange contract scheduling for Swiss Rail
This paper describes the short-term resource scheduling (STRS) function that has been developed by Siemens-Empros as part of the new SBB/Direktion Kraftwerk (Swiss Rail) energy management system. Optimal scheduling of the single-phase hydroelectric power plants, single-phase and three-phase energy accounts, and purchase and sale of three phase energy subject to a multitude of physical and contractual constraints (including spinning and regulating reserve requirements), is the main objective of the STRS function. The operations planning horizon of STRS is one day to one week using an hourly time increment.