{"title":"成本","authors":"Adrian Winstanley","doi":"10.54648/bcdr2020008","DOIUrl":null,"url":null,"abstract":"Article 5: Case management fee\n5.1 As soon as practicable after the submission of the Response or, if no Response is submitted, after the time for submission of a Response has elapsed, the Chamber shall direct the parties to pay the case management fee prescribed by the Fee Schedule (the ‘Case Management Fee’), which shall be paid by the party or parties directed to pay it no later than the deadline set by the Chamber for the payment.\n5.2 The Case Management Fee shall be increased correspondingly if the amount of a monetary claim or counterclaim is increased at any time during the arbitration, in which case, the amount of any such increase will be included in an advance on costs directed by the Chamber in accordance with Article 30.1.\n5.3 The Chamber shall, in its sole discretion, direct the parties to pay the Case Management Fee in such proportions as it deems appropriate, taking account of all the circumstances of the dispute.\n5.4 If the Case Management Fee is not paid promptly and in full, the Chamber may suspend or terminate the proceedings.\nArticle 30:Advances on costs\n30.1 Promptly upon the notification of the appointment of the arbitral tribunal in accordance with Article 9.10, and from time to time thereafter during the arbitration, the Chamber shall direct the parties to pay appropriate amounts as an advance for the costs of the arbitration, other than the parties’ own legal and other costs.\n30.2 If the payments directed are not made promptly and in full, the Chamber shall so inform the parties in order that one or more of them may make the required payment. If such payment is not made, the arbitral tribunal may, after consultation with the Chamber, order the suspension or termination of the proceedings.\n30.3 Failure by a party asserting a claim or counterclaim to make the required payment may be deemed by the arbitral tribunal a withdrawal of the claim or counterclaim.","PeriodicalId":166341,"journal":{"name":"BCDR International Arbitration Review","volume":"17 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Costs\",\"authors\":\"Adrian Winstanley\",\"doi\":\"10.54648/bcdr2020008\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Article 5: Case management fee\\n5.1 As soon as practicable after the submission of the Response or, if no Response is submitted, after the time for submission of a Response has elapsed, the Chamber shall direct the parties to pay the case management fee prescribed by the Fee Schedule (the ‘Case Management Fee’), which shall be paid by the party or parties directed to pay it no later than the deadline set by the Chamber for the payment.\\n5.2 The Case Management Fee shall be increased correspondingly if the amount of a monetary claim or counterclaim is increased at any time during the arbitration, in which case, the amount of any such increase will be included in an advance on costs directed by the Chamber in accordance with Article 30.1.\\n5.3 The Chamber shall, in its sole discretion, direct the parties to pay the Case Management Fee in such proportions as it deems appropriate, taking account of all the circumstances of the dispute.\\n5.4 If the Case Management Fee is not paid promptly and in full, the Chamber may suspend or terminate the proceedings.\\nArticle 30:Advances on costs\\n30.1 Promptly upon the notification of the appointment of the arbitral tribunal in accordance with Article 9.10, and from time to time thereafter during the arbitration, the Chamber shall direct the parties to pay appropriate amounts as an advance for the costs of the arbitration, other than the parties’ own legal and other costs.\\n30.2 If the payments directed are not made promptly and in full, the Chamber shall so inform the parties in order that one or more of them may make the required payment. If such payment is not made, the arbitral tribunal may, after consultation with the Chamber, order the suspension or termination of the proceedings.\\n30.3 Failure by a party asserting a claim or counterclaim to make the required payment may be deemed by the arbitral tribunal a withdrawal of the claim or counterclaim.\",\"PeriodicalId\":166341,\"journal\":{\"name\":\"BCDR International Arbitration Review\",\"volume\":\"17 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-09-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"BCDR International Arbitration Review\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.54648/bcdr2020008\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"BCDR International Arbitration Review","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.54648/bcdr2020008","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Article 5: Case management fee
5.1 As soon as practicable after the submission of the Response or, if no Response is submitted, after the time for submission of a Response has elapsed, the Chamber shall direct the parties to pay the case management fee prescribed by the Fee Schedule (the ‘Case Management Fee’), which shall be paid by the party or parties directed to pay it no later than the deadline set by the Chamber for the payment.
5.2 The Case Management Fee shall be increased correspondingly if the amount of a monetary claim or counterclaim is increased at any time during the arbitration, in which case, the amount of any such increase will be included in an advance on costs directed by the Chamber in accordance with Article 30.1.
5.3 The Chamber shall, in its sole discretion, direct the parties to pay the Case Management Fee in such proportions as it deems appropriate, taking account of all the circumstances of the dispute.
5.4 If the Case Management Fee is not paid promptly and in full, the Chamber may suspend or terminate the proceedings.
Article 30:Advances on costs
30.1 Promptly upon the notification of the appointment of the arbitral tribunal in accordance with Article 9.10, and from time to time thereafter during the arbitration, the Chamber shall direct the parties to pay appropriate amounts as an advance for the costs of the arbitration, other than the parties’ own legal and other costs.
30.2 If the payments directed are not made promptly and in full, the Chamber shall so inform the parties in order that one or more of them may make the required payment. If such payment is not made, the arbitral tribunal may, after consultation with the Chamber, order the suspension or termination of the proceedings.