建筑工程中延期成本回收的考虑

R. Champion
{"title":"建筑工程中延期成本回收的考虑","authors":"R. Champion","doi":"10.1108/17561451111178443","DOIUrl":null,"url":null,"abstract":"Purpose – The purpose of this paper is to review the principles for valuation and proof of contractor's claims for additional site overheads arising from delays to completion of construction projects.Design/methodology/approach – An overview of prolongation costs and established principles for recovery is provided. Aspects of recent decisions are analysed critically with respect to proof of delay claims, site overheads and claims for winter working losses. Findings are compared with the established principles.Findings – Some statements in the judgment in Costain v. Haswell [2010] TCLR 1 with respect to requirements for proof of delay claims and for recovery of site overheads depart from established principles. Other elements of the judgment confirm existing principles. The need to distinguish between time‐ and volume‐related costs emerges as critical in valuation of delay‐related losses.Practical implications – The need for a claimant to establish proof of delays to completion, and proof of loss, particul...","PeriodicalId":158465,"journal":{"name":"International Journal of Law in The Built Environment","volume":"22 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2011-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"A consideration of recovery of prolongation costs in a construction context\",\"authors\":\"R. Champion\",\"doi\":\"10.1108/17561451111178443\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose – The purpose of this paper is to review the principles for valuation and proof of contractor's claims for additional site overheads arising from delays to completion of construction projects.Design/methodology/approach – An overview of prolongation costs and established principles for recovery is provided. Aspects of recent decisions are analysed critically with respect to proof of delay claims, site overheads and claims for winter working losses. Findings are compared with the established principles.Findings – Some statements in the judgment in Costain v. Haswell [2010] TCLR 1 with respect to requirements for proof of delay claims and for recovery of site overheads depart from established principles. Other elements of the judgment confirm existing principles. The need to distinguish between time‐ and volume‐related costs emerges as critical in valuation of delay‐related losses.Practical implications – The need for a claimant to establish proof of delays to completion, and proof of loss, particul...\",\"PeriodicalId\":158465,\"journal\":{\"name\":\"International Journal of Law in The Built Environment\",\"volume\":\"22 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-10-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Law in The Built Environment\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/17561451111178443\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Law in The Built Environment","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/17561451111178443","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

目的-本文件的目的是审查估价原则和证明承包商索赔额外的工地管理费产生的延误,以完成建设项目。设计/方法/方法-提供延长成本的概述和既定的恢复原则。对最近决定的各个方面进行了严格的分析,以证明延误索赔,现场间接费用和冬季工作损失索赔。结果与既定原则进行了比较。调查结果-在Costain v. Haswell [2010] TCLR 1一案中,有关延迟索赔证明要求和现场间接费用回收的判决中的一些陈述偏离了既定原则。判决书的其他内容确认了现有原则。在评估与延误相关的损失时,区分与时间相关的成本和与数量相关的成本是至关重要的。实际影响-索赔人需要建立延迟完成的证明,以及损失证明,特别是…
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A consideration of recovery of prolongation costs in a construction context
Purpose – The purpose of this paper is to review the principles for valuation and proof of contractor's claims for additional site overheads arising from delays to completion of construction projects.Design/methodology/approach – An overview of prolongation costs and established principles for recovery is provided. Aspects of recent decisions are analysed critically with respect to proof of delay claims, site overheads and claims for winter working losses. Findings are compared with the established principles.Findings – Some statements in the judgment in Costain v. Haswell [2010] TCLR 1 with respect to requirements for proof of delay claims and for recovery of site overheads depart from established principles. Other elements of the judgment confirm existing principles. The need to distinguish between time‐ and volume‐related costs emerges as critical in valuation of delay‐related losses.Practical implications – The need for a claimant to establish proof of delays to completion, and proof of loss, particul...
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信