{"title":"成本和时间控制分析与结果价值概念方法在SATPOL PP区的构建项目MAJALENGKA","authors":"Jahar Irawan, Arief Rijaluddin, Eka Juliar","doi":"10.31949/J-ENSITEC.V5I02.1503","DOIUrl":null,"url":null,"abstract":"The success of a project can not be separated from a series of activities that include the stages of planning, implementation and supervision, so that the goals set can be achieved. In an effort to succeed in a construction project, a good technique or management method is needed to improve efficiency, productivity, and quality of work. In connection with that, it is necessary to carry out supervision and control measures in all sectors, especially control of costs and time. This research was conducted at the Majalengka Regency Satpol PP Building Project which aims to determine the project's time performance and the estimated cost and time of the building construction project and the method of concept of the value of the results is effective or not. The data used in this study is the Time Schedule, Cost Budget Plan, and weekly progress reports. From these data can produce BCWP and BCWS values. ACWP, with the help of Microsoft Excel, obtained CP, SV, CPI, SPI, and predicts completion of project costs and end times (ETC, EAC and ECD). From the results of the analysis of the time of the construction of the Satpol PP Building in Majalengka Regency until the 22nd week with a budget of Rp. 2,454,849,000, - resulting in a CPI of 1,1000, SPI obtained at 1,0266, EAC value of Rp. 2.23,681,459.98 and ECD amounted to 126, showing the estimated construction completion time of 126 days, which means the project progressed 24 days from the 150 day plan. Keywords: Earned Value Method, BCWP, BCWS, ETC, EAC","PeriodicalId":448230,"journal":{"name":"J-ENSITEC","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-05-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"ANALISA PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG SATPOL PP KABUPATEN MAJALENGKA\",\"authors\":\"Jahar Irawan, Arief Rijaluddin, Eka Juliar\",\"doi\":\"10.31949/J-ENSITEC.V5I02.1503\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The success of a project can not be separated from a series of activities that include the stages of planning, implementation and supervision, so that the goals set can be achieved. In an effort to succeed in a construction project, a good technique or management method is needed to improve efficiency, productivity, and quality of work. In connection with that, it is necessary to carry out supervision and control measures in all sectors, especially control of costs and time. This research was conducted at the Majalengka Regency Satpol PP Building Project which aims to determine the project's time performance and the estimated cost and time of the building construction project and the method of concept of the value of the results is effective or not. The data used in this study is the Time Schedule, Cost Budget Plan, and weekly progress reports. From these data can produce BCWP and BCWS values. ACWP, with the help of Microsoft Excel, obtained CP, SV, CPI, SPI, and predicts completion of project costs and end times (ETC, EAC and ECD). From the results of the analysis of the time of the construction of the Satpol PP Building in Majalengka Regency until the 22nd week with a budget of Rp. 2,454,849,000, - resulting in a CPI of 1,1000, SPI obtained at 1,0266, EAC value of Rp. 2.23,681,459.98 and ECD amounted to 126, showing the estimated construction completion time of 126 days, which means the project progressed 24 days from the 150 day plan. Keywords: Earned Value Method, BCWP, BCWS, ETC, EAC\",\"PeriodicalId\":448230,\"journal\":{\"name\":\"J-ENSITEC\",\"volume\":\"16 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-05-10\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"J-ENSITEC\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31949/J-ENSITEC.V5I02.1503\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"J-ENSITEC","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31949/J-ENSITEC.V5I02.1503","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
一个项目的成功离不开一系列的活动,包括计划、实施和监督阶段,这样设定的目标才能实现。为了在建设项目中取得成功,需要一种良好的技术或管理方法来提高工作效率、生产力和质量。与此相关的是,有必要在各个环节实施监督和控制措施,特别是成本和时间的控制。本研究是在Majalengka Regency Satpol PP Building Project中进行的,旨在确定项目的时间绩效和建筑施工项目的估计成本和时间,以及结果的价值概念的方法是否有效。本研究中使用的数据是时间进度表、成本预算计划和每周进度报告。从这些数据可以得到BCWP和BCWS值。ACWP借助Microsoft Excel获取CP、SV、CPI、SPI,预测项目成本完成情况和结束时间(ETC、EAC、ECD)。从Majalengka Regency的Satpol PP大楼的建设时间分析结果来看,预算为2,454,849,000卢比,直到第22周,导致CPI为1,1000,SPI为1,0266,EAC值为2,23,681,459.98卢比,ECD为126,显示预计施工完成时间为126天,这意味着该项目从150天的计划进展了24天。关键词:挣值法,BCWP, BCWS等,EAC
ANALISA PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG SATPOL PP KABUPATEN MAJALENGKA
The success of a project can not be separated from a series of activities that include the stages of planning, implementation and supervision, so that the goals set can be achieved. In an effort to succeed in a construction project, a good technique or management method is needed to improve efficiency, productivity, and quality of work. In connection with that, it is necessary to carry out supervision and control measures in all sectors, especially control of costs and time. This research was conducted at the Majalengka Regency Satpol PP Building Project which aims to determine the project's time performance and the estimated cost and time of the building construction project and the method of concept of the value of the results is effective or not. The data used in this study is the Time Schedule, Cost Budget Plan, and weekly progress reports. From these data can produce BCWP and BCWS values. ACWP, with the help of Microsoft Excel, obtained CP, SV, CPI, SPI, and predicts completion of project costs and end times (ETC, EAC and ECD). From the results of the analysis of the time of the construction of the Satpol PP Building in Majalengka Regency until the 22nd week with a budget of Rp. 2,454,849,000, - resulting in a CPI of 1,1000, SPI obtained at 1,0266, EAC value of Rp. 2.23,681,459.98 and ECD amounted to 126, showing the estimated construction completion time of 126 days, which means the project progressed 24 days from the 150 day plan. Keywords: Earned Value Method, BCWP, BCWS, ETC, EAC