基于投资、建设和成本核算进度的电网工程进度评价

Ruiguang Ma, Yunping Liu, Qijun Xian, Qianshan Cheng, Yi-han Luo, Chaofeng Cheng
{"title":"基于投资、建设和成本核算进度的电网工程进度评价","authors":"Ruiguang Ma, Yunping Liu, Qijun Xian, Qianshan Cheng, Yi-han Luo, Chaofeng Cheng","doi":"10.1109/ei2.2018.8582369","DOIUrl":null,"url":null,"abstract":"In this paper, the power grid construction project was taken as the research object, and the matching between the project investment progress, construction progress, and cost accounting progress was analyzed. The main reasons for the mismatch between the three progresses were summarized in the aspects of external environment, planning, project construction, and costs accounting management. On this basis, a project whole progress evaluation model based on the matching degree of investment, construction, and costs accounting progresses was constructed, and the overall implementation progresses of some typical power grid construction projects were evaluated. The research results laid a solid foundation for strengthening the monitoring capabilities of the whole process management of power grid construction projects.","PeriodicalId":226809,"journal":{"name":"2018 2nd IEEE Conference on Energy Internet and Energy System Integration (EI2)","volume":"27 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Progress Evaluation of Power Grid Projects Based on Investment, Construction, and Costs Accounting Progress\",\"authors\":\"Ruiguang Ma, Yunping Liu, Qijun Xian, Qianshan Cheng, Yi-han Luo, Chaofeng Cheng\",\"doi\":\"10.1109/ei2.2018.8582369\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this paper, the power grid construction project was taken as the research object, and the matching between the project investment progress, construction progress, and cost accounting progress was analyzed. The main reasons for the mismatch between the three progresses were summarized in the aspects of external environment, planning, project construction, and costs accounting management. On this basis, a project whole progress evaluation model based on the matching degree of investment, construction, and costs accounting progresses was constructed, and the overall implementation progresses of some typical power grid construction projects were evaluated. The research results laid a solid foundation for strengthening the monitoring capabilities of the whole process management of power grid construction projects.\",\"PeriodicalId\":226809,\"journal\":{\"name\":\"2018 2nd IEEE Conference on Energy Internet and Energy System Integration (EI2)\",\"volume\":\"27 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-10-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2018 2nd IEEE Conference on Energy Internet and Energy System Integration (EI2)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ei2.2018.8582369\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 2nd IEEE Conference on Energy Internet and Energy System Integration (EI2)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ei2.2018.8582369","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

本文以电网建设项目为研究对象,分析了项目投资进度、建设进度、成本核算进度之间的匹配关系。从外部环境、规划、项目建设、成本核算管理等方面总结了三个进度不匹配的主要原因。在此基础上,构建了基于投资、建设、成本核算进度匹配度的项目整体进度评价模型,并对部分典型电网建设项目的整体实施进度进行了评价。研究成果为加强电网建设项目全过程管理的监控能力奠定了坚实的基础。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Progress Evaluation of Power Grid Projects Based on Investment, Construction, and Costs Accounting Progress
In this paper, the power grid construction project was taken as the research object, and the matching between the project investment progress, construction progress, and cost accounting progress was analyzed. The main reasons for the mismatch between the three progresses were summarized in the aspects of external environment, planning, project construction, and costs accounting management. On this basis, a project whole progress evaluation model based on the matching degree of investment, construction, and costs accounting progresses was constructed, and the overall implementation progresses of some typical power grid construction projects were evaluated. The research results laid a solid foundation for strengthening the monitoring capabilities of the whole process management of power grid construction projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信