{"title":"软件项目中迭代工作量估算技术的一种方法","authors":"J. Pow-Sang, Enrique Jolay-Vasquez","doi":"10.1109/APSEC.2006.20","DOIUrl":null,"url":null,"abstract":"The estimation of effort and cost is still one of the hardest tasks in software project management. At the moment, there are many techniques to accomplish this task, such as function points, use case points and COCOMO, but there is not much information available about how to use those techniques in non-waterfall software lifecycles such as iterative or spiral lifecycles projects. This paper shows the results obtained when applying a technique to estimate the effort of each construction iteration in software development projects that use iterative-incremental lifecycles. The results were obtained from software projects of a fourth-year course in Informatics. The technique proposes the use of Function Points and COCOMO II.","PeriodicalId":341929,"journal":{"name":"2006 13th Asia Pacific Software Engineering Conference (APSEC'06)","volume":"79 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-12-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"14","resultStr":"{\"title\":\"An Approach of a Technique for Effort Estimation of Iterations in Software Projects\",\"authors\":\"J. Pow-Sang, Enrique Jolay-Vasquez\",\"doi\":\"10.1109/APSEC.2006.20\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The estimation of effort and cost is still one of the hardest tasks in software project management. At the moment, there are many techniques to accomplish this task, such as function points, use case points and COCOMO, but there is not much information available about how to use those techniques in non-waterfall software lifecycles such as iterative or spiral lifecycles projects. This paper shows the results obtained when applying a technique to estimate the effort of each construction iteration in software development projects that use iterative-incremental lifecycles. The results were obtained from software projects of a fourth-year course in Informatics. The technique proposes the use of Function Points and COCOMO II.\",\"PeriodicalId\":341929,\"journal\":{\"name\":\"2006 13th Asia Pacific Software Engineering Conference (APSEC'06)\",\"volume\":\"79 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2006-12-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"14\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2006 13th Asia Pacific Software Engineering Conference (APSEC'06)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/APSEC.2006.20\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2006 13th Asia Pacific Software Engineering Conference (APSEC'06)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/APSEC.2006.20","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 14

摘要

工作量和成本的估算仍然是软件项目管理中最困难的任务之一。目前,有许多技术可以完成这项任务,例如功能点、用例点和COCOMO,但是关于如何在非瀑布式软件生命周期(例如迭代或螺旋生命周期项目)中使用这些技术的可用信息并不多。本文展示了在使用迭代增量生命周期的软件开发项目中,应用一种技术来评估每个构建迭代的工作量时所获得的结果。结果来自信息学四年级课程的软件项目。该技术建议使用功能点和COCOMO II。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
An Approach of a Technique for Effort Estimation of Iterations in Software Projects
The estimation of effort and cost is still one of the hardest tasks in software project management. At the moment, there are many techniques to accomplish this task, such as function points, use case points and COCOMO, but there is not much information available about how to use those techniques in non-waterfall software lifecycles such as iterative or spiral lifecycles projects. This paper shows the results obtained when applying a technique to estimate the effort of each construction iteration in software development projects that use iterative-incremental lifecycles. The results were obtained from software projects of a fourth-year course in Informatics. The technique proposes the use of Function Points and COCOMO II.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书