{"title":"国际指导和管制","authors":"P. E. Pfeifer","doi":"10.2139/ssrn.2975064","DOIUrl":null,"url":null,"abstract":"Thomas Stearns must decide whether to continue with planned software development and risk missing the completion deadline on a $20 million project or bite the bullet and make some costly hardware changes that will virtually eliminate the risk of missing the deadline. This introductory decision analysis case: (1) contains a compound (square-circle-square) decision, (2) encourages a discussion of the meaning of probability, and (3) requires the use of sensitivity analysis to handle the unspecified costs of missing the deadline. \nExcerpt \nUVA-QA-0350 \nINTERNATIONAL GUIDANCE AND CONTROLS \nTime was running out on the $ 20 million CARV (confined aquatic recovery vehicle) project, and Project Manager Thomas Stearns was concerned about maintaining the project's schedule. With 10 months left, considerable portions of the software remained to be developed, and Stearns was by no means certain that all the necessary development work would be completed on time. \nSoftware Development \nStearns had had his project team working full force in recent months on the software development for CARV's command and guidance system. His headcount (the number of full-time-equivalent workers assigned to the project) had been increased recently, so total development costs were running at $ 300,000 per month, which was 25% over the project's budget. Stearns believed that there was but an 80% chance that the necessary software would be completed in the remaining 10 months. Despite the risk of not maintaining the schedule, he could not increase the headcount on the project or increase the rate of software development in any way. \nIf the software were not completed on time, Stearns was fairly certain that one or two extra months of work would suffice to complete the project. Unfortunately, each month's delay in project completion meant a 2.5% ($ 500,000) reduction in the price of the contract. In addition to this precisely defined cost of not meeting the schedule, a hard‑to‑quantify, but no less significant cost of lost reputation was associated with not completing the project as scheduled. \n. . .","PeriodicalId":390041,"journal":{"name":"Darden Case Collection","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"International Guidance and Controls\",\"authors\":\"P. E. Pfeifer\",\"doi\":\"10.2139/ssrn.2975064\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Thomas Stearns must decide whether to continue with planned software development and risk missing the completion deadline on a $20 million project or bite the bullet and make some costly hardware changes that will virtually eliminate the risk of missing the deadline. This introductory decision analysis case: (1) contains a compound (square-circle-square) decision, (2) encourages a discussion of the meaning of probability, and (3) requires the use of sensitivity analysis to handle the unspecified costs of missing the deadline. \\nExcerpt \\nUVA-QA-0350 \\nINTERNATIONAL GUIDANCE AND CONTROLS \\nTime was running out on the $ 20 million CARV (confined aquatic recovery vehicle) project, and Project Manager Thomas Stearns was concerned about maintaining the project's schedule. With 10 months left, considerable portions of the software remained to be developed, and Stearns was by no means certain that all the necessary development work would be completed on time. \\nSoftware Development \\nStearns had had his project team working full force in recent months on the software development for CARV's command and guidance system. His headcount (the number of full-time-equivalent workers assigned to the project) had been increased recently, so total development costs were running at $ 300,000 per month, which was 25% over the project's budget. Stearns believed that there was but an 80% chance that the necessary software would be completed in the remaining 10 months. Despite the risk of not maintaining the schedule, he could not increase the headcount on the project or increase the rate of software development in any way. \\nIf the software were not completed on time, Stearns was fairly certain that one or two extra months of work would suffice to complete the project. Unfortunately, each month's delay in project completion meant a 2.5% ($ 500,000) reduction in the price of the contract. In addition to this precisely defined cost of not meeting the schedule, a hard‑to‑quantify, but no less significant cost of lost reputation was associated with not completing the project as scheduled. \\n. . .\",\"PeriodicalId\":390041,\"journal\":{\"name\":\"Darden Case Collection\",\"volume\":\"16 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Darden Case Collection\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2139/ssrn.2975064\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Darden Case Collection","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2139/ssrn.2975064","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
Thomas Stearns必须决定是继续按计划进行软件开发,冒着错过完成期限的风险,还是咬紧牙关,进行一些昂贵的硬件更改,从而消除错过期限的风险。这个介绍性决策分析案例:(1)包含一个复合(方-圆-方)决策,(2)鼓励对概率含义的讨论,(3)要求使用敏感性分析来处理错过截止日期的未指定成本。价值2000万美元的CARV(限水回收飞行器)项目的时间已经不多了,项目经理Thomas Stearns非常关心项目的进度。在剩下10个月的时间里,软件的相当一部分还有待开发,Stearns并不确定所有必要的开发工作都能按时完成。最近几个月,斯特恩斯已经让他的项目团队在CARV的指挥和制导系统的软件开发上全力以赴。他的员工人数(分配给项目的全职员工的数量)最近有所增加,因此每月的总开发成本为30万美元,超出了项目预算的25%。斯特恩斯认为,在剩下的10个月内完成必要软件的可能性只有80%。尽管有不能维持进度的风险,他不能以任何方式增加项目的人数或增加软件开发的速度。如果软件没有按时完成,Stearns相当肯定,一两个月的额外工作就足够完成这个项目了。不幸的是,项目每延迟一个月就意味着合同价格减少2.5%(50万美元)。除了这个精确定义的不能按时完成的成本之外,一个难以量化的,但同样重要的声誉损失成本与不能如期完成项目. . . .有关
Thomas Stearns must decide whether to continue with planned software development and risk missing the completion deadline on a $20 million project or bite the bullet and make some costly hardware changes that will virtually eliminate the risk of missing the deadline. This introductory decision analysis case: (1) contains a compound (square-circle-square) decision, (2) encourages a discussion of the meaning of probability, and (3) requires the use of sensitivity analysis to handle the unspecified costs of missing the deadline.
Excerpt
UVA-QA-0350
INTERNATIONAL GUIDANCE AND CONTROLS
Time was running out on the $ 20 million CARV (confined aquatic recovery vehicle) project, and Project Manager Thomas Stearns was concerned about maintaining the project's schedule. With 10 months left, considerable portions of the software remained to be developed, and Stearns was by no means certain that all the necessary development work would be completed on time.
Software Development
Stearns had had his project team working full force in recent months on the software development for CARV's command and guidance system. His headcount (the number of full-time-equivalent workers assigned to the project) had been increased recently, so total development costs were running at $ 300,000 per month, which was 25% over the project's budget. Stearns believed that there was but an 80% chance that the necessary software would be completed in the remaining 10 months. Despite the risk of not maintaining the schedule, he could not increase the headcount on the project or increase the rate of software development in any way.
If the software were not completed on time, Stearns was fairly certain that one or two extra months of work would suffice to complete the project. Unfortunately, each month's delay in project completion meant a 2.5% ($ 500,000) reduction in the price of the contract. In addition to this precisely defined cost of not meeting the schedule, a hard‑to‑quantify, but no less significant cost of lost reputation was associated with not completing the project as scheduled.
. . .