{"title":"坎贝尔·杜德·史密斯的方法对76-0001-表单表单机的调度生产有影响","authors":"Widya Spalanzani, Salwiah, Asmuddin","doi":"10.31599/jaringsaintek.v3i2.694","DOIUrl":null,"url":null,"abstract":"\n CEGEONE (CG) is a manufacturing industry company in furniture. It is a supplier company for the Horrison & Gil company. The company manufactures furniture from raw materials into semi-finished goods. The company produces its products on consumer demand (customized order). The overwhelming and varying amount of demand each period was a major problem in the company's production. Hence it takes scheduling. Production scheduling is an important process in production system. In the production process, particularly in the Shop Machine line there is often bottle neck. Under that, researchers did production scheduling at the Shop Machine with the Campbell Dudeck Smith (CDS) method. This method uses Johnson's algorithm that aims to determine the order of the job in order for the earned makespan to be smaller than before. Using production scheduling on shop machines, the company can reduce the total process time to complete the job by 95 minutes or 1 hour 35 minutes. Smaller compared to the previous total makespan of 250 minutes or 4 hours 10 minutes. So that shows total savings in production at 19.79%. The results of the study can be concluded that by using production scheduling on shop machines. \n","PeriodicalId":286819,"journal":{"name":"Jurnal Jaring SainTek","volume":"87 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-10-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Pengaruh Metode Campbell Dudeck Smith dalam Penjadwalan Produksi Table 76-0001-Veneer Mesin Shop PT. Cegeone\",\"authors\":\"Widya Spalanzani, Salwiah, Asmuddin\",\"doi\":\"10.31599/jaringsaintek.v3i2.694\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n CEGEONE (CG) is a manufacturing industry company in furniture. It is a supplier company for the Horrison & Gil company. The company manufactures furniture from raw materials into semi-finished goods. The company produces its products on consumer demand (customized order). The overwhelming and varying amount of demand each period was a major problem in the company's production. Hence it takes scheduling. Production scheduling is an important process in production system. In the production process, particularly in the Shop Machine line there is often bottle neck. Under that, researchers did production scheduling at the Shop Machine with the Campbell Dudeck Smith (CDS) method. This method uses Johnson's algorithm that aims to determine the order of the job in order for the earned makespan to be smaller than before. Using production scheduling on shop machines, the company can reduce the total process time to complete the job by 95 minutes or 1 hour 35 minutes. Smaller compared to the previous total makespan of 250 minutes or 4 hours 10 minutes. So that shows total savings in production at 19.79%. The results of the study can be concluded that by using production scheduling on shop machines. \\n\",\"PeriodicalId\":286819,\"journal\":{\"name\":\"Jurnal Jaring SainTek\",\"volume\":\"87 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-10-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Jaring SainTek\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31599/jaringsaintek.v3i2.694\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Jaring SainTek","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31599/jaringsaintek.v3i2.694","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
CEGEONE (CG)是一家家具制造行业公司。它是Horrison & Gil公司的供应商。这家公司把家具从原材料加工成半成品。公司根据消费者需求(定制订单)生产产品。每个时期的需求势不可挡且数量多变,这是该公司生产的一个主要问题。因此需要调度。生产调度是生产系统中的一个重要环节。在生产过程中,特别是在铺机生产线上往往会出现瓶颈。在此基础上,研究人员采用Campbell Dudeck Smith (CDS)方法对Shop Machine进行生产调度。该方法使用约翰逊算法,该算法旨在确定作业的顺序,以便使挣得的最大完工时间比以前小。在车间机器上使用生产调度,公司可以将完成工作的总工艺时间减少95分钟或1小时35分钟。与之前的总完工时间250分钟或4小时10分钟相比,缩短了。因此,这表明生产的总节省为19.79%。研究的结果可以得出,通过对车间机械的生产调度。
Pengaruh Metode Campbell Dudeck Smith dalam Penjadwalan Produksi Table 76-0001-Veneer Mesin Shop PT. Cegeone
CEGEONE (CG) is a manufacturing industry company in furniture. It is a supplier company for the Horrison & Gil company. The company manufactures furniture from raw materials into semi-finished goods. The company produces its products on consumer demand (customized order). The overwhelming and varying amount of demand each period was a major problem in the company's production. Hence it takes scheduling. Production scheduling is an important process in production system. In the production process, particularly in the Shop Machine line there is often bottle neck. Under that, researchers did production scheduling at the Shop Machine with the Campbell Dudeck Smith (CDS) method. This method uses Johnson's algorithm that aims to determine the order of the job in order for the earned makespan to be smaller than before. Using production scheduling on shop machines, the company can reduce the total process time to complete the job by 95 minutes or 1 hour 35 minutes. Smaller compared to the previous total makespan of 250 minutes or 4 hours 10 minutes. So that shows total savings in production at 19.79%. The results of the study can be concluded that by using production scheduling on shop machines.