{"title":"罗马尼亚多瑙河新建悬索桥桥面安装中应用的创新卸载和提升系统","authors":"Fumiya Murano, M. Nakayama, Shinjiro Seki, Yuya Uchida","doi":"10.2749/istanbul.2023.0560","DOIUrl":null,"url":null,"abstract":"This paper describes an innovative unloading and lifting system applied for the deck erection of a new suspension bridge (1120m in main span) across the Danube in Romania, with emphasis on concept design and operation on site. The deck erection was performed in the spring of 2022. In this project, independent unloading and lifting systems were arranged while considering topographical constraints. One of the systems was used for unloading deck segments from the river to the tips of the embankments via a swing operation, whereas another was used to lift the deck segments vertically from the river or embankment to the designated elevations. In general, deck lifting devices equipped with both jacking and carriage system are installed in a cross-gantry manner on main cables. In this project, all structural and mechanical components relevant to deck unloading and lifting operations except clamps anchored to the main cables were integrated at the deck side to pursue light weight and highly mobile devices taking account of irregular deck erection step. As a result, less material and cost effective erection devices were realized compared with dominant gantry systems.","PeriodicalId":237396,"journal":{"name":"IABSE Symposium, Istanbul 2023: Long Span Bridges","volume":"66 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Innovative unloading and lifting system applied for deck erection of new suspension bridge across the Danube river in Romania\",\"authors\":\"Fumiya Murano, M. Nakayama, Shinjiro Seki, Yuya Uchida\",\"doi\":\"10.2749/istanbul.2023.0560\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper describes an innovative unloading and lifting system applied for the deck erection of a new suspension bridge (1120m in main span) across the Danube in Romania, with emphasis on concept design and operation on site. The deck erection was performed in the spring of 2022. In this project, independent unloading and lifting systems were arranged while considering topographical constraints. One of the systems was used for unloading deck segments from the river to the tips of the embankments via a swing operation, whereas another was used to lift the deck segments vertically from the river or embankment to the designated elevations. In general, deck lifting devices equipped with both jacking and carriage system are installed in a cross-gantry manner on main cables. In this project, all structural and mechanical components relevant to deck unloading and lifting operations except clamps anchored to the main cables were integrated at the deck side to pursue light weight and highly mobile devices taking account of irregular deck erection step. As a result, less material and cost effective erection devices were realized compared with dominant gantry systems.\",\"PeriodicalId\":237396,\"journal\":{\"name\":\"IABSE Symposium, Istanbul 2023: Long Span Bridges\",\"volume\":\"66 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IABSE Symposium, Istanbul 2023: Long Span Bridges\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2749/istanbul.2023.0560\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IABSE Symposium, Istanbul 2023: Long Span Bridges","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2749/istanbul.2023.0560","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Innovative unloading and lifting system applied for deck erection of new suspension bridge across the Danube river in Romania
This paper describes an innovative unloading and lifting system applied for the deck erection of a new suspension bridge (1120m in main span) across the Danube in Romania, with emphasis on concept design and operation on site. The deck erection was performed in the spring of 2022. In this project, independent unloading and lifting systems were arranged while considering topographical constraints. One of the systems was used for unloading deck segments from the river to the tips of the embankments via a swing operation, whereas another was used to lift the deck segments vertically from the river or embankment to the designated elevations. In general, deck lifting devices equipped with both jacking and carriage system are installed in a cross-gantry manner on main cables. In this project, all structural and mechanical components relevant to deck unloading and lifting operations except clamps anchored to the main cables were integrated at the deck side to pursue light weight and highly mobile devices taking account of irregular deck erection step. As a result, less material and cost effective erection devices were realized compared with dominant gantry systems.