模糊环境下建设项目的时间成本权衡模型研究(以运动称重系统为例)

Solmaz Salehzadeh, A. Mahmoudabadi
{"title":"模糊环境下建设项目的时间成本权衡模型研究(以运动称重系统为例)","authors":"Solmaz Salehzadeh, A. Mahmoudabadi","doi":"10.1504/IJAOM.2018.10015011","DOIUrl":null,"url":null,"abstract":"Completion time is an important issue on construction projects with limited practical duration usually studied comparing to construction or implementation cost. In this research work, the fuzzy behaviour of cost and time for project activities has been investigated based on predicted completion time followed by developing a mathematical model for making a trade-off approach for project planning. The objective function is to minimise project cost which is defined in discrete and continuous domains considering limited implementation time. According to the constraints, a nonlinear model was developed, so a linearisation technique has been utilised to convert that to linear. In addition, an acceptable range of changes (tolerance) is considered for the project completion time to achieve better solutions followed by making a sensitivity analysis process on results of time-cost trading-off approach. Installing a weigh in motion (WIM) system in the central Iranian road of Isfahan-Naein has been selected as case study and the proposed model has been validated using experimental data. Results revealed that the proposed model, which has been converted to linear, is capable to perform a time-cost trading-off approach for projects of those that do not have exact time and cost for project activities.","PeriodicalId":191561,"journal":{"name":"Int. J. Adv. Oper. Manag.","volume":"38 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-08-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Developing a time-cost trading-off model for construction projects in fuzzy environment (case study: weigh in motion system)\",\"authors\":\"Solmaz Salehzadeh, A. Mahmoudabadi\",\"doi\":\"10.1504/IJAOM.2018.10015011\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Completion time is an important issue on construction projects with limited practical duration usually studied comparing to construction or implementation cost. In this research work, the fuzzy behaviour of cost and time for project activities has been investigated based on predicted completion time followed by developing a mathematical model for making a trade-off approach for project planning. The objective function is to minimise project cost which is defined in discrete and continuous domains considering limited implementation time. According to the constraints, a nonlinear model was developed, so a linearisation technique has been utilised to convert that to linear. In addition, an acceptable range of changes (tolerance) is considered for the project completion time to achieve better solutions followed by making a sensitivity analysis process on results of time-cost trading-off approach. Installing a weigh in motion (WIM) system in the central Iranian road of Isfahan-Naein has been selected as case study and the proposed model has been validated using experimental data. Results revealed that the proposed model, which has been converted to linear, is capable to perform a time-cost trading-off approach for projects of those that do not have exact time and cost for project activities.\",\"PeriodicalId\":191561,\"journal\":{\"name\":\"Int. J. Adv. Oper. Manag.\",\"volume\":\"38 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-08-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Int. J. Adv. Oper. Manag.\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1504/IJAOM.2018.10015011\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Int. J. Adv. Oper. Manag.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/IJAOM.2018.10015011","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

在实际工期有限的建设项目中,竣工时间是与施工成本或实施成本相比较研究的一个重要问题。在这项研究工作中,研究了项目活动的成本和时间的模糊行为,基于预测完成时间,然后建立了一个数学模型,为项目计划制定权衡方法。目标函数是考虑有限的实施时间,使项目成本在离散和连续领域中最小化。根据约束条件,建立了非线性模型,利用线性化技术将其转化为线性模型。此外,考虑项目完成时间的可接受变化范围(公差),以获得更好的解决方案,然后对时间-成本折衷方法的结果进行敏感性分析过程。在伊朗中部伊斯法罕-奈因公路上安装动态称重(WIM)系统作为案例研究,并使用实验数据验证了所提出的模型。结果表明,所建议的模型已转换为线性模型,能够为那些没有项目活动的确切时间和成本的项目执行时间-成本折衷方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Developing a time-cost trading-off model for construction projects in fuzzy environment (case study: weigh in motion system)
Completion time is an important issue on construction projects with limited practical duration usually studied comparing to construction or implementation cost. In this research work, the fuzzy behaviour of cost and time for project activities has been investigated based on predicted completion time followed by developing a mathematical model for making a trade-off approach for project planning. The objective function is to minimise project cost which is defined in discrete and continuous domains considering limited implementation time. According to the constraints, a nonlinear model was developed, so a linearisation technique has been utilised to convert that to linear. In addition, an acceptable range of changes (tolerance) is considered for the project completion time to achieve better solutions followed by making a sensitivity analysis process on results of time-cost trading-off approach. Installing a weigh in motion (WIM) system in the central Iranian road of Isfahan-Naein has been selected as case study and the proposed model has been validated using experimental data. Results revealed that the proposed model, which has been converted to linear, is capable to perform a time-cost trading-off approach for projects of those that do not have exact time and cost for project activities.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信