安排软件项目,以在给定的人员下最小化开发时间和成本

F. Padberg
{"title":"安排软件项目,以在给定的人员下最小化开发时间和成本","authors":"F. Padberg","doi":"10.1109/APSEC.2001.991476","DOIUrl":null,"url":null,"abstract":"A probabilistic scheduling model for software projects is presented. The model explicitly takes a scheduling strategy as input. When the scheduling strategy is fired, the model outputs a probability distribution for the project completion time or cost. By applying stochastic optimization techniques, schedules for software projects can be computed which minimize the development time or cost with a given staff.","PeriodicalId":130293,"journal":{"name":"Proceedings Eighth Asia-Pacific Software Engineering Conference","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2001-12-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"25","resultStr":"{\"title\":\"Scheduling software projects to minimize the development time and cost with a given staff\",\"authors\":\"F. Padberg\",\"doi\":\"10.1109/APSEC.2001.991476\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A probabilistic scheduling model for software projects is presented. The model explicitly takes a scheduling strategy as input. When the scheduling strategy is fired, the model outputs a probability distribution for the project completion time or cost. By applying stochastic optimization techniques, schedules for software projects can be computed which minimize the development time or cost with a given staff.\",\"PeriodicalId\":130293,\"journal\":{\"name\":\"Proceedings Eighth Asia-Pacific Software Engineering Conference\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2001-12-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"25\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings Eighth Asia-Pacific Software Engineering Conference\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/APSEC.2001.991476\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings Eighth Asia-Pacific Software Engineering Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/APSEC.2001.991476","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 25

摘要

提出了一个软件项目的概率调度模型。该模型显式地将调度策略作为输入。当调度策略启动时,模型输出项目完成时间或成本的概率分布。通过应用随机优化技术,可以计算出软件项目的时间表,从而使给定人员的开发时间或成本最小化。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Scheduling software projects to minimize the development time and cost with a given staff
A probabilistic scheduling model for software projects is presented. The model explicitly takes a scheduling strategy as input. When the scheduling strategy is fired, the model outputs a probability distribution for the project completion time or cost. By applying stochastic optimization techniques, schedules for software projects can be computed which minimize the development time or cost with a given staff.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信