{"title":"IBM奥斯汀工业业务中心全面生产维护-开始","authors":"M. Sanderson, M. Shelton, S. Mulligan","doi":"10.1109/IEMT.1993.398201","DOIUrl":null,"url":null,"abstract":"The efforts of IBM Austin Industrial Business Center (AIBC) to adopt total productive maintenance (TPM) as the process for improving quality, increasing production and eliminating waste on the pull production lines (PPLs) are described. Over-all equipment effectiveness (OEE) is seen as the measurement for AIBC improvement activities. The initial introductory conversations with management and early pilot measurement activities are described. The data collection tools used and the resulting analysis of the data collected are shown. The initial benchmark activities are described. The authors describe how they obtained the necessary top-down commitment from management by showing the faults of pilot measurements.<<ETX>>","PeriodicalId":206206,"journal":{"name":"Proceedings of 15th IEEE/CHMT International Electronic Manufacturing Technology Symposium","volume":"63 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1993-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":"{\"title\":\"IBM Austin Industrial Business Center total productive maintenance - The beginning\",\"authors\":\"M. Sanderson, M. Shelton, S. Mulligan\",\"doi\":\"10.1109/IEMT.1993.398201\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The efforts of IBM Austin Industrial Business Center (AIBC) to adopt total productive maintenance (TPM) as the process for improving quality, increasing production and eliminating waste on the pull production lines (PPLs) are described. Over-all equipment effectiveness (OEE) is seen as the measurement for AIBC improvement activities. The initial introductory conversations with management and early pilot measurement activities are described. The data collection tools used and the resulting analysis of the data collected are shown. The initial benchmark activities are described. The authors describe how they obtained the necessary top-down commitment from management by showing the faults of pilot measurements.<<ETX>>\",\"PeriodicalId\":206206,\"journal\":{\"name\":\"Proceedings of 15th IEEE/CHMT International Electronic Manufacturing Technology Symposium\",\"volume\":\"63 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1993-10-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"7\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of 15th IEEE/CHMT International Electronic Manufacturing Technology Symposium\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/IEMT.1993.398201\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of 15th IEEE/CHMT International Electronic Manufacturing Technology Symposium","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IEMT.1993.398201","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7

摘要

介绍了IBM奥斯汀工业业务中心(AIBC)在拉动式生产线(ppl)上采用全面生产维护(TPM)作为提高质量、增加产量和消除浪费的过程所做的努力。整体设备效率(OEE)被视为AIBC改进活动的衡量标准。描述了与管理层和早期试点度量活动的初始介绍性对话。显示了所使用的数据收集工具和所收集数据的结果分析。描述了初始基准测试活动。作者描述了他们如何通过展示试点测量的错误,从管理层获得必要的自上而下的承诺。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
IBM Austin Industrial Business Center total productive maintenance - The beginning
The efforts of IBM Austin Industrial Business Center (AIBC) to adopt total productive maintenance (TPM) as the process for improving quality, increasing production and eliminating waste on the pull production lines (PPLs) are described. Over-all equipment effectiveness (OEE) is seen as the measurement for AIBC improvement activities. The initial introductory conversations with management and early pilot measurement activities are described. The data collection tools used and the resulting analysis of the data collected are shown. The initial benchmark activities are described. The authors describe how they obtained the necessary top-down commitment from management by showing the faults of pilot measurements.<>
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信