{"title":"获得的计划和计划执行报告指标的使用","authors":"P. Beck, Dennis Kovacs","doi":"10.1115/IPC2018-78067","DOIUrl":null,"url":null,"abstract":"The traditional approach of managing project performance is with the use of Earned Value Management. There is a recent trend towards the expansion of traditional Earned Value Management practices to include the concept of Earned Schedule.\n Whereas Earned Value provides insight as to how the project is trending in relation to the plan by assessing cost and schedule variances, Earned Schedule focuses on the time element of schedule performance throughout the project execution phase.\n Earned Value, although very effective at providing visibility to cost performance, is not as transparent when it comes to schedule performance over time. Case in point, at completion, irrespective as to how work progressed on the schedule (ahead or behind plan) at completion, the schedule performance index will always be 1.0.\n Earned Schedule overcomes this drawback, providing useful tools to report on schedule performance, and providing visibility to the project state from which to base informed decisions.\n To perform the analysis, Earned Schedule analysis incorporates detail from the baseline and forecast schedules as well as the integrated project management cost report (earned versus planned). In addition to looking at Earned Schedule metrics, other key metrics are factored into this approach to assess overall schedule performance.\n Key metrics derived from the schedule and highlighted in this approach include:\n • Critical Path Length Index (CPLI)\n • Baseline Execution Index (BEI)\n • Total Float Consumption Index (TFCI)\n • To Complete Schedule Performance Index (TSPI)\n • Predicted Forecast Finish Date (PFFD)\n • Schedule Performance Index (time) (SPIt)\n • Independent Estimate At Complete (time) (IEACt)\n The intent of these metrics is to identify trends and assist in predicting project outcomes based on past performance. Since this approach is highly dependent on the schedule data, the more compliant a schedule is to industry best practices the better the quality of the results. The metrics are negatively impacted by recent re-baselining as this causes us to lose historical performance detail.\n Frequent analysis of the schedule execution reporting metrics defined above provides transparency of project performance and brings visibility to early risk triggers in support of a proactive approach to project execution monitoring and control.\n This paper will present a case study demonstrating how additional transparency through this approach highlighted a potential schedule risk. This increased visibility allowed the project team to reprioritize and implement proactive corrective actions to mitigate any potential impact to the project In Service Date (ISD).","PeriodicalId":164582,"journal":{"name":"Volume 2: Pipeline Safety Management Systems; Project Management, Design, Construction, and Environmental Issues; Strain Based Design; Risk and Reliability; Northern Offshore and Production Pipelines","volume":"89 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-09-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Earned Schedule and the Use of Schedule Execution Reporting Metrics\",\"authors\":\"P. Beck, Dennis Kovacs\",\"doi\":\"10.1115/IPC2018-78067\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The traditional approach of managing project performance is with the use of Earned Value Management. There is a recent trend towards the expansion of traditional Earned Value Management practices to include the concept of Earned Schedule.\\n Whereas Earned Value provides insight as to how the project is trending in relation to the plan by assessing cost and schedule variances, Earned Schedule focuses on the time element of schedule performance throughout the project execution phase.\\n Earned Value, although very effective at providing visibility to cost performance, is not as transparent when it comes to schedule performance over time. Case in point, at completion, irrespective as to how work progressed on the schedule (ahead or behind plan) at completion, the schedule performance index will always be 1.0.\\n Earned Schedule overcomes this drawback, providing useful tools to report on schedule performance, and providing visibility to the project state from which to base informed decisions.\\n To perform the analysis, Earned Schedule analysis incorporates detail from the baseline and forecast schedules as well as the integrated project management cost report (earned versus planned). In addition to looking at Earned Schedule metrics, other key metrics are factored into this approach to assess overall schedule performance.\\n Key metrics derived from the schedule and highlighted in this approach include:\\n • Critical Path Length Index (CPLI)\\n • Baseline Execution Index (BEI)\\n • Total Float Consumption Index (TFCI)\\n • To Complete Schedule Performance Index (TSPI)\\n • Predicted Forecast Finish Date (PFFD)\\n • Schedule Performance Index (time) (SPIt)\\n • Independent Estimate At Complete (time) (IEACt)\\n The intent of these metrics is to identify trends and assist in predicting project outcomes based on past performance. Since this approach is highly dependent on the schedule data, the more compliant a schedule is to industry best practices the better the quality of the results. The metrics are negatively impacted by recent re-baselining as this causes us to lose historical performance detail.\\n Frequent analysis of the schedule execution reporting metrics defined above provides transparency of project performance and brings visibility to early risk triggers in support of a proactive approach to project execution monitoring and control.\\n This paper will present a case study demonstrating how additional transparency through this approach highlighted a potential schedule risk. This increased visibility allowed the project team to reprioritize and implement proactive corrective actions to mitigate any potential impact to the project In Service Date (ISD).\",\"PeriodicalId\":164582,\"journal\":{\"name\":\"Volume 2: Pipeline Safety Management Systems; Project Management, Design, Construction, and Environmental Issues; Strain Based Design; Risk and Reliability; Northern Offshore and Production Pipelines\",\"volume\":\"89 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-09-24\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Volume 2: Pipeline Safety Management Systems; Project Management, Design, Construction, and Environmental Issues; Strain Based Design; Risk and Reliability; Northern Offshore and Production Pipelines\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1115/IPC2018-78067\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Volume 2: Pipeline Safety Management Systems; Project Management, Design, Construction, and Environmental Issues; Strain Based Design; Risk and Reliability; Northern Offshore and Production Pipelines","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/IPC2018-78067","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

管理项目绩效的传统方法是使用挣值管理。最近有一种扩展传统挣值管理实践的趋势,包括挣得计划的概念。挣值通过评估成本和进度差异来洞察项目是如何与计划相关的,而挣值则关注整个项目执行阶段的进度绩效的时间要素。挣值虽然在提供成本性能的可见性方面非常有效,但在涉及到随时间推移的计划性能时就不那么透明了。例如,在完成时,无论工作进度如何(提前或落后于计划),完成时的进度绩效指标始终为1.0。Earned Schedule克服了这个缺点,提供了有用的工具来报告进度执行情况,并提供了对项目状态的可见性,从而可以根据项目状态做出明智的决策。为了执行分析,挣得进度分析结合了基线和预测进度的细节,以及集成的项目管理成本报告(挣得的与计划的)。除了查看获得的进度指标外,其他关键指标也被纳入该方法以评估总体进度绩效。从进度中得出的关键指标,并在此方法中强调包括:•关键路径长度指数(CPLI)•基线执行指数(BEI)•总浮动消耗指数(TFCI)•完成进度绩效指数(TSPI)•预测预测完成日期(PFFD)•进度绩效指数(时间)(SPIt)•完成时独立评估(时间)(IEACt)这些指标的目的是识别趋势并协助预测基于过去绩效的项目结果。由于该方法高度依赖于进度数据,因此进度越符合行业最佳实践,结果的质量就越好。这些指标受到最近重新设定基线的负面影响,因为这会导致我们丢失历史性能细节。对上述定义的进度执行报告度量标准的频繁分析提供了项目绩效的透明度,并带来了对早期风险触发器的可见性,以支持项目执行监视和控制的主动方法。本文将展示一个案例研究,演示通过这种方法增加的透明度如何突出潜在的进度风险。这增加了可见性,使项目团队能够重新确定优先级并实施主动纠正措施,以减轻对项目在役日期(ISD)的任何潜在影响。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Earned Schedule and the Use of Schedule Execution Reporting Metrics
The traditional approach of managing project performance is with the use of Earned Value Management. There is a recent trend towards the expansion of traditional Earned Value Management practices to include the concept of Earned Schedule. Whereas Earned Value provides insight as to how the project is trending in relation to the plan by assessing cost and schedule variances, Earned Schedule focuses on the time element of schedule performance throughout the project execution phase. Earned Value, although very effective at providing visibility to cost performance, is not as transparent when it comes to schedule performance over time. Case in point, at completion, irrespective as to how work progressed on the schedule (ahead or behind plan) at completion, the schedule performance index will always be 1.0. Earned Schedule overcomes this drawback, providing useful tools to report on schedule performance, and providing visibility to the project state from which to base informed decisions. To perform the analysis, Earned Schedule analysis incorporates detail from the baseline and forecast schedules as well as the integrated project management cost report (earned versus planned). In addition to looking at Earned Schedule metrics, other key metrics are factored into this approach to assess overall schedule performance. Key metrics derived from the schedule and highlighted in this approach include: • Critical Path Length Index (CPLI) • Baseline Execution Index (BEI) • Total Float Consumption Index (TFCI) • To Complete Schedule Performance Index (TSPI) • Predicted Forecast Finish Date (PFFD) • Schedule Performance Index (time) (SPIt) • Independent Estimate At Complete (time) (IEACt) The intent of these metrics is to identify trends and assist in predicting project outcomes based on past performance. Since this approach is highly dependent on the schedule data, the more compliant a schedule is to industry best practices the better the quality of the results. The metrics are negatively impacted by recent re-baselining as this causes us to lose historical performance detail. Frequent analysis of the schedule execution reporting metrics defined above provides transparency of project performance and brings visibility to early risk triggers in support of a proactive approach to project execution monitoring and control. This paper will present a case study demonstrating how additional transparency through this approach highlighted a potential schedule risk. This increased visibility allowed the project team to reprioritize and implement proactive corrective actions to mitigate any potential impact to the project In Service Date (ISD).
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信