{"title":"主动与被动资源约束项目调度问题:基于缓冲的反应的关键作用","authors":"Morteza Davari, E. Demeulemeester","doi":"10.2139/ssrn.2976350","DOIUrl":null,"url":null,"abstract":"The proactive and reactive resource-constrained project scheduling problem (PR-RCPSP), that has been introduced recently (Davari and Demeulemeester, 2016a), deals with activity duration uncertainty in a very unique way. The optimal solution to an instance of the PR-RCPSP is a proactive and reactive policy (PR-policy) that is a combination of a baseline schedule and a set of required transitions (reactions). In this research, we introduce two interesting classes of reactions, namely the class of selection-based reactions and the class of buffer-based reactions. We also discuss the theoretical relevance of these two classes of reactions. We run some computational results and report the contributions of the selection-based reactions and the buffer-based reactions in the optimal solution. The results suggest that although both selection-based reactions and buffer-based reactions contribute largely in the construction of the optimal PR-policy, the contribution of the buffer-based reactions is of much greater importance.","PeriodicalId":200007,"journal":{"name":"ERN: Statistical Decision Theory; Operations Research (Topic)","volume":"10 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-02-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"The Proactive and Reactive Resource-Constrained Project Scheduling Problem: The Crucial Role of Buffer-Based Reactions\",\"authors\":\"Morteza Davari, E. Demeulemeester\",\"doi\":\"10.2139/ssrn.2976350\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The proactive and reactive resource-constrained project scheduling problem (PR-RCPSP), that has been introduced recently (Davari and Demeulemeester, 2016a), deals with activity duration uncertainty in a very unique way. The optimal solution to an instance of the PR-RCPSP is a proactive and reactive policy (PR-policy) that is a combination of a baseline schedule and a set of required transitions (reactions). In this research, we introduce two interesting classes of reactions, namely the class of selection-based reactions and the class of buffer-based reactions. We also discuss the theoretical relevance of these two classes of reactions. We run some computational results and report the contributions of the selection-based reactions and the buffer-based reactions in the optimal solution. The results suggest that although both selection-based reactions and buffer-based reactions contribute largely in the construction of the optimal PR-policy, the contribution of the buffer-based reactions is of much greater importance.\",\"PeriodicalId\":200007,\"journal\":{\"name\":\"ERN: Statistical Decision Theory; Operations Research (Topic)\",\"volume\":\"10 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-02-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"ERN: Statistical Decision Theory; Operations Research (Topic)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2139/ssrn.2976350\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"ERN: Statistical Decision Theory; Operations Research (Topic)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2139/ssrn.2976350","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
The Proactive and Reactive Resource-Constrained Project Scheduling Problem: The Crucial Role of Buffer-Based Reactions
The proactive and reactive resource-constrained project scheduling problem (PR-RCPSP), that has been introduced recently (Davari and Demeulemeester, 2016a), deals with activity duration uncertainty in a very unique way. The optimal solution to an instance of the PR-RCPSP is a proactive and reactive policy (PR-policy) that is a combination of a baseline schedule and a set of required transitions (reactions). In this research, we introduce two interesting classes of reactions, namely the class of selection-based reactions and the class of buffer-based reactions. We also discuss the theoretical relevance of these two classes of reactions. We run some computational results and report the contributions of the selection-based reactions and the buffer-based reactions in the optimal solution. The results suggest that although both selection-based reactions and buffer-based reactions contribute largely in the construction of the optimal PR-policy, the contribution of the buffer-based reactions is of much greater importance.