澎湖列岛未来大型海上风电场系统影响研究

Wu Yuan-kang, Lee Ching-Ying, Chao Huang-Yu, Chang Ming-Jen
{"title":"澎湖列岛未来大型海上风电场系统影响研究","authors":"Wu Yuan-kang, Lee Ching-Ying, Chao Huang-Yu, Chang Ming-Jen","doi":"10.1109/POWERCON.2010.5666517","DOIUrl":null,"url":null,"abstract":"The Penghu archipelago, located at the Taiwan Straits, offers a great opportunity for developing large-scale offshore wind farm. However, the Penghu system represents a weak-grid characteristic, and the reactive power produced by the 59-km submarine cable connecting Taiwan and Penghu is high, which brings a severe challenge on the wind power integration. Therefore, in the initial planning phase, it is necessary to perform various system impact analyses, including the computations on steady-state power flows, fault currents, and transient stability. In terms of the stability analyses, this paper has focused on the impact of system faults on wind farms, the effects of wind speed fluctuation and wind farm trips on the system. This study utilized PSS/E software as a simulation tool. The results would provide significant references to the Penghu offshore wind farm project.","PeriodicalId":169553,"journal":{"name":"2010 International Conference on Power System Technology","volume":"94 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2010-12-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"System impact study for the future large-scale offshore wind farm around Penghu archipelago\",\"authors\":\"Wu Yuan-kang, Lee Ching-Ying, Chao Huang-Yu, Chang Ming-Jen\",\"doi\":\"10.1109/POWERCON.2010.5666517\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Penghu archipelago, located at the Taiwan Straits, offers a great opportunity for developing large-scale offshore wind farm. However, the Penghu system represents a weak-grid characteristic, and the reactive power produced by the 59-km submarine cable connecting Taiwan and Penghu is high, which brings a severe challenge on the wind power integration. Therefore, in the initial planning phase, it is necessary to perform various system impact analyses, including the computations on steady-state power flows, fault currents, and transient stability. In terms of the stability analyses, this paper has focused on the impact of system faults on wind farms, the effects of wind speed fluctuation and wind farm trips on the system. This study utilized PSS/E software as a simulation tool. The results would provide significant references to the Penghu offshore wind farm project.\",\"PeriodicalId\":169553,\"journal\":{\"name\":\"2010 International Conference on Power System Technology\",\"volume\":\"94 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2010-12-13\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2010 International Conference on Power System Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/POWERCON.2010.5666517\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2010 International Conference on Power System Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/POWERCON.2010.5666517","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

澎湖群岛位于台湾海峡,为发展大型海上风电场提供了绝佳的机会。然而,澎湖系统具有弱电网的特点,连接台湾与澎湖的59公里海底电缆产生的无功功率高,这给风电并网带来了严峻的挑战。因此,在初始规划阶段,有必要进行各种系统影响分析,包括对稳态潮流、故障电流和暂态稳定性的计算。在稳定性分析方面,本文重点研究了系统故障对风电场的影响、风速波动和风电场跳闸对系统的影响。本研究采用PSS/E软件作为仿真工具。研究结果可为澎湖海上风电场项目提供参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
System impact study for the future large-scale offshore wind farm around Penghu archipelago
The Penghu archipelago, located at the Taiwan Straits, offers a great opportunity for developing large-scale offshore wind farm. However, the Penghu system represents a weak-grid characteristic, and the reactive power produced by the 59-km submarine cable connecting Taiwan and Penghu is high, which brings a severe challenge on the wind power integration. Therefore, in the initial planning phase, it is necessary to perform various system impact analyses, including the computations on steady-state power flows, fault currents, and transient stability. In terms of the stability analyses, this paper has focused on the impact of system faults on wind farms, the effects of wind speed fluctuation and wind farm trips on the system. This study utilized PSS/E software as a simulation tool. The results would provide significant references to the Penghu offshore wind farm project.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信