{"title":"基于风险的输变电规划应急分析","authors":"Sung-Hwan Song, Sang-ho Lee, T. Oh, Jinsu Lee","doi":"10.1109/TD-ASIA.2009.5356815","DOIUrl":null,"url":null,"abstract":"This paper examines the scheme of risk-based contingency analysis for transmission and substation planning. Compared to the traditional approach, in which system reliability is assessed by deterministic ‘n−1’ contingency criteria, the present method can capture the 'risk' concepts consisting of two parameters; 1) the likelihood that some events will happen and 2) the consequences if they do. The key method of this paper is to evaluate the risk considering the event probability such as two transmission lines failure and substation failure, and event consequences such as the amount of load shedding. The presented risk evaluation procedure can provide a single dimension index like 'probability−1 × consequence' representing a contingency severity level. Furthermore it can be a vehicle to perform the probabilistic contingency analysis for transmission and substation planning.","PeriodicalId":131589,"journal":{"name":"2009 Transmission & Distribution Conference & Exposition: Asia and Pacific","volume":"122 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-12-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"11","resultStr":"{\"title\":\"Risk-based contingency analysis for transmission and substation planning\",\"authors\":\"Sung-Hwan Song, Sang-ho Lee, T. Oh, Jinsu Lee\",\"doi\":\"10.1109/TD-ASIA.2009.5356815\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper examines the scheme of risk-based contingency analysis for transmission and substation planning. Compared to the traditional approach, in which system reliability is assessed by deterministic ‘n−1’ contingency criteria, the present method can capture the 'risk' concepts consisting of two parameters; 1) the likelihood that some events will happen and 2) the consequences if they do. The key method of this paper is to evaluate the risk considering the event probability such as two transmission lines failure and substation failure, and event consequences such as the amount of load shedding. The presented risk evaluation procedure can provide a single dimension index like 'probability−1 × consequence' representing a contingency severity level. Furthermore it can be a vehicle to perform the probabilistic contingency analysis for transmission and substation planning.\",\"PeriodicalId\":131589,\"journal\":{\"name\":\"2009 Transmission & Distribution Conference & Exposition: Asia and Pacific\",\"volume\":\"122 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2009-12-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"11\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2009 Transmission & Distribution Conference & Exposition: Asia and Pacific\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/TD-ASIA.2009.5356815\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 Transmission & Distribution Conference & Exposition: Asia and Pacific","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TD-ASIA.2009.5356815","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 11

摘要

本文研究了基于风险的输变电规划应急分析方案。与传统方法相比,该方法采用确定性的“n−1”偶然性准则评估系统可靠性,该方法可以捕获由两个参数组成的“风险”概念;1)某些事件发生的可能性,2)如果发生了后果。本文的关键方法是综合考虑两条输电线路故障、变电站故障等事件概率和减载量等事件后果进行风险评估。所提出的风险评估程序可以提供一个单一维度的指标,如“概率- 1 ×后果”,表示一个突发事件的严重程度。此外,它还可以作为执行输电和变电站规划的概率偶然性分析的工具。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Risk-based contingency analysis for transmission and substation planning
This paper examines the scheme of risk-based contingency analysis for transmission and substation planning. Compared to the traditional approach, in which system reliability is assessed by deterministic ‘n−1’ contingency criteria, the present method can capture the 'risk' concepts consisting of two parameters; 1) the likelihood that some events will happen and 2) the consequences if they do. The key method of this paper is to evaluate the risk considering the event probability such as two transmission lines failure and substation failure, and event consequences such as the amount of load shedding. The presented risk evaluation procedure can provide a single dimension index like 'probability−1 × consequence' representing a contingency severity level. Furthermore it can be a vehicle to perform the probabilistic contingency analysis for transmission and substation planning.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信