建设项目延误的原因和影响

Amílcar Arantes, Pedro Fernandez da Silva, L. Ferreira
{"title":"建设项目延误的原因和影响","authors":"Amílcar Arantes, Pedro Fernandez da Silva, L. Ferreira","doi":"10.1109/IESM.2015.7380293","DOIUrl":null,"url":null,"abstract":"The main aim of this paper is to identify the main causes for the delays in the Portuguese construction industry and its impact, with the purpose of increasing knowledge on the causes and impacts of delays in construction projects. The Relative Importance Index was adopted to classify the importance of the 47 causes and six impacts identified causes of delays. Results show the main causes of delay are slow decision-making, changes to orders, unrealistic timescales and poor contract specifications, financial constraints on the contractor and the type of bidding and contract award process. The main impacts are time and cost overruns and disputes. Factor analysis revealed eight high-level causes that result in 26 of the original causes. Finally, Pearson correlation coefficients were calculated to find the relationship between the extracted factors (latent causes) and impacts, revealing that lack of commitment and substandard contracts are positively correlated with all impacts, and poor consultant performance is negatively correlated with time overrun. These findings are expected to improve the scientific community's knowledge of construction management.","PeriodicalId":308675,"journal":{"name":"2015 International Conference on Industrial Engineering and Systems Management (IESM)","volume":"62 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"28","resultStr":"{\"title\":\"Delays in construction projects - causes and impacts\",\"authors\":\"Amílcar Arantes, Pedro Fernandez da Silva, L. Ferreira\",\"doi\":\"10.1109/IESM.2015.7380293\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The main aim of this paper is to identify the main causes for the delays in the Portuguese construction industry and its impact, with the purpose of increasing knowledge on the causes and impacts of delays in construction projects. The Relative Importance Index was adopted to classify the importance of the 47 causes and six impacts identified causes of delays. Results show the main causes of delay are slow decision-making, changes to orders, unrealistic timescales and poor contract specifications, financial constraints on the contractor and the type of bidding and contract award process. The main impacts are time and cost overruns and disputes. Factor analysis revealed eight high-level causes that result in 26 of the original causes. Finally, Pearson correlation coefficients were calculated to find the relationship between the extracted factors (latent causes) and impacts, revealing that lack of commitment and substandard contracts are positively correlated with all impacts, and poor consultant performance is negatively correlated with time overrun. These findings are expected to improve the scientific community's knowledge of construction management.\",\"PeriodicalId\":308675,\"journal\":{\"name\":\"2015 International Conference on Industrial Engineering and Systems Management (IESM)\",\"volume\":\"62 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-10-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"28\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2015 International Conference on Industrial Engineering and Systems Management (IESM)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/IESM.2015.7380293\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2015 International Conference on Industrial Engineering and Systems Management (IESM)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IESM.2015.7380293","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 28

摘要

本文的主要目的是确定葡萄牙建筑业延误的主要原因及其影响,目的是增加对建筑项目延误的原因和影响的了解。采用相对重要性指数对延误原因的47个原因和确定的6个影响的重要性进行分类。结果表明,延误的主要原因是决策缓慢、订单变更、不切实际的时间表和合同规格不佳、承包商的财务约束以及招标和合同授予过程的类型。主要影响是时间和成本超支以及纠纷。因子分析揭示了导致26个原始原因的8个高级原因。最后,计算Pearson相关系数,找出提取的因素(潜在原因)与影响之间的关系,发现缺乏承诺和不合格合同与所有影响呈正相关,顾问绩效差与超时负相关。这些发现有望提高科学界对施工管理的认识。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Delays in construction projects - causes and impacts
The main aim of this paper is to identify the main causes for the delays in the Portuguese construction industry and its impact, with the purpose of increasing knowledge on the causes and impacts of delays in construction projects. The Relative Importance Index was adopted to classify the importance of the 47 causes and six impacts identified causes of delays. Results show the main causes of delay are slow decision-making, changes to orders, unrealistic timescales and poor contract specifications, financial constraints on the contractor and the type of bidding and contract award process. The main impacts are time and cost overruns and disputes. Factor analysis revealed eight high-level causes that result in 26 of the original causes. Finally, Pearson correlation coefficients were calculated to find the relationship between the extracted factors (latent causes) and impacts, revealing that lack of commitment and substandard contracts are positively correlated with all impacts, and poor consultant performance is negatively correlated with time overrun. These findings are expected to improve the scientific community's knowledge of construction management.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信